KERAJAAN MALAYSIA
JABATAN KERJA RAYA MALAYSIA
STANDARD SPECIFICATION
FOR ROAD WORKS
Section 10: Piling Works
Pr
CAWANGAN KEJURLITERAAN JALAN DAN GEOTEKNIK KETIA PENGARAH KFRIA RAYA
JKR) __ |BUPEJABAT JABATAN KERJA RAYA, JABATAN KERJA RAYA MALAYSIA,
Se J JALAN RAJA LAUT, 50582 KUALA LUMPUR.
60350 KUALA LUMPUR,FOREWORD
As practices in road construction change over time, it is imperative for Jabatan Kerja Raya (JKR) to
continuously update and improve their standard specifications. These new specifications are nol
only aimed at keeping abreast with current technologies but also helping in improving the quality of
constructed product. In unison, these new specifications have a significant positive impact on the
construction industry especially with the corporation ot new products and technologies.
Standard Specification for Road Works is an essential component in the road infrastructure
construction industry. This specification provides an improved guidance in the material selection
and the production of good quality workmanship and products, based on current best practices. The
purpose of this standard specification is to establish uniformity in road works to be used by road
designers, road authorities, manufacturers and suppliers of road related products.
This document “Standard Specification for Road Works - Section 10: Piling Works” is a part of a
seties of improved specifications in the Standard Specification for Road Wotks. The vompilation of
this document was carried ont through many discussions hy the technical committee members
Additionally it has been reviewed by a group of independent consultants and presented at a
technical workshop held on 16" July 2008. Feedbacks and comments received were carefully
considered and incorporated in the specification where appropriate,
This Specification also had heen presented in Mesyuarat Ketua Sektor (MKS) JKR on
2 September 2010 and Mesyuarat Pengarah JKR Malaysia Bil 3/2011 on 15" August 2011ACKNOWLEDGEMENT
‘This Standard Specification for Road Works - Section 10: Piling Works has been prepared by a
technical committee consisting of engineers from Cawangan Kejuruteraan Awam, Struktur dan
Jambatan (CKASJ), Cawangan Jalan & Geoteknik (CKJG), Cawangan Jalan (C1) and Cawangan
Pengurusan Projek Kompleks (CPPK). The members of the committee involved in preparing this
Standard Specification for Road Works - Section 10: Piling Works are:-
Committee Members
Dato’ Ir. Dr Ismail bin Mohamed Talb (Chairman until April 2009) CKASI
Ir, Abd Rahman bin Salleh (Chairman from Aprit 2009) CKASI
En, Wan Sohaimi bin Wan Mohamed CKASI
Hj. Sulaiman bin Md. Ali a
Pn. Khairiah bt Moh Tai, a
En.Lee Choon Siang CKASI
Ir, Fairul Zatti bin Mohd Abas (until June 2009) crPK
Ir, Amir Hamzah bin Mustapha (until July 2007) cKIG
‘The Committee would also like to thank other JKR personnel and individuals who have assisted and
contributed towards the successful completioa of this specification,10.1
10.2
103
10.4
JKRISPJ/2010-810
SECTION 10-PILING WORKS
DESCRIPTION
GENERAL REQUIREMENT AND TOLERANCES:
10.2.1 Setting Out
10.2.2 Position
10.23 Verticality
10.24 Rake
10.25 Forcible Corrections
10.2.6 Piles Out of Alignment or Position
10.2.7 Records
10.2.8 Soil Investigation Report
10.2.9 Unexpected Ground Conditions
10.2.10 Adjacent Structures
10.2.11 Existing Services
10.2.12 Method Statement for Construcion Operation
10.2.13 Alternative Piling System by Contractor
10.214 As-Built Location
PRECAST REINFORCED CONCRETE PILES.
103.1 Description
10.3.2. Materials
103.2.1 Concrete
103.22 Reinforcement
103.23 Pile Shoes
10.3.3 Manufacture and Storage of Precast Reinforced Conercte Piles
1033.1 Casting
1033.2 Handling and Storage
10.3.4 Installation of Precast Reinforced Concrete Piles,
103.4. Pitching of Piles
103.42 Driving of Piles
103.43 Preboring and Jetting of Piles
103.44 Repair of Damage Pile Heads
103.45 Lengthening of Piles
10.3.4.6 Pile Joint
1034.7 Pile Bending Strength Test
103.48 Cutting and Preparation of Pile Heads
PRESTRESSED SPUN CONCRETE PILES
10.4.1 Description
10.4.2 Materials
10.4.2.1 Conerete
10.4.2.2 Reinforcement
104.23 Transfer of Prestress
10.424 End Plates
10.4.2.5 Pile Shoes
10.4.3 Manufacture and Storage of Prestressed Spun Concrete Piles
1043.1 Casting
1043.2 Handling and Storage
S10-i
PAGE
10-1
S101
s10-1
$10-1
S10-1
10-1
10-1
$102
10-2
810-2
10-2
10-3
10-3
810-3
10-4
10-5
s10-s
s10-s
10-5
10-5
10-5
$10-5
810-6
$10-6
$10-6
10-7
10-7
310-7
S10-8
10-9
10-9
10-10
10-10
810-10
10-11
810-11
810-11
10-11
10-11
10-11
S10-11
10-11
810-12
10-12
10-1210.5
106
JKRISPJ/2010-810
10.4.4 Installation of Prestressed Spun Concrete Piles
1044.1 Pitching and Driving of Piles
104.42 Lengthening of Piles
9443 Cotting and Preparation of Pile Heads
BORED CAST-IN-PLACE PILES
10.5.1 Description
10.5.2. Materials
10.5.2.1 Conerete and Reinforcement
10.5.2.2 Permanent Casings
105.23 Support Fluid
10.5.3 Boring Operations
1053.1 Diameter of Piles
10.5.3.2 Boring
Drilling In Rock
‘Temporary Casings
Stability of Piling Excavations Using Support Fluid
Spillage and Disposal
Pumping of Boreholes
Continuity of Construction
Enlarged Pile Bases
Cleanliness of Pile Bases
10.53.11 Inspection
10.5.4 Placing of Reinforcement
10.5.4.1 Joints in Longitudinal Bars
1054.2 Positions of Reinforcement
10.5.5 Conereting Operations
10.5.5.1 Placing Concrete
10.5.5.2 Workability of Concrete
10.5.5.3 Compaction
105.54 Placing Concrete in Dry Borings
105.55 Placing Conerete Under Water or Support Fluid
10.5.6 Extraction of Casing
10.5.6.1 Workability of Concrete
105.62 Concrete Level
105.63 Vibrating Fxtractors
10.5.7 Construction of Pile Heads
1057.1 Water Levels
105.72 Cutting and Preparation of Pile Heads
105.73 ‘Temporary Rackfilling Above Pile Casting Level
105.74 Piling Records
10.5.8 Pressure Grouting of Piles
STEEL H-SECTION PILES
10.6.1 Description
10.6.2 Materials
10.6.3 Manufacture and Storage of Steel H-Section Piles
10.6.3.1 Manufacturing Tolerances
10.6.3.2 Straightneas of Sections
10.6.3.3 Strengthening of Piles
10.6.3.4 Marking of Piles
810
PAGE
$10-12
$10-12
10-12
810-13,
810-13
810-13
810-13
$10-13
$10 13
810-13
810-14
S10-14
$10-14
810-14
sl0-14
810-15
810-15
810-15
10-15
810-16
810-16
10-16
S10-16
$10-16
S10-16
$10-17
$10-17
$10-17
810-17
810-17
810-17
810-18
$10-18
810-18
S10-18
810-19
$10-19
810-19
10-19
810-19
810-20
810-20
10-20
$10-20
810-20
810-20
810 20
$10-21
10-2110.7
19.8
1063.5 Handling and Storage
10.6.4 Installation of Steel H-Section Piles
1064.1 Pitching and Driving of Piles
10.6.4.2 Lengthening of Pil
10.643 Cutting and Preparation of Pile Heads
STEEL PIPE PILES
10.7.1 Description
10.7.2 Materials
10.7.3 Manufacture and Storage of Steel Pipe Piles
10.7.3.1 Welding
10.732 Fabrication of Piles
10.733 Matching of Pile Lengths
10.734 Straightness of Piles
10.735 Fabrication of Piles on Site
10.736 Handling and Storage
10.737 Marking of Piles
10.74
10.7.4. Welding Procedures
19749 Welders! Qualifieations
10.743 Weld Tests
10744 Standards for Welds
10.7.5 Protective Coatings
10.7.5. Surface Preparation
10.7.5.2 Application and Type of Primer
10.753 Control of Humidity During Coating
10.754 Part to be Welded
10.755 ‘Thickness, Number and Colour of Coats
10.756 Inspection of Coatings and Acceptability
10.7.6 Installation of Steel Pipe Piles
10.7.6. Pitching and Driving of Piles
10.7.6.2 Lengthening of Piles
10.7.63 Cutting and Preparation of Pile Heads
10.7.6.4 Conereting of Pile Shaft
MICROPIT FS,
108.1 Description
10.8.2 Materials
1082.1 Reinforcement Unit
10.8.2.2 Grout
10.8.3 Drilling Operations
10.8.3.1 umeter of Piles
10.832 Drilling
10.8.4 Grouting Operations
10.8.4.1 Mixing and Placing Grout
10.8.4.2 Testing Grout
10.8.5 Construction of Pile Heads
1085.1 Lengthening of Piles
10.8.5.2 Cutting and Preparation of Pile Heads
810 - iii
JKRISPJ/2010-810
PAGE
10-21
10-21
$1021
10.21
810-22
$10-22
810-22
810-22
810-22
810-22
810-22
$10-23
10-23
10-23
810-23
310-24
10-24
810-24
10-74
810-24
810.95
10-25
10-26
810-26
S10-26
$10.26
10-27
810-27
310-27
10-27
810-28
810-28
810-28
$10.98
$10-28
810-28
810-28
810-29
$10-29
$10.29
10-29
810-29
S029
$10.29
10-30
10-30
810-3010.9
JKRISPJ/2010-810
PILE TESTING
10.9.1 General
10.9.2 Construction of Pile to be Tested
10.9.2.1 ‘Notice of Construction
10.9.2.2 Method of Construction
10.9.2.3 Boring or Driving Record
10.9.2.4 Concrete Test Cube
10.9.2.5 Cutoff Level
10.926 Preparation for Pile Head for Testing,
10.9.2.7 Supervision
10.9.3 Protection of Testing Equipment
1.93.1 Protection from Weather
1093.2 Prevention of Disturbance
10.933 Notice of Test
10.94 Method of Loading
1094.1 Test Load
10.9.4.2 Contractor's Load Test System
10.943 Measuring Apparatus
10.944 Reference Beams and Displacement Measuring Devices
10948 Auiliary Systems
10.9.4.6 Measurement of Load
