Subcontracting Process in SAP
Subcontracting Process in SAP
For example, one company that manufactured batteries needed specialized printing services
which were outsourced to subcontractors. Plastic boxes were provided to subcontractors and they
did required printing on these boxes. Later, the subcontractors returned the boxes back to the
client. The subcontractors charged the company for their services rendered per box.
Another example of the subcontracting process in SAP is when a company provided raw sims and
packaging materials to a subcontractor. The subcontractor converted the raw sims into finished
sims well packed and returned finished product back to the company. They charged the company
for their services rendered.
Let’s start with discussing the steps that are involved in the subcontracting process in SAP. They
are summarized below:
You order the end product using a subcontract order. The components that the vendor needs to
manufacture the end product are specified in the subcontract order.
The components are posted to the stock of materials provided to the vendor. The components are then
supplied to the vendor.
The vendor performs its service and delivers the ordered material (the end product). The consumption of
the components is posted.
If, after the goods receipt has been posted, the vendor informs you that a larger or smaller quantity of
the components was actually consumed than planned in the purchase order, you must make an
adjustment.
The vendor charges for his or her service. The invoice is posted.
Diagra
m of Subcontracting Process in SAP
Prerequisites
A material BOM needs to be created before any subcontracting order can be placed. The bill of
materials (BOM) is a formally structured list of the components that make up a product. The list
contains the object number of each component, together with the quantity and unit of measure.
Subcontracting Requisition
The subcontracting requisition lists the finished material that is to be procured in a subcontract
item. Against each subcontracted item the system copies the material components that are to be
provided to the vendor from the bill of material (BOM). The bill of material refers to the end product
that the vendor will deliver.
The requisition for subcontracting must contain the item category ‘L’ which is used for
subcontracting in the SAP system.
Subcontracting materials are sent to vendors for processing finished products. A subcontracting
purchase order is placed by converting the subcontracting requisition into a purchase order. The
system will generate a purchase order number internally.
The rates quoted by the vendor for labour charges are mentioned in the purchase order line items.
If a purchase info record has been maintained, the service charges are defaulted into the
purchase order.
To receive material against the purchase order, SIM cards and packaging materials need to be
issued to the subcontractor. The materials that are provided to the subcontractor are managed as
stock provided to a vendor. The provision is a transfer posting from the unrestricted use stock to
the stock of material provided to a vendor.
The SIM cards supplier will be instructed to deliver the raw material at the subcontractor’s
premises. When the subcontractor receives the raw SIM cards at his premises, he will inform the
client and a goods receipt will be posted with reference to the purchase order increasing the
subcontractor stock in the system. If the material is already available in the client own stock, it will
be issued from the unrestricted use stock to the vendor. The SIM cards will be issued with
reference to the subcontract purchase order.
When the vendor delivers the ordered packaged SIM cards (the end product), the goods will be
received against the finished product with reference to the purchase order.
At the time of receipt, the raw materials for each order item will be determined and the system will
create a goods issue accounting entry item for each raw material. As a result, the material
document will consists of the following items:
Goods receipt items for the packaged SIM cards (end product) supplied by the vendor.
Goods issue items for the SIM cards (components).
The goods receipt will be valuated at the subcontract price plus the value of the SIM cards
consumed.
Subcontracting Invoice
Invoices will be entered in the system against the purchase order. The vendor will be billed only for
items delivered. At the time of invoice receipt a liability is created against the vendor. The liability
created will only be of the amount charged by the vendor for processing and does not include the
material component value.
Create
a Subcontracting Purchase Order – Select a Document Type and Provide a Vendor
In the Item Overview screen, you need to use Item Category ‘L’ which is used for subcontracting
documents. Also, you need to provide Material, Quantity, Delivery Date, Plant, and Price.
Enter
Information about Items of Subcontracting Order
Now, click Explode BOM button to open the below screen, where you provide your
components to the subcontractor.
Compo
nents of Subcontracted Product
If there are any additional charges required, you input them in the Conditions tab as shown on the
screenshot below. Finally, you save the subcontracting purchase order.
Pricing
Conditions in a Subcontracting Purchase Order
In the Item Overview Screen, you need to provide Material, Quantity, Plant, and Storage Location.
If the material is managed with batches, a batch number will be shown as well.
Item
Overview Screen of Transfer Posting
It will open the screenshot shown below. Here in the highlighted box you provide the number of
your subcontractor.
Next, click on Check button to check whether the document is OK. Finally, click on Post button to
post the document.
Goods
Receipt in Transaction MIGO
Now, press to display the components provided to the subcontractor for the finished
material as shown on the screenshots below.
Next, click OK checkboxes as shown below. The first line corresponds to the goods receipt of the
final product, whereas the second two lines correspond to the issue of components which you
provided to the subcontractor earlier. The good receipt and the goods issue will be done
simultaneously by the SAP system.
Click OK Checkboxes
Now, let’s display the document that we have just created. It can also be done through
via MIGO transaction. Start it and select Display against Material Document while inputting
the document number as shown below and click Enter.
Please note the movement types used: 101 for Goods Receipt and 543 for Issue of Components.
Items
of Material Document
It is also possible to see accounting documents that were automatically generated by the SAP
system during posting of material movements. To do it, click on Doc. Info button.
Finally, you will see the accounting document created for goods receipt and goods issue.
SAP FI
Document Corresponding to Transfer Posting
The next step of subcontracting process in SAP is to do posting of invoice receipt against the
purchase order using the transaction MIRO.
MIRO Transaction:
Enter Details and Amount
Click on Simulate button which will notify you of any errors. If none, a green light will turn on
near Balancefield and the SAP system will show you accounting document which will be created.
Click
Simulate Button
The
Results of Simulation of Invoice Posting