Bill of Quantities: Division 2: Site Work
Bill of Quantities: Division 2: Site Work
Earthfill P 75,000
Hauling P 15,000
Excavation P 25,000
SUBTOTAL P 130,000
B DIVISION 3: CONCRETE
B.1 COLUMN FOOTINGS, COLUMNS AND GRADE BEAM
Cement 30 bags 237 /per bag P 7,110.00
Sand 15 cu.m. 200 per cu.m. 3,000.00
Gravel 32 cu.m. 400 per cu.m. 12,800.00