10947 Measurement of Settlement
10.9.5 Testing Procedure
10.9.5.1 General
10.9.5.2 Maintained Load Test
10.6 Submission of Results
10.9.6.1 Interpretation of Teot Results
10.9.7 Completion of a Test
10.9.7.1 Removal of Test Equipment
10.9.7.2 Preliminary Test Pile Head
TABLE,
Table 10.1 Specification of Precast Concrete Piles
Table 10.2 Slump Range for Typical Conereting Situations
Table 10.3 Minimum Holding Time for Pile Test
APPENDIX A/1
Bending Strength for Precast Concrete Piles
Table 1: Maximum Allowable Crack Width
‘Table 2: Cracking Rending Moment (Mc) and Factor *f for
Precast Reinforced Conerete Square Piles (RC Piles)
Table 3: Cracking Bending Moment (Mc) and Factor ‘P for
Precast Pretensioned Spun Concrete Piles (Spun Piles)
Table 4: Cracking Bending Moment (Mc) and Factor ‘P’ for
Precast Prestressd Concrete Square Piles- Class PC-X,
Class PC-Y, Small Piles
Figure 1: Loading Method
S10-iv
PAGE
$10-30
810-30
$1030
10-30
10-30
10-30
810-31
10-31
10-31
810-31
810-32
810-32
10-32
10-32
810-32
10-32
810-33
810-33
810-33
sia-34
810-35
s10.35
810-35
810-35
810-36
$10-36
$1037
810-37
810-37
810-37
810-38
$10-39
$10-39
$10-40
310-40
810-43
810-44
10-45
s10-41SECTION 10-— PILING WORKS10.1
10.2
JKRISPU/2010-510
SECTION 10 - PILING WORKS
DESCRIPTION
This work shall consist of the supply, installation and testing of piles in accordance
‘with this Specification and the lines, levels, grades and cross-sections shown on the
Drawings and as directed by the S.0.
GENERAL, REQUIREMENTS AND TOLERANCES
10.2.1
10.2.2
10.2.3
10.24
10.2.5
Setting Out
Setting out shall be carried out using the data and reference points as shown
‘on the Drawings. The pile position shall be marked with suitable identifiable
pins, pegs or markers at least 300mm length. ‘The pins, pegs or markers
should be driven to ground level and the location marked with contrasting
‘material. If raking piles are to be installed then the setting out pins, pegs or
markers is located in an offset position at piling platform level taking into
account of depth to cut-off level and rake value of the pile. In addition, the
alignment of pins, pegs or markers shall indicate the direction of the rake.
Immediately before installation of the pile, the pile positions shall be checked
by the Contractor again.
Position
For a pile cut off at or above ground level the maximum permitted deviation
of the pile centre from the centre points shown on the Drawings shall not
execed 75 mm in any dircetion. For a pile cut off below ground level an
increase in this tolerance of 150mm is permitted in accordance with Sub-
Sections 10.2.3 and 10.2.4 herein below
No pile edge shall be nearer than 150mm from the edge of any pile cap.
Verticality
‘The maximum permitted deviation of the finished pile from the vertical is 1 in
75:
Rake
The piling rig shall be set and maintained to attain the required rake. The
maximum permitted deviation of the finished pile from the specified rake or
the rake shown on the Drawings is 1 in 25,
Fou
ible Curreetiouy
Forcible corrections to concrete piles shall not be permitted. Forcible
corrections may be permitted to specific types of piles if approved by the S.O.
However, no forcible corrections shall be made ta piles which have deviated
s10-410.2.6
10.2.7
w.2.8
10.2.9
JKRISPU/2010-510
beyond the permissible limits specified in Sub-Sections 10.2.2, 10.2.3 and
10.2.4 above.
Piles Out of Alignment or Position
The Contactor shall, if videred by the 8.0., catavt aud reinstall any pile
which has deviated out of position or alignment by more than the specified
limit, or altematively the substructure shall be modified to the approval of the
S.0. The cost of such extraction and reinstallation or any extra cost in the
design and construction of a modified foundation shall be borne by the
Contractor if, such extra works have been made necessary due to the error
and/or negligence of the Contractor.
Records
‘The Contractor shall keep records of the installation of each pile as required
by the §.0. and chall submit two signed copice of these records to the $.0 not
later than at noon of the next working day after the pile has been installed.
The signed records shall form part of the records for the Works. Any
‘unexpected driving or boring conditions shall be noted in the records.
Soil Investigation Keport
A soil investigation report shall be made available at the §.0."s office for the
Contractors information, The report is intended solely as a preliminary guide and
the completeness nor the accuracy of the information provided is not guaranteed,
No responsibility is assumed by the S.0 for any opinion or conclusion given in
the soil report,
‘The Contractor shall study the given soil report in detail and oblige to place his
‘own interpretation on the information provided and to make due allowance for
the effect of site conditions on his construction operations.
Unexpected Ground Conditions
The Coutracior shall report immediately Ww the 8.0 any vitcumstanves which, in
the Contractor's apininn, indicate ground conditions that may differ from those
expected by him from interpretation of the soil investigation report. The
Contractor's report shall be in the form of written notice of which shall be given
to the $.0 at the carlicst possible time after encountering such conditions and
‘obstructions. The report shall be accompanied by all information available to the
Contractor which will materially assist the SO in verifying the conditions
reported, and in determining the cause and reasonableness of any claim relating
thereto in accordance with the Conditions of Contract.
It unexpected ground conditions require the permanent substructure works to be
constructed tn a modified design, the S.0 shall issue instruction for a variation to
the permanent works in the contract.
10-2102.10
102.11
0.2.12
JKRISPJ2010-510
Adjacent Structures
‘The Contractor shall pay very careful attention to the construction constraints
imposed by adjacent structures. The Contractor shall exercise extra care and
implement adequate monitoring measures when carrying out his piling operations
so as not to disturb or damage existing adjacent properties and foundations. The
Contractor shall provide a proposal for monitoring adjacent properties for any
detrimental effects arising out in execution of the piling works, so that
appropriate and timely preventive action can be taken to minimise damage. The
Contractor's proposal and monitoring program shall be certified by his
Professional Engineer.
‘The Contractor shall also carry out a condition survey of adjacent properties to
establish the condition of the existing structues and facilitics prior to
commencement of piling work. Condition Surveys shall be conducted by a
registered building surveyor and the result of the survey shall be submitted to the
8.0. for record.
‘The Contractor shall be responsible for and shall bear the cost of such works and
any claims for damage to adjacent structure and facilities arising. from his
‘execution of the piling works
Existing Sorvicos
‘The Contractor shall give all required notices to the appropriate utility authorities
before commencement of piling works. The Contractor shall also locate existing
services by piloting, protect existing services. rectify any damage or interference
to them and provide temporary support while repairs are being carried out if s0
required,
‘Method Statement for Construction Operations
‘Two weeks before the commencement of piling works, the Contractor shall
submit to the S.O. a detailed method statement for the installation of piles. For
the purpose of this elauee, a method etatement chall be « document containing:
i) A detailed construction sequence.
fi) Shop drawings showing details of all special requirements for the
construction activities such as hoisting of piles, reinforcement cages, cast
in fining ete
iii) Design calculation of key temporary works endorsed by his Professional
Engineer.
iv) Material, plant and labour requirement at each construction stage.
v) Rate of production output based on resources allocated.
vi) Other information relevant to the piling works.
If requested by the S.O, the Contractor shall submit additional information
pertaining to the method of construction (including temporary works and the use
ff the cansimetion plant), calculation of the stresses, strain and deflection that
will arise in the permanent works of any part thereof during construction.
s10.3102.13
JKRISP/2010-510
‘The Contractor shall not change the methods which have been approved by the
8.0. Approval by the §.0. of the Contractor's proposed methods of construction
in accordance with the clause shall not in anyway relieve the Contractor of any of
his duties or responsibilities under the contract.
