0% found this document useful (0 votes)
246 views

Government Polytechnic Bramhapuri Dist Chandrapur

The document is a report on specifications for plain cement concrete (PCC) submitted by Nikhil Vinod Tembhurne, a civil engineering student at Government Polytechnic Bramhapuri. It includes an introduction to PCC, objectives and importance of specifications. The report was completed under the guidance of Pranjay Sahare and certifies that Nikhil conducted the study and prepared the report to fulfill requirements for a diploma in civil engineering.

Uploaded by

Fake Account
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
246 views

Government Polytechnic Bramhapuri Dist Chandrapur

The document is a report on specifications for plain cement concrete (PCC) submitted by Nikhil Vinod Tembhurne, a civil engineering student at Government Polytechnic Bramhapuri. It includes an introduction to PCC, objectives and importance of specifications. The report was completed under the guidance of Pranjay Sahare and certifies that Nikhil conducted the study and prepared the report to fulfill requirements for a diploma in civil engineering.

Uploaded by

Fake Account
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 18

GOVERNMENT POLYTECHNIC BRAMHAPURI

DIST CHANDRAPUR

I am , the student of 6th sem of department of civil


Engineering, completed this micro project work for time to time as
described in this report by my own skill and study between the
period from 2021-2022

As per instruction and guidance of PRANJAY SAHARE and


following student is associated for this work However, Quantum of
my contribution has been approved
By the guide…

NIKHIL VINOD TEMBHURNE-45

Enrollment No. -1901210143

Date:- / / Place:-Bramhapuri

GOVERNMENT POLYTECHNIC BRAMHAPURI


GOVERNMENT POLYTECHNIC BRAMHAPURI
DIST CHANDRAPUR
DEPARTMENT OF CIVIL ENGINEERING

CERTIFICATE
This is to certify that the following student of this institute have
carried out this micro project work on TO PREAPARE A REPORT
ON SPECIFICATIONS OF PCC under the guidance of PRANJAY
SAHARE in the department civil Engineering during the session
2021-2022. This work has been done in the partial fulfillment of the
award for Civil Engineering from MSBTE…

SUBMITTED BY:- NIKHIL VINOD TEMBHURNE

PROJECT GUIDE:- PRANJAY SAHARE

Dr. D. K. PARBAT DR. D. N. SHINGADE


Head of department Principal
Civil Engg. Dept. Govt. poly. Bramhapuri
A MICRO PROJECT ON
TO PREAPARE A REPORT ON SPECIFICATIONS OF PCC
Submitted2021-2022Submitted2021-2

SUBMITTED FOR 2021- 2022

This micro project work submitted in partial fulfillment


of requirement for the award of Diploma in

CIVIL ENGINEERING
Under the guidance of
PRANJAY SAHARE

(Lecturer in Civil Engineering Department)


By

1) NIKHIL VINOD TEMBHURNE

GOVERNEMNT POLYTECHINIC BRAMHPURI


INDEX

Sr. No. Content Page.


No.
1. Introduction
2. Proposal Part- A
i. Aim / benefit of project

ii. Course outcome addressed

iii. Proposed methodology

iv. Action plan

v. Resources required

vi. Name of team members


3. Proposal Part- B
i. Rationale

ii. Aim of micro project

iii. Course outcome

iv. Literature review

v. Actual methodology followed

vi. Actual resources used

vii. Output of the micro project

viii. Skilled developed/ learning outcomes

ix. Application of the micro project


INTRODUCTION

A Contract document specifying the quality of material to be used


and procedure and method of workmanship to be adopted in the
construction work is called as specifications.

Importance of specifications
a) Specification shows the method of doing wok and act as a guide
to the supervising staff.
b) The cost of unit quantity of work is known by its specifications
c) Work should be carried out according to the specifications
mentioned in contract, otherwise contractor will not get
payment. Hence contractor is only paid according to the
specifications.
d) Tender document without specifications is considered an
incomplete and invalid.
e) Any change in specifications changes the rate mentioned in the
tender paper.

