Chapter 7 - Budgeting - Estimating Cost and Risks
Chapter 7 - Budgeting - Estimating Cost and Risks
(HAND-OUTS)
The objectives of this chapter are to:
Top-down Budgeting
- This strategy is based on collecting the judgements and experiences of top and middle
managers, and available past data concerning similar activities. These managers estimate overall
project cost as well as the costs of the major subprojects that comprise it. These cost estimates are
then given to lower-level managers, who are expected to continue the breakdown into budget
estimates for the specific tasks and work packages the comprise the subprojects. This process
continues to the lowest level.
Bottom-Up Budgeting
- In this method, elemental tasks, their schedules, and their individual budgets are constructed.
-The advantages of the bottom-up process are those generally associated with participative
management.
-While top down budgeting is common, true bottom-ups are rare.
Suppose a work element is estimated to require 25 hours of labor by technician. The specific
technician assigned to this job is paid $17.50/hr. Overhead charges to the project are 84 percent
of direct labor charges.
25 hr x $17.50 x 1.84 = $805.00
but the accuracy of this calculation depends on the precise assumptions behind the 25-hr
estimate.
A typical allowance for personal time is 12 percent of total work time. If personal time was not
included in the 25-hr estimate made above, then the cost calculation becomes
1.12 x 25hr x $17.50 x 1.84 = $901.60
The uncertainty in labor cost estimating lies in the estimate of hours to be expended. Not
including personal time ensures an underestimate.
There are two types of estimation error. First, there is random error in which overestimates and
underestimates are equally likely. These are errors that tend to cancel each other. If we sum these
errors over many estimates, their sum will approach zero. Second, there is bias, which is systematic
error. For biased estimates, the chance of over- and underestimates are not equally likely, and their
sum, either positive or negative, will increase as the number of estimates increases.
- California’s 2600-mile long system of levees east of San Francisco is arguably the most
worrisome infrastructure risk in America – called a “ticking time bomb” by some – whose
failures would top the economic cost of Katrina.
- Simulation combined with the sensitivity analysis is also useful for evaluating projects while they
are still in conceptual stage.
- These individual estimated changes in production cost and time, together with upstream and
downstream time and cost changes that might also result are used to generate the required cash
flow information – presuming that the time savings have been properly costed.
PsychoCeramic Science Revisited
1. Click on the cell F17 to identify it as containing an outcome that interests us.
2. Select the menu option Define Forecast near the left end of the tool bar.
3. CB’s Define Forecast dialog box is now displayed as shown in Figure 7-9. In the Forecast Name:
textbox, enter a descriptive name such as Net Present Value of Project. Then enter a descriptive label such
as Dollars in the Units: textbox.
4. Click OK. There is only one Forecast cell in this example, but there are several. Use the same five steps
for each.
5. Before leaving the Define Forecast, there is some additional work that will be helpful. There are
several views of the output of the simulation. Click on the View (double arrow at right) button to choose.
You may also control the precision of the output data, you can filter it if you wish, and you can decide
what information about the results you would like to examine. The latter choice is made by clicking Auto
Extract. Put a check in the “Extract forecast….” box and then check as many statistical output as you
wish. Be sure to make an entry in the :Starting Cell” box and choose any entry outside of the bounds of