Alternative Piling System by Contractor
The Contractor may submit his proposed alternative piling system, exchuding
timber and bakau piles, other than that specified in the drawings for the S.0’s
review. The Contractor’s submission shall be endorsed by his Professional
Engineer, an Independent Check Engineer (ICE) and shall include the following
information: -
1) Calculation demonstrating the single pile and group working capacity
and pile lengths of the pile system proposed stating clearly the
underlying assumptions adopted.
ii) Specification for the proposed system. including type of piling
equipment, maximum length of piles that can be satisfactorily installed
and average output in linear metres of installed pile per piling frame per
normal working day of 8 working hours per day.
ft) Pile layout arrangements.
iv) Method of construction, including method of jointing,
¥) Design drawing and quantities of pile cap.
vi) Guarantee of pile capacity for all piles installed, regardless whether or
not the capacity of a pile is proven by test.
vi) Any other information required by the engineer in his review of the
alternative system.
viii) Cost savings to the Government.
The system put forward by the Contractor shall have good records of successful
{installation and performance in local projects of comparably project size and
ground conditions.
‘The Contractor's design calculation and specification shall comply fully with the
relevant recommendations of the Rritish Standard RS 8004, the requirement of
the specification and the Condition of Contract. In matters not specifically
covered by the British Standard BS 8004 and the specification, the Contractor's
proposal shill also be subject tv the 8.0" approval. It shall be te Contactors
responsibility to clearly itemise any departure from British Standard BS 8004 and
piling specification provided.
Prior to the acceptance of the alternative pile design and the installation of any
working pile, the Contractor shall be required 0 carry out failure load tests to
confirm his design. Based on the results of the tests, the Contractor shall be
required 10 modify his design of piles where necessary to the satisfaction of the
S.O at no extra cost
S104JIKRISPJ2010-510
10.2.14 As-Built Locations
‘After construction, actual pile locations shall be certified by a Licensed Surveyor
employed by the Contractor for this purpose. The Contractor shall submit an as~
built pile plan to the S.0 within 7 (seven) working days of completion of the last
pile. Partial as-buult may be submitted throughout construction of the foundation
for verification by the S.0.
PRECAST REINFORCED CONCRETE PILES
10.3.1 Description
This work shall comprise the supply and installation of precast reinforced
concrete piles, inclusive of pitching and driving, lengthening and cutting and
preparation of pile heads, all in accordance with this Specification and to the
details shown on the Drawings. The classification and definition of Precast
Concrete Pile shall be in accordance with Table 10.1 of this Specification,
10.3.2 Materials
10.3.2.1 Concrete
103,
103.2.
Unless otherwise specified, Portland cement shall be used for the casting of
piles. The materials and workmanship shall be as specified under Section 9 of
this Specification. The grade of concrete and the details of reinforcement (0
he used shall he as shown on the Drawings and shall comply with the
specification as stated in Table 10.1 of this Specification.
Reinforcement
‘The main reinforcing bars in piles not exceeding 12 m in length shall be in one
continuous length unless otherwise approved by the S.O. In piles exceeding
12 m long, joints shall be permitted in main longitudinal bars at 12 m nominal
intervals. Joints in adjacent bars shall be staggered at least 1 m apart along
the length of the pile. Joints shall be butt welded as specified in Sub-Section
9.7.3.5 of this Specification. Jointing at reinforcement, by means of
‘mechanical couplings shall not be permitted.
Pile Shoes
‘The type of pile shoes to be used shall be as shown on the Drawings and shall
comply with the following as relevant: -
i) "Chilled-hardened” cast iron shoes as used for making grey iron
castings to BS EN 1561, Grade 10; or
Mild steel to B.S FN 10025 ar equivalent, Grade SOR; or
Cast steel to BS EN 10293, Grade A.
s10-5JKRISPJ/2010-510
Mild steel straps cast into the shoes shall be as shown on the Drawings. Rock
shoes where required shall consist of wrought iron shoes and mild steel straps
cast into "Chilled hardened” cast iron blocks, ae chown on the Drawings
‘The shoes shall be truly coaxial and firmly embedded on to end of the pile.
10.3.3 Manufacture and Storage of Precast Reinforced Concrete Piles
10.3.3.1 Casting
The length of piles to be cast shall be as shown on the Drawings, subject to
revision by the $.0. The concrete shall be compacted by approved means
against the face of the mould and in between reinforcements.
Based on the results of pile driving resistance and/or load tests carried out on
piles driven on the site, the S.0. may from time to time order the lengths of
piles to be modified.
Piles shall he east on a horizontal platform in approved moulds to the
dimensions as shown on the Drawings. The moulds used in manufacture shall
be sufficiently rigid and accurate to maintain the pile dimension within the
tolerance stated in the following paragraph, The concreting of each pile shall
be completed in one continuous operation and no interruptions will be
permitted. Lifting holes shall be formed during casting in the positions and in
accordance with the details shown on the Drawings. The piles shall be cured
in accordance with Section 9 of this Specification.
‘The cross-sectional dimensions of the pile shall not be less than those shown
‘on the Drawings and shall not exceed by more than 6 mm. Any face of a pile
shall not deviate by more than 6 mm from a straight edge 3 m long laid on the
face, and the centroid af any cross-sections of the pile chall not deviate hy
‘more than 12 mm from the straight line connecting the centroid of the end
faces of the pile.
After a pile has been cast, the date of casting, reference number and the
length shall be clearly marked with undeletable marker on the top surface and
‘on the head of the pile, Each pile shall be marked at intervals of 0.5 m along
its length before being driven.
10.3.3.2 Handling and Storage
The method and sequence of lifting. handling, transporting and storing piles
shall be such that piles are not damaged or having crack width greater than
0.1mm. Only the designed lifting and support points shall be used. During
transport and storage, piles shall be placed on adequate supports located
under the lifting points of the piles. Piles shall be stored and stacked on firm
ground not liable to settlement under the weight of piles. The supports shall
bbe vertically above one another. All piles within a stack shall be in groups of
the same length. Packings of uniform thicknesses shall be provided between
piles at the lifting points.
s1n6JKRISPL/2010-510
No piles shall be allowed for transportation before achieving concrete
strength of 30 N/mm?
No pile shall be driven before the specified characteristic strength of
appropriate grade of concrete has been achieved.
10.3.4 Installation of Precast Reinforced Conerete Piles
10.3.4.1 Pitching of Piles
Piles shall be pitched accurately in the positions as shown on the Drawings.
‘At all stages during driving and until the pile has set or been driven to the
required length, all exposed piles shall be adequately supported and
restrained by means of leaders, trestles, temporary supports or other guide
arrangements to maintain position and alignment and to prevent buckling
and damage to the piles.
10.3.4.2 Driving of Piles
Each pile shall be driven continuously until the specified set and/or depth has
been reached, unless otherwise approved by the S.O. The driving equipment
used shall be of such type and capacity to the approval of the S.O. A follower
(long dolly) shall not be used unless otherwise meet the followi
requirement and approved by the $.0.
i) The first pile in each pile system and every tenth pile driven thereafter
shall be driven full length, without a follower, to verify that adequate
pile length is being attained to develop the desired pile capacity.
ii) The follower and pile shall be held and maintained in equal and
proper alignment during driving.
‘The follower shall be of such material and dimension to permit the
piles to be driven to the length determined necessary from the driving
of the full length piles.
iv) The final position and alignment of the first two piles installed wi
follower in each substructure unit shall be verified to be in accordance
with the location tolerances specified in Sub-Section 10.2 before
additional piles are installed,
Follower shall not be used in dr
ing of raked pile,
A detailed record of the driving resistance over the full length of each pile
shall be kept. The log shall record the number of blows for every 0.5 m ot
pile penetration. The Contractor shall inform the S.O. without delay if an
‘unexpected change in driving characteristics is encountered. Where required
by the S.0. set shall be taken at approved intervals during the driving to
establish the behaviour of the piles.
A set shall be taken only in the presence of the .0, unless otherwise
approved. The Contractor shall provide all facilities to enable the S.0. to
check driving resistances. The final set of a pile other than as friction pile,
10-7JKRISPJI2010-S10
shall be recorded as the penetration in millimetres per 10 blows. The
temporary compression of the pile shall he recorded if requited
When a set is being measured, the following requirements shall be met:
i) The pile shall be in good condition, without damage or distortion.
ii) The hammer blow shall be in line with the axis of the pile and the
impact surface shall be flat and perpendicular to the hammer axis,
iii) The hammer chall be in good condition, delivering the required
energy per blow and operating correctly.
iv) The rebound shall be measured and recorded accordingly.
When an acceptable resistance or set appears to have been reached, the
driving of pile should be suspended for an interval sufficient to permit the soil
to recover from the disturbance of pile driving, and then resumed to
determine whether there is any increase or decrease in resistance.
In soils that dilate when disturbed c.g. silts and some shales, negative pore
pressure can be set up temporarily and the driving resistance may fall as these
pore pressure return to normal. In clays disturbance can cause positive pore
pressure to develop and the strength of the soil may increase as these
dissipate, The necessary time interval before redriving may vary from 1 hour
to 2 hours for non-cohesive soils or to 2 days or more for clays.
The resistance at the start of redriving is more likely to be representative of
the true bearing value of the pile. and each redriving result should be taken
into consideration when deciding the pile penetration length.
Piles shall be driven in an approved sequence to minimise the detrimental
effects of heave and lateral displacement of the ground. When required,
carefil levelling from a datum unaffected hy the piling shall he made on the
pile heads already driven, before and after driving subsequent piles. Piles
which have been displaced vertically by more than 3mm as a result of driving
adjacent piles shall be redriven to the required resistance,
10.3.4.3 Preboring and Jetting of Piles
Piles chall not be prebored without the written approval of the $.0. Preboring
of piles may be allowed for the following reasons:
i) To ease pile drivability by breaking through soil layers.