Purpose of specifications
1. It helps to the contractor and pricing the tender.
2. Specifications fixes the responsibilities of owner and contractor
3. Specification is an important tool or document and plays the
important role for arbitration.
4. It helps to prepare rate analysis of various item.
5. Specifications are the witness document and hence useful in
court to settle the disputes…
PART-A
MICRO PROJECT PRAPOSAL
TO PREAPARE A REPORT ON SPECIFICATIONS OF PCC

1. AIM 0F THE MICRO PROJECT

To Preapare A Report On Specifications Of PCC

2. COURSE OUTCOME ADDRESS


e) Prepare the detailed specification for various items of construction

3. PRAPOSED METHEDOLOGY

1. Select the micro project topic


2. To discuss about project with respective guide.
3. To take guidelines from respective guide.
4. To prepare a project proposal as per instructions.
5. Making literature review among topic
6. To do literature survey
7. To prepare project report
8. Submission of report to respective guide.
4. ACTION PLAN

SR. Details of activity Plans Plans end Name of


NO. start date date responsible
student
1 Selection of topic and 11/03/202 14/03/2022 NIKHIL VINOD
discussion with teacher 2 TEMBHURNE
2 Searching info. From 15/03/202 24/03/2022 NIKHIL VINOD
reference book 2 TEMBHURNE
3 Collection of 25/03/202 03/04/2022 NIKHIL VINOD
information and making 2 TEMBHURNE
report on it
4 Completion and approval 4/4/2022 7/04/2022 NIKHIL VINOD
and submission of micro TEMBHURNE
project

5. RESOURCES REQUIRED

SR. NAME OF SPECIFICATIONS QUANTITY REMARKS


NO. RESOURCES
1. REFERENCE Construction 1 Reading
BOOK management and
contract practices
2. LAPTOP To edit info and 1 ----
AND print the report
PRINTER

6. NAME OF MEMBER WITH THEIR ROLL. NO.


NAME ROLL NO.

NIKHIL VINOD TEMBHURNE 45


PART-B
MICRO PROJECT PRAPOSAL

TO PREAPARE A REPORT ON SPECIFICATIONS OF PCC

1. RATIONALE
Concrete has been used for many wonderful things throughout
history, for either architecture or for infrastructure work and more.
The term PCC stands for plain cement concrete, the mixture of
cement, fine aggregate and coarse aggregate are generally called plain
cement concrete, before starting any R.C. core masonry work directly
on the excavated soil, PCC is done to form levelled surface and to
avoid laying concrete on soil directly so as to avoid mixing/with soil
and also to prevent soil extracting water from PCC thereby weakening
it.

2. COURSE OUTCOME INTEGRATED


e. Prepare the specification for various items of construction

3 . LITERATURE REVIEW

Li. Et. Al. (2004)

The object of plain cement concrete alias PCC is to arrange a firm


impermeable bed to RCC in the foundation where the soil is soft and
flexible. It is mostly applied over brick flat soiling or devoid of brick flat
soiling, it is also known as cement concrete (CC) OR binding concrete.
When any reinforcement is not used inside the concrete, it is defined as the
plain cement concrete. It just a blend of concrete ingredients
4. ACTUAL METHEDOLOGY FOLLOWED

1. Selected the micro project topic


2. Discussed about project with respective guide.
3. Took guide lines from respective guide.
4. Prepared a project proposal as per instructions.
5. Made literature review among topic
6. Done the literature survey
7. Prepared project report
8. Submitted the report to respective guide.