To reduce lateral soil displacement where this could cause damage to
nearby structure.
iii) ‘To investigate and possibly deal with obstruction in the ground.
The piles shall remain in intimate contact with surrounding soil and the
completed piles shall comply with the requirements of this Specification
Diameter of preboring shall be in accordance with Section 10.5.3.1 of this
Specification. If boring is oversize. any gap between the tube and ground
shall be filled with compacted sand prior driving the pile,
sto.8JKRISPJ/2010-S10
In some soils, jetting may lift adjacent structure or cause undermining of
nearby foundations. Pile shall not he jetted withont the written appreval af the
8.0. Prior to jetting any pile, the Contractor shall submit to the $.0. details of
the equipment to be used and the proposed method to be adopted.
10.3.4.4 Repair of Damaged Pile Heads
If a pile is to be subjected to further driving, concrete in the damaged pile
head chall be out off equare at cound concrete, and all looce particles chall be
removed by wire brushing, followed by washing with water. Care shall be
exercised to ensure that the reinforcement in the pile head is not in any way
damaged. Any damaged reinforcement shall be made good to the satisfaction
of the $.0, The head shall be replaced with concrete of similar grade or
higher.
‘The new head shall be east truly in line with the remainder of the pile and be
properly cured and allowed to harden sufficiently to develop the strength
necessary for further driving. If a pile has been driven to the required set or
depth but the level of sound conerete of the pile is below cut-off level, the
pile shall be made good to the cut-off level as described above so that the
completed foundation will safely withstand the specified ultimate load
10.3.4.5 Lengthening of Piles
Whcte piles have to be lengthened, other than by means of welding of steel
plates as detailed on the Drawings. the reinforcement shall be stripped of all
surrounding concrete for a distance equal to forty (40) times the diameter of
the main reinforcement measured from the pile head for spliced joints and
300 mm for hutt welded joints and all lateral reinforcement shall be removed,
The new concrete shall he of the same grade ar higher as the original concrete
on pile and shall be adequately compacted.
The lengthening bars shall butt on the exposed bars in tue alignment and
shall be butt welded as specified or shall be spliced with bars of the same
diameter as the main pile bars, 60 diameters in length and lapping the main
bars for a distance of 40 diameters above and below the joint, and shall be
securely bound with 1.63 mm soft annealed iron wire
New binders of similar size shall he provided and spaced at half the centers of
the binders in the main body of the pile and shall be securely bound with 1.63,
mm soft annealed iron wire and the pile extended by concreting in properly
constructed mounds to the length required.
Care shall be taken to form the joint between the old and new concrete ae
specified hereinbefore. The old concrete shall be adequately roughened and
all loose particles shall be removed by wire brushing, followed by washing
with clean water. The extension shall be truly in line at all stages of handling
and driving with the remainder of the pile and be properly cured and allowed
to harden sufficiently to develop the strength necessary for further driving.
s10.0JKRISPUI2010-S10
10.3.4.6 Pile Joint
‘The bending strength test of pile joint shall be done for laterally loaded pile
only to determine the bending capacity at each respective joint. The test shall
be done as in 10.3.4.7 provided that the joint is positioned at the centre of the
span, Ihe bending capacity at the pile joint shall be greater than the bending
capacity of the pile body by 10%. The result shall be submitted to S.0 for
approval prior to driving of any pile.
10.3.4.7 Pile Bending Strength Test
Pile bending strength test shall be performed in accordance with Appendix
Al of this Specification,
10.3.4.8 Cutting and Preparation of Pile Heads
‘When a pile has been driven to the required set or depth, the head of the pile
shall be eut off to the level specified or shown on the Drawings. This shall be
done carefully to avoid shattering or otherwise damaging the rest of the pile.
Any eracked or defective concrete shall be cut away and made good with new
‘concrete properly bonded to the old. The length of reinforcing bars projecting
above this level shall be as shown or specitied on the Drawings. If the length
of reinforcing bars left projecting is insufficient, then they shall be extended
by either of the following methods: -
(a) Butt Welding
The extension bars shall butt on the projecting bars in true alignment and
shall be butt welded in accordance with Sub-Section 1074 of this
Specification,
Redriving of the piles shall only be allowed after the welded joints have
sufficiently air cooled to 100°C or below.
(b) Splicing
‘The projecting bars shall be stripped of all surrounding concrete as necessary
to allow splices of length 60 diameters with extension bars. The extension
boars shall be securely bound to the projecting bars with 1.63 mm soft annealed
iron wire. The concrete of the pile shall be made good either before or
together with the casting of the pile cap, all to the satisfaction of the S.O.
Care shall be taken to avoid cracking or otherwise damaging the rest of the
pile. Any eracked or defective conerete shall be cut away and made good with
new concrete properly bonded to the old.
10-10JKRISP4/2010-510
10.4 PRESTRESSED SPUN CONCRETE PILES
10.4.1 Deseription
This work shall comprise the supply and installation of prestressed spun
conerete piles, inclusive of pitching and driving, lengthening and cutting and
preparation of pile heads, all in accordance with this Specification and to the
details shown on the Drawings and shall comply with the specification as
stated in Table 10.1 of this Specification.
10.4.2.1 Concrete
Unless otherwise specified, Portland cement shall be used for the casting of
piles. The materials and workmanship shall be as specified under Section 9 of
this Specification. The grade of concrete to be used shall be as shown on the
Drawings.
2 Reinforcement
‘The prestressing tendons and the non-prestressing reinforcement of the piles
including workmanship shall be as specified under Sections 9 and 11
respectively of this Specification and to the details as shown on the Drawings.
Prestressing steel shall comply with JIS G3137 or BS 4486 or BS $896 or
ASTM A416 or equivalent.
A certificate of conformance is required for every d of reinforcement,
‘The minimum concrete cube strength at transfer should be 30 N/mm’, All test
cubes should be stored under same conditions as the piles.
10.4.2.4 End Plates
Details of end plates of each length of pile shall be as shown on the
Drawings. Lach end plate shall be machinc-finished and provided with a
chamter to accommodate the welding when two lengths of pile are jointed.
10.4.2.5 Pile Shoes
If specified, the type of pile shoes to be used shall be as shown on the
Drawings and shall be in accordance with Sub-Section 10.3.2.3,
sin4JKRISPU/2010-510
10.4.3 Manufacture and Storage of Prestressed Spun Conerete Piles
1 Casting
The length of piles to be cast shall be as shown on the Drawings, subject to
revision by the $.0. Based on the results of pile driving resistance and/or load
tests carried out on piles driven on the site, the S.0. may from time to time
‘order the lengths of piles to be modified.
Piles shall be hollow cylinders manufactured by the centrifugal casting
process. Moulds shall be of metal, well braced and stiffened against
deformations caused by the hydrostatic pressure of the wel concrete while
spinning. The mould used in manufacture and casting shall be in accordance
with Sub-Section 10.3.3.1.
‘The metal forms shall have smooth joints and inside surfaces. The forms shall
be accessible for adequate cleaning. Ihe spiral reinforcement shall be
securely held to the longitudinal reinforcement during casting and pinning
‘Any welding used shall not affect the strength of the pre-stressing tendons.
The pile shall not be removed from the moulds until after the specified
transfer strength is achieved.
‘The external diameter and the thickness of the pile shall not be less than that
shown on the Drawings and shall be coustant over the cutire length of the
pile and coaxial with the end plate at each end.
After a pile has been cast, the date of casting, reference number and length
shall be clearly marked with undeletable marking on the top surface and on
the head of the pile. In addition, each pile shall be marked at intervals of 0.5 m
along ite length before being driven.
10.4.3.2 Handling and Storage
‘The method and sequence of lifting, handling. transporting and storing piles
shall be in accordance with Sub-Section 10.3.3.2..
10.4.4 Installation of Prestressed Spun Coucrete Piles
10.4.4.1 Pitching and Driving of Piles
Pitching and driving of piles shall be in accordance with Sub-Sections 10.3.4.1
and 10.3.4.2. Piles shall not be driven until the concrete has achieved the
specified characteristic strength,
10.4.4.2 Lengthening of Piles
Where lengthening of piles is required, the details of the joint shall be as
shown on the Drawings and in auvudauee with Sub-Seotion 10.7.4, When
1042JKRISPJ/2010-510
two lengths of pile are jointed, the end plates shall bear over their complete
areas. Shims for packing shall nat he accepted. Far laterally loaded pile, the
pile joint shall be in accordance with Sub-Section 10.3.45.
10.4.4.3 Cutting and Preparation of Pile Heads
When a pile has been driven to the required set or depth, the head of the pile
shall be cut off to the level specified or shown on the Drawings using a
diamond cutter. Pile heads chall be constructed to details as chown on the
Drawings.
10.5 BORED CAST-IN-SITU PILES
10.5.1 Description
‘This work shall comprise the boring or grabbing, with or without casing, and
subsequently filling the hole with plain or reinforced concrete to form bored
cast-in-situ piles, all in acvordauve with this Specification aud (w the details
shown on the Drawings
10.5.2.1Conerete and Reinforcement
The concrete and reinforcement to be used and workmanship for bored cast-
in-situ piles shall be a9 specified under Scction 9 of this Specification. The
grade of concrete and the details of reinforcement to be used shall be as
shown on the Drawings.
10.5.2.2 Permanent Casings
Permanent casings which form part of the designed pile shall be as specified
on the Drawings.