5. ACTUAL RESOURCESUSED

Sr. No. Name of Specifications Remarks


Resources
1. Referen Emerging Reading
ce Book trends in civil
engineering
2. Laptop To edit info. And to ---
And print the report
printer
6. OUTPUT OF THE MICROPROJECT

PLAIN CEMENT CONCRETE

Plain cement concrete is the mixture of cement, fine aggregate and


coarse aggregate without steel, PCC is an important component of a
building which is laid on the soil surface to avoid direct contact of
reinforcement of concrete with soil and water

MATERIALS USED IN PCC ARE:-

1. Coarse aggregate
a) Coarse aggregate shall be from hard broken stone of compact
besalt or granite or similar stone and shall be free from dust,
dirt, oil and other foreign matters
b) Size of stone shall be 20 mm and down and all sizes of stones
shall be retained in a 5 mm square mesh and well graded, shall
not gave voids more than 42%

2. Fine aggregate
a) Fine aggregate shall have coarse sand consisting of hard, sharp
and angular grains
b) These aggregates shall pass through sieve of 5mm square
mesh.
c) Sand shall be as per the standard specification
d) Sand shall be clean and free from dust, dirt, oil and other
organic matter
e) Sea sand shall not be used
f) Crushed stones sand can also be used if specified…
3. Cement
a) Cement shall be fresh, not old, and as per the Indian standards
Specification and shall have required compressive strength and
Fineness.
b) Portland pozzolona cement is normally used for plain cement
Concrete, it should be confirm to the specifications and shall have the
Required tensile and compressive stress and fines.

4. Water
a) Water used shall be clean and reasonably free from injurious
quantities of deleterious materials such as oils, acids, alkalis, salts
and vegetable growth.
b) Generally, potable water shall be used having a pH value not less
than 6. The maximum permissible limits for solids shall be as per IS
456:2000 Clause 5.4, Page No 15.

Proportioning of Plain Cement Concrete

1. The proportioning is done based on the requirement or given


specification. Generally 1:2:4 or 1:3:6 mix is used.
2. The measurement of material can be done by weight batching or volume
batching.
3. In volume batching, coarse aggregate and sand shall be measured by
measuring box of 30cmx30cmx38cm of a suitable size equivalent to one
bag cement of 1/30 m3or 0.035 m3.
4. Sand shall be measured on the basis of its dry volume.
5. While measuring the aggregate, sacking, ramming or hammering shall
not be done.
Mixing of Plain Cement Concrete

Mixing of PCC can be done either manually or by the means of machines

Hand Mixing
1. PCC is allowed to be done by hand-mixing only for small-scale works.
2. The base on which the concrete is mixed must be clean, watertight slab or a
steel platform.
3. For concrete of 1:2:4 / 1:4:8 proportions, one bag of cement , first two boxes
of mixed dry thoroughly making the material turning up and down by spade
or phawrah and then this homogenous dry mix shall be placed over a spread
stack of 4 boxes of coarse aggregate and the complete mix dry turn up and
down with phawrah or spade at least three times so as to obtain uniform
mix.
4. Then water shall be added to slowly and gradually and then turning the mix
up and down at least three times by spade till to obtain mix of the required
workability and water cement ratio

Machine Mixing

1.Cement, sand and coarse aggregate shall be taken into the machine mixer in
required proportion.
2. For concrete of proportion 1:2:4 consist of one bag of cement, two boxes of
sand and four boxes of coarse aggregate shall be taken into mixer.

3. The machine shall then be operated to mix material dry & then water shall
be added gradually with required quantity 25 to 30 liters of water per bag of
cement to obtain the desired water-cement ratio.

4. The mixing should have homogeneous mass or plastic mix of uniform


colour so as to obtain thorough mixing. 1 to 2 minutes rotation shall be given
to the drum mixer.

Mixed concrete shall be discharge on a masonry platform or on a flat iron


sheet.
Form work

1. Form work and centering shall be used as per the standard


specifications

2. Internal surface of formwork shall be applied by oil so as to avoid


sticking of concrete during removal of the formwork.

3. The base of formwork shall be watered before laying the concrete


on it.

4. Forms at the bottom surface in case of beam and slab shall not be
removed before 14 days in general and sides of form shall be
removed after 3 days.

5. Form work shall be removed slowly and with care and not to
disturb and damage the concrete.

Slump test

1. Regular slump test shall be carried out so as to check the


workability of concrete mix and to control the addition of water.