10.5.2.3 Support Flui
Support uid material, bentonite, shall comply with the manufacturer's
certificate and mix proportion. A certificate shall be obtained by the
Contractor from the manufacturer of the bentonite powder, showing the
properties of each consignment delivered to the site. This certificate shall be
made available to the S.0. Test should he carried out at regular interval to
censure consiateney of the batching process.
Polymer can be used as an alternative to bentonite to maintain stability of the
bores with the approval of the S.O.
Bentonite or polymer shall be mixed thoroughly with water complying with
MS 28 to make a suspension which will maintain the stability of the pile
excavation for dhe period necessary wW place comeicic and complete
1043JKRISPJ2010-510
construction. Preparation of the suspension shall comply with the
‘manufacturer's instructions
Where saline or chemically contaminated ground water occurs, special
precautions shall be taken to modify the bentonite suspension or prehyydrate
the bentonite in fresh water to render it suitable in all respects for the
construction of piles.
10.5.3 Boring Operations
10.5.3.1 Diameter of Piles
‘The diameter of piles shall not be less than the specified designed diameter at
any level throughout its length.
The auger width shall be checked as necessary and recorded for each pile to
ensure the specified diameter is achieved. A tolerance of +5% to 0% on the
auger width is permissible.
10.5.3.2 Boring
Boring shall be carried down to the depth as required and directed by the
8.0. When deemed necessary by the S.O.. the Contractor shall take
undisturbed soil samples while the pile is being bored. The samples shall be
taken to an approved Laboratory for testing.
‘Sampling and all subsequent handling and testing shall be carried out in
accordance with BS EN ISO 1997, BS EN ISO 14688, BS EN ISO 14689,
BS EN ISO 22475 and BS EN ISO 22476,
Piles shall not be bored at a distance less than 3 times diameter close to other
piles which have recently heen east and which contain workable or unset
concrete,
10.8.3.3 Drilling In Rock
The Contactor shall submit a method statement when drilling in rock. Chiselling
of rock may cause micro cracks in surrounding rock and is not allowed.
10.5.3.4 Temporary Casings
‘Temporary casings of approved quality or an approved alternative method
shall be used to maintain the stability of pile excavations which might
otherwise collapse,
‘Temporary casings shall be fice from significant distortion. They shall be of
uniform cross-section throughout each continuous length. During concreting
they shall be free from internal projections and encrusted concrete which
tight prevent dhe prupes formation of the piles being eas.
s1044JKRISPU/2010-S10
10.5.3.5 Stability of Piling Excavations Using Support Fluid
Where the use of support fluid or a column of water is approved for
maintaining the stability of boring, the level of fluid or column of water in the
excavation shall be maintained such that the fluid pressure always exceeds the
pressure exerted by the soil and external ground water and an adequate
temporary casing shall be used in conjunction with the method to ensure the
stability of the strata near ground level until concrete has been placed. The
fluid water level shall be maintained at a level not less than 1 metre above the
level of the external ground water. In the event of a rapid loss of bentonite
suspension, polymeric fluids or water from the piling excavation, the
excavation shall be backfilled with lean concrete or well compacted sand as
specified in Section 9 of this Specification without delay and the instructions
of the S.O. shall be obtained prior to resuming boring at that location.
10.5.3.6 Spillage and Disposal
[All reasonable steps shall be taken to provent the spillage of bentonite
suspension or water on the site in areas outside the immediate vicinity of the
boring operations. Discarded bentonite water shall be removed from the site
without delay. The disposal of bentonite water shall comply with the
regulations of the Local Authorities,
Entrained solids shall be removed trom the polymeric fluid by use of
flocculants before disposal of the remaining fluid to the environmentally
acceptable area,
10.5.3.7 Pumping of Boreholes
Pumping from the borehole shall not be permicted unless @ casing has been
placed into the stable stratum (o prevent the further ingress af water in
significant quantities from other strata into the boring, or, unless it can be
shown that pumping will not have a detrimental effect on the surrounding soil
orits properties.
10.5.3.8 Continuity of Construction
A pile constructed in atable soil, without the use of temporary casings or other
support, shall be bored and concreted without delay to ensure that the soil
characteristics are not significantly altered. Sandy clays or clayey silts may
soften significantly in less than 12 hours. Where prolonged delay in
construction arises, the bore may have to be backtilled with lean concrete as
specified in Section 9 of this Specification or well compacted sand to
‘minimise deterioration of the shaft. The time interval between completion of
boring and placing of concrete should be preferably within 6 hours.
If the pile excavation is carried out using permanent or temporary casing, the
time period between completion of pile excavation and completion of concreting
is recommended not to exceed 24 hours.
s10-15JKRISP/2010-510
10.5.3.9 Enlarged Pile Bases
The enlarged pile base shall not be smaller than the dimensions specified und
shall be concentric with the pile shaft to within 10% of the shaft diameter. A
sloping surface of the frustum forming the enlargement shall make an angle to
the horizontal of not less than 55. At the specified diameter of the under ream
at the perimeter of the base there shall be a minimum height of 150mm.
10.5.3.10 Cle of Pile B.
‘On completion of boring, loose, disturbed or remoulded soil or fragments of
+0ck shall be removed from the base ofthe pile
10.53.11 Inspection
For dry boreholes, each hole shall be inspected prior to the placing of concrete
in it. The inspection shall be carried out from the ground surface in the case
where the borehole diameter is less than 1500 mm, Where the borehole
diameter exceeds 1500 mm, adequate equipment shall he provided to enable
the Contractor and the S.0. to descend into the borehole for the purpose of
inspection. All works shall conform to the requirement of BS 5537: Safety
Precaution in the Construction of Large Diameter Borehole for Piling and
Other Purposes. For wet boreholes, ic. holes filled with drilling fluid or
water, a suitable probe shall be provided to ascertain the evenness and
cleauliness uf the pile base
10.5.4 Placing of Reinforcement
10.5.4.1 Joints in Longitudinal Bars
Reinforcement shall be such that the full strength of the bar is effective
across the joint and the joint shall be made so that there is no relative
displacement of the reinforcement during the construction of the pile and the
spacing of the reinforcing bars shall be maintained in such a way that proper
concreting shall not be impeded.
Adequate spacer blocks, guide tubes, and lifting wires shall be provided so
as to maintain the reinforcing stecl in the positions as specified,
Where temporary casings are employed, the longitudinal reinforcement shall
extend at least 1.0 metre below the bottom of the casing so that movement of
the reinforcement during extraction of the casing is minimised.
s10-16JKRISPU/2010-510
10.8.5 Conereting Operations
10.5.5.1 Placing Concrete
‘The method of placing and the workability of conerete shall be such that a
continuous monolithic concrete shaft of the full cross-section is formed,
5.2 Workability of Concrete
‘The workability of the concrete shall be determined by the slump test as
described in MS. 26,
The suggested slump details for typical concreting situations shall be as
specified in Table 10.2 of this Specification. The slump shall be measured at
the time of discharge into the borehole.
10.5.5.3 Compaction
Internal vibrators shall not be used to compact concrete unless it can be
satisfied that they will not cause segregation or arching of the concrete.
10.5.5.4 Placing Concrete In Dry Borings
Approved measures shall be taken to avoid segregation and bleeding and to
ensure that the concrete at the bottom of the pile is not deficient in grout
Where piles are vertical, concrete may be poured through a funnel with a
length of tube so that the flow is directed and does not hit reinforcement bars
or the side of the hole. Chutes extending to near the base shall be employed
for raking piles of large diameter. For raking piles of small diameter, an
enriched mix of 20% more cement shall be used in the first few batches of
concrete to minimise segregation.
10.5.5.5 Placing Concrete Under Water or Support Fluid
‘The concrete mix shall he 20% more cement content when placing is done under
water,
Conerete to be placed under water or support fluid shall be placed by tremie
unless otherwise approved and shall not be discharged freely into the water or
support fluid. Refore placing concrete, measures shall be taken to ensure that
there is no accumulation of silt or other material at the base of the boring.
The hopper and pipe of the tremie shall be clean and watertight throughout
The pipe shall extend to the base ot the boring and a sliding plug or barrier
shall he placed in the pipe to prevent direct contact between the first charge of
cconerete in the pipe of the tremie and the water or support fluid. The tremie
pipe shall at all times penetrate the concrete which has previously been placed
fond ahall not be withdrawn from th sonerote until the completion of
$10.17JKRISPJI2010-510
concreting,
AC all Limes, a sufficient quantity of concrete shall be maintained within the
tremic pipe to ensure that the pressure from it exceeds that from the water or
support fluid. The internal diameter of the tremie pipe shall not be less than
150 mm for conerete made with 20 mm aggregate and not less than 200 mm
for concrete made with 40 mm aggregate.
‘The tremie pipe shall he se designed that external prajections are minimised,
allowing the tremie pipe to pass through the reinforcing cage without causing
damage or uplifting. The intemal face of the tremie pipe shall be from
projections,
10.5.6 Extraction of Casing
105.
Workability of Concrete
‘Temporary casings shall be extracted while the eonerete within them remains
sufficiently workable to ensure that the concrete is not lifted,
10.5.6.2 Concrete Level
When the casing is being extracted, a sufficient quantity of concrete shall be
maintained within it to ensure that the pressure from external water, drilling
fluid or soil is exceeded and dhat the pile is meither reduced in section nor
contaminated
No conerete shall be placed in the bore once the bottom of the casing has
been lifted above the top of the conorete, It shall be placed continuously ae
the casing is extracted until the desired head of concrete is obtained.
‘Adequate precautions shall be taken in all cases where excess heads of water
or drilling fluid could be caused as the casing is withdrawn because of the
displacement of water or fluid by the conerete as it flows into its final
position against the wall of the pile shaft. Where double casings are used in
the boring, the proposed method of working shall be with the approval of the
Sw.
10.5.6.3 Vibrating Extractors
‘The use of vibrating extractors shall be permitted subject to the condition
that work shall be carried out in such a manner and at such times as to
minimise nuisance and disturbance.
$1018JKRISPLI2010-S10
10.5.7 Construction of Pile Heads
10.5.7-1 Water Levels
In the event of the ground water level bein higher than the required pile head
casting level shown on the Drawings, the Contractor shall submit his
proposals for approval prior to placing concrete. The pile head shall not be
left helow the ground water level unless approved precautions are taken
2 Cutting and Preparation of Pile Heads
The top of the pile shall be brought at least 300 mm or more as specified in
the drawings above the cut-off level of the pile to permit all laitance and weak
conerete to be removed and to ensure that it can be properly keved into the
pile cap. Only hand held cutting equipment or hydraulic splitters shall be
used. Pile heads shall be constructed to the details shown on the Drawings.
.3 Temporary Backfilling Above Pile Casting Level
After each pile has been cast, any empty bore remaining shall be protected
and chall be carefully backfilled as soon as possible with well compacted
sand.
10.5.7.4 Piling Records
‘Complete piling records shall be kept by the Contractor during pile installation
‘The Contractor shall submit in duplicate the following information to the $.0:
’) Signed records of all piles as the work proceeds. Individual pile record
shall be submitted not later than noon of the next working day after the pile
was installed. The signed records shall form record of the work. Any
‘unexpected installation condition shall be noted in the record.
ii) Upon completion, compile a record of the work as carried out and provide
as-build drawings. The Drawings shall be prepared and endorsed by the
Licensed Surveyor.
‘The format of the record shall be approved by the S.O. and shall contain but not
be hmited to the following information where applicable: ~
Date of concreting
= Concrete mix
= Method af concreting
= Standing ground water level
= Length of temporary casing
- Length of permanent casing
= Details of soil strata penetrated,
= Soil samples taken and in-situ tests camied out
~ Length and details of reinforcement.
- Estimated and actual volume of concrete required to
form the pile shaft
All record shall bear the names of person who records and person who checks,
s10 10JKRISPJI2010-S10
10.5.8 Pressure Grouting of Piles
Post grouting of piles in sand shall be constructed to details as shown in the
drawings if encounter any base disturbance to ensure compatible performance
of piles. Method of grouting shall be carefully controlled to prevent pile uplift
and avoid other potential problems with prior approval of the S.0.
Pressure grouting shall not be used to compensate for poor pile construction
practice,
10.6 STEEL H-SECTION PILES
This work shall comprise the supply and installation of steel H-section piles,
inclusive of pitching and driving, lengthening and preparation of pile heads, all
in accordance with this Specification and to the details shown on the
Drawings
10.6.2 Materials
All steel H-bearing piles shall comply with the requirement of BS EN 10025 and
or BS EN 10029, BS EN 10210. BS EN 10113. BS 7668 or JIS A5526. The
profile and grade to be used are as specified or as shown on the Drawings.
10.6.3 Manufacture and Storage of Steel I1-Section Piles
10.6.3.1 Manufacturing Tolerances
Al piles shall be of the type and cross-sectional dimensions as designed. For
standard rolled sections the dimensional tolerances and weight shall comply with
the relevant standard, Length tolerance of H-section steel hearing piles shall he
£50 mm in accordance with BS EN 10034
The rolling or proprietary tolerances for H-section steel hearing, piles shall he
such that the actual weight of the section does not differ from the theoretical
weight by more than + 2.5%,
2 Straightness of Sections
For standard rolled sections the deviation from straightness shall be within the
compliance provisions of BS EN 10034, When two or mare rolled sections are
joined by butt-jointing, the deviation from straightness shall not exceed 1/600 of
the overall length of the pile.
For proprietary sections made up from rolled sections and for tubular piles, the
deviation from straightness on any longitudinal face shall not exceed 1/600 of the
Tength of the pile nor 5 mm in any 3 m length
$10.20JKRISPJI2010-S10
Based on the results of pile driving resistance and/or load tests carried out on
piles driven on the Site, the S.O. may from time to time order the lengths of
piles tu be modified,
10.6.3.3 Strengthening of Piles
Unless otherwise approved by the S.0.., the strengthening of the toe of the
lieu of a shoe or the strengthening of the head of a pile shall be made from
material of the came grade as the pile and to the details as shown on the
Drawings,
10.6.3.4 Marking of Piles
Each pile shall be clearly marked with white undeletable marking at the
flanged head showing its reference number and overall length. In addition,
cach pile ehall be marked at intervals of 500 mm along its length before being
driven. The length of piles to be supplied shall be as shown on the Drawings
subject to revision by the S.0
10.6.3.5 Handling and Storage
Al operations such as handling and transporting of piles shall be carried out
in such a manner that damage to piles and their coatings is minimized. Piles
that are damaged during handling and transporting shall be replaced by the
Contractor at his own expense. All damaged and rejected piles ahall be
removed from the Site forthwith.
Piles within a stack shall be in groups of the same length and on approved
supports
10.6.4 Installation of Stool H-Section Piles
10.6.4.1 Pitching and Driving of Piles
Pitching and driving of piles shall be in accordance with Sub-Sections
10.3.4.1 and 10.3.4.2.
10.6.4.2 Lengthening of Piles
Where lengthening of piles is required, the piles shall be jointed by butt
welding. Butt welded joints shall be stiffened with plates fillet welded on all
four sides as detailed on the Drawings. All welding shall be continnons and
complying with BS 638, BS EN 1011 and BS EN 1993 for arc welding and
BS EN ISO 4577 for resistance welding as appropriate. The type and size of
weld shall be as Uetailed ou the Drawings.
Weld tests shall be performed by radiographic or ultrasonic methods as
specified. Provided that satisfactory results are being obtained, one test of a
length of 300 mm shall be made for 10% or more of the number of welded
splices.
s10.24JKRISP./2010-S10
Redriving of the piles shall only be allowed after the welded joints have
sufficiently air cooled to 100°C or below.
10.6.4.3 Cutting and Preparation of Pile Heads
When a pile has been driven to the required set or depth and before encasing
in concrete, the piles shall be cut to within 20 mm of the levels shown on
the Drawings. Pile heads shall be constructed to the details as shown on the
Drawings.
‘The remaining section which can be reused for lengthening of piles shall be
stored and protected as directed by the S.O.
10.7 STEEL PIPE PILES
10.7.1 Description
This work shall comprise the supply and installation of steel pipe piles,
inclusive of pitching and driving, lengthening and preparation of pile heade,
all in accordance with this Specification and to the details shown on the
Drawings.
10.7.2 Materials
Al steel pipes shall comply with BS EN 10296, BS EN 10297 and BS EN
10305 with regard to sectional dimensions and the stecl shall comply with
the requirements of BS EN 10113 or BS EN 10025,
10.7.3 Manufacture and Storage of Steel Pipe Files
1.7.3.1 Welding
Unless otherwise specified, all welds shall be full penetration butt welds
complying with the requirements of BS EN 12334.
10.7.3. Fabrication of Piles
Pile lengths shall be set up so that the differences in dimensions are matched
as evenly as possible, The length of piles to be supplied shall be as shown on
the Drawings subject to revision by the S.0.
Based on the results of pile driving resistance and/or load tests carried out on
piles driven on the Site, the S.O, may from time to time order the lengthe of
piles to be modified.
Tor tubular piles where the load will be carried by the wall ofthe pile, and if the
pile will be subjected to loads that induce reversal of stress during or after
construction, the external diameter at any section as measured by using a steel
$10.22JKRISPJI2010-S10
tape on the circumference shall not differ from the theoretical diameter by more
than = 1%,
The ends of all tubular piles as manufactured shall be within a tolerance on
ovality of 4 1% as measured by a ring gauge for a distance of 100 mm at each
end of the pile length.
The root edges or root faces of lengths of piles that are to be shop butt-welded
shall not differ by more than 25% of the thickness af pile walls not exceeding 12
mm thick or by more than 3 mm for piles where the wall is thicker than 12 mm,
‘When piles of unequal wall thickness are to be butt-welded, the thickness of the
thinner material shall be the criterion.
Pile lengths shall be set up so that the differences in dimensions are matched as
evenly as possible,
10.7.3.3 Matching of Pile Lengiis
Longitudinal shop seam welds and spiral seam welds of lengths of pipe piles
forming a completed pile shall, whenever possible, be evenly staggered.
However, if in order to obiain a satisfactory match of the ends of piles or the
specified straightness, the longitudinal seams or spiral seams are brought
closely to one alignment at the joint, then they shall be staggered by at least
100 mm,
10.7.3.4 Straightness of Piles
For standard rolled sections (he deviation fiom straightness shall be within the
compliance provisions of RS FN 100%4 and in accordance with Suh-section
10.6.3.2.
10.7.3.5 Fabrication of
son.
When pile lengths are to be made up on Site, all test procedures and
dimensional tolerances shall conform to the Specification for the supply of
pipe materials, Adequate facilities shall be provided for supporting and
aligning the lengths of pile.