2. For building work, a slump of 75 mm to 100 mm may be permitted


and for road work, 30 mm to 40 mm may be allowed.
Laying of Plain Cement Concrete

1. Concrete shall be laid gently in layers not exceeding 150 mm and


compacted with rods & tamping with wooden tampers or with
mechanical vibrating machine until a dense concrete is obtained.

2. Immersion type vibrators or needle vibrators shall be used for thick


concrete or mass concrete. Surface vibrators or form vibrators shall
be used for thin concrete. There shall not be over vibration.

3. Concrete shall be laid continuously. If laying of concrete is


suspended for rest or on next day the end of concrete shall be slope
with an angle of 30° and its surface shall be made rough for proper
joining.

4. If the concreting work is resumed, the previous sloped portion shall


be made rough, clean, watered and a grout of neat cement shall be
applied and fresh concrete shall be laid in successive layer in such
way that the upper layer shall be laid before the lower layer is set.
Curing of Plain Cement Concrete
9.1. Role:
1. Freshly laidofconcrete
The role shallResource
the Human be protected from rain
Department is by suitable
to create the climate
covering. in which management throughout the Bank will be enabled
& conditions
to optimize the individual & collective Contribution of all employees to
2.After
the shortthe concrete has
& long-term begunoftothe
success harden-
Bank..that is about one to two
hours after it has been laid- it shall be protected with moist gunny
2.bags, sand or any other materials against quick drying.
Responsibilities:
3After
1) To24
behours of layingsponsor
the principal of concrete, the surface
& ―guardian of shall be cured
HR policies inby
the
flooding with
Bank. water of about 25mm depth or by covering with weight
absorbent materials.
2) To propose
4.Curing shall be&done
obtain
for agreement
a minimumonperiod
changes to days.
of 14 these policies from
time to time & to ensure that policies which have been agreed are
being implemented throughout the Bank.

3) To contribute fully to the task of meeting the business challenges


which the bank has to face by supporting Branch/Unit Managers in
continuously developing the potential of employees & in creating
conditions in which all the employees are motivated to meet the
objectives of the Bank.

4) To continuously monitor the Bank‘s strategies to ensure that HR


policies are appropriate & that employee numbers & skills are fully
supportive of such strategies.

5) To deliver a full range of personnel services in support of line


management. These services include manpower planning,
recruitment/transfer, remuneration, and training & employee
welfare.
7. Skilled developed / learning outcome of this micro project
1) We are able to learn the aspects of Specification of PCC

8. Applications of this micro project

1) This micro project helps to learn the plain cement concrete

2) This micro project helps to learn the material used in PCC.

3) This micro project helps to learn the methods of mixing of PCC

4) This micro project helps to learn The Laying of PCC.

5) This micro project helps to learn proportions in PCC

6) This micro project helps to learn Curing of PCC.


Teacher Evaluation sheet
Name of student: Nikhil vinod Tembhurne Enrollment No. 1901210143

Name of programme :- Civil engineering Semester – Sixth

Course title :- Contract and accounts Code :- 22601

Name of micro project :- To Prepare a report on specifications of PCC..

Roll. No. 45
Course outcome achieved :- e. Prepare the detailed specification for various items of construction

Evaluation as per suggested Rubric for assessment of micro project

Sr. no. Characteristic to be Poor Averag Good Excellen Total


assessed [1-3] e [6-8] t [10]
[4-5] [8-10]
1 Relevance in the course

2 Literature survey

3 Project proposal

4 Completion of target

5 Analysis of data

6 Quality of prototype
5 Quality of prototype

6 Report presentation
Micro project Evaluation sheet
Process assessment product assessment
`
Total
marks
Part A – Project Part B – Project Individual (10)
Project methodology report/ working presentation /
proposal ( 2 marks) model viva
( 2 marks) ( 2 marks) ( 4 marks)

Comments/ suggestions about team work / leadership / interpersonal


communications

…………………………………………………………………………………

…………………………………………………………………………………

Any other comment

…………………………………………………………………………………

…………………………………………………………………………………

…………………………………………………………………………………

Name and designation of the faculty member

……………………………………………………………………………..

Signature ………………………………………………………………….

You might also like