10.7.3.6 Handling and Storage
All piles within a stack shall be in groups of the same length and on approved
supports. All operations such as handling. transporting and pitching of piles
shall be carried out in a manner such that no damage occurs to piles and their
coatings. Piles that are damaged during handling and transporting shall be
Seba yikes COHN RNa Gove Gene, AMI Gaetan atta Pafected ios
shall be removed from the Site forthwith
61029JKRISP./2010-510
10.7.3.7 Marking of Piles
Each pile shall be clearly marked with white undeletable marking near the pile
head showing its reference number and overall length. In addition, each pile
shall be marked at intervals of 500 mm along its length before being driven.
The length of piles to be supplied shall be as shown on the Drawings subject
to revision by the S.0.
10.7.4 Workmanship,
10.7.
1 Welding Procedures
The Contractor shall submit for approval, full details of the welding
procedures and electrodes with drawings and schedules as may be necessary.
Tests shall be undertaken as may be required by the S.O. and shall be in
accordance with the requirements of BS EN 288.
Al welding procedures shall have been qualified to BS EN ISO 15607, BS EN
ISO 15609-1, BS EN ISO 15613 and BS EN ISO 15614-1 and the Contractor
shall make available full details of the welding procedures and electrodes, with
drawings and schedules a may he necessary Tests shall he undertaken ns may
be required by the S.0.
10.7.4.2 Welders’ Qualifications
All welding works shall be exccuted by qualified welders with valid certificate
issued by approved Authorities such as Pusat Latihan Pengajar & Kemahiran
Lanjutan (CIAST).
Only welders who are qualified to BS EN 287-1 or who have attained a similar
standard shall be employed on the Works. Proof of welders’ proficiency shall be
‘made available on request by the S.0.
3 Weld Testy
During production of welded tube piles, at least one radiograph approximately
300 mm long shall be required on each completed length as a spot check on
weld quality. This shall be taken ou a cincumferential or Tougitudinal weld
and its position shall be as directed by the S.0.
For spirally welded piles, one of the following tests shall be carried out :-
i) For tubes of wall thickness 12 mm or less. three spot check
radiographs, one at cach end of each length of the tube as
‘manufactured and one at a position to be chosen at the time of testing
by the S.0.; and spot check radiographs as required by the $.0, on
the weld joints between strip lengths;
1024JKRISP./2010-S10
ii) For tubes of any wall thickness, continuous ultra-sonic examination
‘over the whole weld, supplemented where necessary by radiographs
to investigate defects revealed by the ultrasonic examination,
Weld tests shall be performed by radiographic or ultrasonic methods as specified.
Provided that satisfactory results are being obtained, one test of a length of
300 mm shall be made for 10% or more of the number of welded splices in the
cease where the load will be carried by the wall or section of the pile will not
normally exceed 10%.
Results shall be made available to the 8.0. within 10 days of completion of the
tests
10.7.44 Standards for Welds
Longitudinal welds in tubular piles
For piles of longitudinal or spiral weld manufacture where the load will be
carried by the wall of the pile, and if the pile will be subject to loads which
induce reversal of stress during or after construction other than driving stresses,
the standard for interpretation of non-destructive testing shall be the American
Petroleum Institute Specification SL. The maximum permissible height of weld
reinforcement shall not exceed 3.2 mm for wall thicknesses not exceeding
12.7 sun and 4.8 nun for wall thickuesses greater than 12.7 sm,
Circumferential welds
For circumferential welds in tubular piles the some maximum height of weld
reinforcement as specified above for longitudinal welds in tubular piles shall
apply, the standard for interpretation of non-destructive testing shall he the
American Petroleum Institute Specification SL.
If the results of any weld (est do not conform to the specified requirements,
‘two additional specimens from the same length of pile shall be tested. In the
« case of failure of one or both of these additional tests, the length of pile
covered by the test shall be rejected.
10.7.5 Protective Coatings
‘The term ‘coating’ shall include the primer and the coats specified.
If protective coutings are specified, dhe preparatin of surfaces and dhe
application of the coatings shall be carried out by skilled labour having
‘experience in the preparation of the coatings specified.
Corrosion protection of permanent steel structure in accordance with
environment classified as C4 according to BS EN ISO 12944-2 shall require
durability resistance of 25 years.
10-25JKRISP/2010-510
The protective canting system shall comply with BS FN 180 12044- and shall
comprise of at least
i) First Coating or Prime Coat Zinc Epoxy of 0.08 mm thick
ii) 2 layers of Intermediate coating of 0.08 mm thick epoxy each layer
iii) Top coating of Polyurethane of 0.08 mm thick
10.7.5.1 Surface Proparation
‘Surface preparation to cleanliness SA 2 % in accordance with BS EN ISO 12944-
4 and BS EN ISO 8501-1
Blast-cleaning shall be done after fabrication. Unless an instantaneous-recovery
blasting machine 1s used, the cleaned steel surtace shall be air-blasted with clean
dry air and vacuum-cleaned or otherwise fieed from abrasive residues and dust
immediately after cleaning,
10.7.5.2 Application and Type of Primer
Immediately after surface preparation, the surface shall be coated with an
approved primer or the specified coating to avoid recontamination. No primer
coat shall be applied to a metal surface which is not thoroughly dry. Within 4
hours alter surface preparation, before visible deterioration takes place, the
aurfaee shall be coated with an appropriate primer or the specified coating.
‘The primer shall be compatible with the specified coating and shall be such that
if subsequent welding or culting is to be carried oul il shill uot emil noxious
fimes ar he detrimental to the welding
10.7.5.3 Control of Humidity During Coating
‘No coating shall be applied when the surface metal temperature is less than 3°C
above the dew point temperature or when the humidity could have an adverse
effect on the coat.
Wheu heating or veutilation is used ty secure suitable conditions (o allow coating
to proceed, care shall be taken to ensure the heating or ventilation of a local
surface docs not have an adverse effect on adjacent surfaces or work already
done,
10.7.5.4 Part to be Welded
‘The coating within 200 mm of a weld shall be applied after welding. The
‘method of application shall comply with the manufacturer's recommendations.
$10.26JKRISPU/2010-S10
10.7.5.5 Thickness, Number and Colour of Coats
The minimum dry film thickness of the finished coating, including the
minimum dry film thickness of each coat and the minimum number of coats
that are to be applied, shall be as specified and shown on the Drawings
Coatings shall be applied in accordance with the manufacturer's instructions,
‘The nominal thickness of the finished coating and each coat shall be as specified
The average coat or finiched coating thicknecs chall be equal to or greater than
the specified nominal thickness. In no ease shall any coat or finished coating be
less than 75% of the nominal thickness. Each coat shall be applied after an
interval that ensures the proper ta dening or eu
of the previous coat,
Where more than one coat is applied to a surface, each coat shall be different
colour trom the previous coat. Lhe colour sequence and final coating colour shall
be established prior to application of coatings.
Inspection of Coatings and Acceptability
The finished coating shall be generally smooth, of a dense and uniform
texture and free from sharp protuberances or pin holes.
Any coat damaged by subsequent processes or which has deteriorated to an
extent such that proper adhesion of the coating may not be obtained or
maintained, shall be recleaned to the original standard and recoated with the
specified sequence of coats.
‘The completed coating shall be checked for thickness and continuity by an
approved magnetic gauge or detector. Areas where the thickness is less than
that specified shall receive approved additional treatment.
When specified, the completed coating shall be checked for adhesion by means
of an adhesion test to BS EN ISO 2409, BS 3900-E6, carried out on 10% of the
piles. The adhesion of any completed couting shall not be worse than
Classification 2. If adhesion tests on the initial batch are satisfactory, then on
further batches 1% of the piles shall be tested, Adhesion tests shall not be carried
‘out until seven (7) days after coating.
10.7.6 Installation of Steel Pipe Piles
10.7.
1 Pitching and Driving of Piles
Pitching and driving of piles shall be in accordance with Sub-Sections 10.3.4.1
and 103.42
10.97JKRISP/2010-S10
10.7.6.2 Lengthening of Piles
Unless otherwise approved, where lengthening of piles is required, the piles
shall be jointed by butt welding along the entire periphery as detailed on the
Drawings.
Redriving of the piles shall only be allowed after the welded joints have
sufficiently air cooled to 100°C or below.
10,7.63 Cutting and Preparation of Pile Heads
When a pile has been driven to the required set or depth and before encasing
in concrete, the pile shall be cut to within 20 mm of the levels shown on the
Drawings and protective coatings shall be removed from the surfaces of the
pile head 100 mm above the soffit of the concrete. Pile heads shall be
constructed (0 details as shown on the Drawings.
10.7.6.4 Conereting of Pile Shaft
If conereting is specified or shown on the Drawings after the pile has been
cut off to the specified level, the shaft shall be filled with concrete in a
continuous operation. The method of placing shall be approved by the S.O.
The reinforcement cage in the pile shall be made sufficiently rigid and kept in
its correct position during concreting,
The length of the reinforcing bars projecting above the pile cut off level shall
be as shown on the Drawings.
10.8 MICROPILES.
10.8.1 Description
This work shall comprise the drilling of a hale, placing of reinforcement unit
and subsequently filling the hole with grout to form micropiles, all in
accordance with this Specification and to the details shown on the Drawings.
10.8.2 Materials
Reinforcement Unit
The type of reinforcement unit to be used. the diameter and/or thickness,
grade, yield strength and working stress shall be as specified or as shown on
the Drawings.
s10.28JKRISPL/2010-510
Grout
Unless otherwise specified, the grout shall be non-shrink cement grout. The
grout mix design such as the water-cement ratio, the minimum cement and
grout strength at 7 and 28 days shall be as specified and shown on the
Drawings.
If admixtures are used, details of admixtures shall be submitted to the $.0. for
approval before commencement of works. The use of the admixture chall
fully comply with the manufacturer's instructions.
10.8.3 Drilling Operations
10.8.3.1 Diameter of Piles
The diameter of piles shall not be less than the specified/designed diameter at
any level throughout its length and shall be in accordance with Sub-Section
10.5.3.1.
10.8.3.2 Drilling
The Contractor shall submit to the $.0. details of drilling equipment and
drilling procedure for approval before commencement of works. Drilling
operations shall be carried out in accordance with the relevant requirements of
Sub-Section 10.5.3.
10.8.4 Grouting Operations
10.8.4.1 Mixing and Placing Grout
‘The Contractor shall provide details of the method and equipment used in
ioul amiaing, Further information such as grouting pressure, grouting
procedure, grouting equipment and techniques employed in grouting
underwater shall also be furnished for approval
Grout shall be mixed on Site and shall be free from segregation, slumping and
bleeding. Grout shall be pumped into its final position in one continuous
operation as soon as possible and in no case more than half an hour after
inixing
10.8.4.2 Testing Grout
Grout shall be tested in accordance with BS EN 12390 and BS EN 196.
Maximum bleed shall be limited to 5%.
If the grout cube as tested failed to satisfy the criteria as prescribed in
specification and drawings, the pile constructed using this batch of grout
shall be rejected. The contractor shall undertake all necessary additional
10-20JKRISPJ/2010-S10
and consequential remedial works to the approval of S.O.
10.8.5 Construction of Pile Heads
10.8.5.1 Lengthening of Piles
Where lengthening is required, the pile reinforcement unit shall be connected
fon Site to the details shown on the Drawings. Other means of jointing
reinforcement shall be to the approval of the $.0.
10.8.5.2 Cutting and Preparation of Pile Heads
Pile heads shall be constructed to the details as shown on the Drawings.
10.9 PILE TESTING
10.9.1 General
In order to verify the working load, the Contractor shall carry out pile load test as,
shown on the Drawings and / or as instructed by the S.0. The Contractor shall
at Teast 48 hours notice of the commencement of construction of any
preliminary pile which is tobe testloaded
‘The design and construction of the load application system shall be satisfactory
for the required test. These details shall be made available prior to the
commencement testing.
10.9.2 Construction of Pile to be Tested
10.9.
1 Notice of Construction
The Contactor shall give at Teast 48 hous notice of commencement of
construction of any preliminary pile which is to be tested.
10,9.2.2 Method of Construction
Each preliminary test pile shall be constructed in a manner similar to that to be
used for the construction of the working piles and by the used of similar
equipment and material. Extra reinforcement and concrete of increase strength
will be permitted in the shafts of preliminary piles where necessary for carrying
out the testing
3 Boring or Driving Record
For each preliminary pile which is to be tested, a detailed record of the conditions
experienced during boring or of the progress during driving, shall be made
available daily, not later than noon on the next working day. Where soil samples
are required to be taken or in-situ tests to be made, the Contractor shall present
the results without delay.
sto-30JKRISPL/2010-S10
10.9.2.4 Concrete Test Cube
‘Three (3) teat cubes shall be made from the concrete used in the preliminary test
pile and from the conerete used for building up the working pile. If the conerete
pile is extended or capped for the purpose of testing, a further three (3) cubes
shall be made trom the corresponding batch of concrete. Ihe cube shall be made
and tested in accordance with Section 9 of this Specification.
The pile test shall not be started until the strength of the cubes taken from the pile
exceed twice the average direct stress in any pile section under the maximum
required test load and the strength of the cubes taken from the pile head or cap
exceed twice the average stress at any point in the pile head or cap under the
same load.
10.9.2.5 Cutoff Level
The cut-off level for the preliminary test pile/working piles shall be a3 specified
on the Drawings or as directed by the S.O.
Where the cut-off level of working piles 1s below the ground level atthe time of
pile instalation and where it is required to carry out a load test from that
Installation level, either allowance shall be made in the determination of the
twice working load for friction which may be developed between the cutoff
level and the exieting ground level, or the piling may be cleeved appropriately or
otherwise protected to eliminate friction which develop over the extended lensth
10.9.2.6 Preparation for Pile Head for Testing
For a pile that is tested in compression, the pile head or cap shall be formed to
give the plane surface which is normal to the axis of the pile, sufficiently large to
accommodate the loading and settlement measuring equipment and adequately
reinforced ot protected to prevent damage trom the concentrated application ot
Toad from the loading equipment.
For a pile that is tested in tension, means shall be provided for transmitting the
‘teat load axially without inducing moments in the pile. The connection between
the pile and the loading equipment shall be constructed in such a manner as to
provide strength equal to the maximum load which is to be applied to the pile
‘during the test with an appropriate factor of safety on the structural design.
10.9.2.7 Supervision
The setting up of pile testing equipment shall be carried out under competent
supervision and the equipment shall be checked to ensure that the setting-up is
satisfactory before the commencement of load test.
All tests shall be carried out only under the direction of an experience and
‘competent supervisor conversant with the test equipment and test procedures. All
personal operating the test equipment shall have been trained in its use. The
Curriculum Vitao of Tester(s) shall be submitted 48 houre prior testing works:
sto.a1JKRISP/2010-510
10.9.3. Protection of Testing Equipment
10.9.3.1 Protection from Weather
‘Throughout the test period, all equipment for measuring load and movement and
‘beams shall be protected from adverse effects of sun, wind and precipitation,
‘Temperature reading shall be taken at the start, end and at the maximum load of
«each loading cycle.
10.9.3.2 Prevention of Disturbance
Construction activities and person who are not involved in the testing processes
shall be kept at a sufficient distance from the test to avoid disturbance to any
unavoidable activity and its effects.
10.9.3.3 Notice of Test
‘The Contractor shall give at least 24 hours notice of the commencement of the
test. No load shall be applied to the test pile before the commencement of the
specified test procedure,
10.9.4 Method of Loading
10.9.4.1 Test Load
The test load shall be applied in one of the following ways: ~
1) By means of a jack which obtains its reaction from kentledge heavier
than the required load;
ii) By means of a jack which obtains its reaction trom tension piles or other
suitable anchors,
In all oases the Contractor shall ensure that when the hydraulic jack and load
measuring device are mounted on the pile head, the whole system shall be stable
up to the maximum load to be applied
If in the course of carrying out a test, any unforeseen occurrence should take
place, further loading shall not be applied until a proper engineering assessment
Of the conditions has been made and steps have been taken to rectify any fault
‘Where au inadequacy in any past of the system might constitute a hazard, means
shall be provided to enable the test to be controlled from a position clear of the
kkentledge stack or test frame.
The hydraulic jack, pump, hoses, pipes, couplings and other apparatus to be
operated under hydraulic pressure shall be capable of withstanding pressure of
1.5 times the maximum pressure used in the test without leaking. Test certificate
shall be submitted before carrying the tes.
The maximnm test nad expressed as a reading on the gauge in use shall he
displayed and all operators shall be made aware of this limit.
10.92JKRISPL/2010-S10
When method (i) is used, care shall be taken to ensure that the centre of gravity
of the kentledge is on the axis of the pile. The nearest edge of the crib supporting
the kentledge stack shall not be closer than 1300 mm to the surface of the test
pile. Kentledge shall not be used for testing raked piles.
‘When method (ii) is used, all anchor piles shall be at a distance of at least three
(3) pile shaft diameters from the test pile, centre to centre, and in no case shall
they be less than 2000 mm from the test pile.
If the anchor piles are to be permanent working piles, their levels shall be
observed during application of the test load to ensure no residual uplift occurs
Alternatively, the Contractor may propose the use of other types, patented or
otherwise, in which case the requirements as below shall be fully complied with.
10.9.4.2 Contractor’s Load Test System
‘The Contractor may propose to use other different types from those specified,
The proposal shall be submitted to the S.O. at least 90 days before the date of
testing. The suitability or adequacy of any system shall be determined by the 8.0.
In the event that the testing system proposed by the Contractor is acceptable, the
Contractor shall obtain a Professional Engineer's endorsement on load settlement
results
10.9.4.3 Measuring Apparatus
The Contractor shall provide apparatus for measuring settlement consisting of a
primary system, at least one auxiliary system, and a network of settlement
reference points. Two fixed independent benchmarks at least 15 metre from the
test site to monitor the settlement reference point shall be established. It desired.
the auxiliary system may also be referenced to these benchmarks. All measuring
devices, scales and reference points with numbers or letters to ensure accurate
data recording ehall be clearly identified,
10.9.4.4 Reference Beams and Displacement Measuring Devices
At least three (3) Linear Variable Differential ‘Transformers (LVDI) and a
Readout Unit are to be used for measuring the displacement. DC/DC-type
displacement transducer having at least 73 mm of travel and a linearity of 0.5 %
or less shall be used. A Readout Unit having a minimum display of 3 digits,
capable of monitoring output from DC/DC — Type LVDT shall be provided.
‘The measurement devices parallel to the longitudinal axis of the test pile and the
axis of load application shall be aligned,
‘An independent reference beam or beams shall be set up to enable measurement
of the movement of the pile to be made to the required accuracy. The supports for
bbeam shall be founded in such a manner and at such a distance from the test pile
and reaction system that movement of the ground do not cause movement of the
reference beam ar beams which will affect the accuracy af the test Embedded
1.93UKRISPJ/2010-S10
the references beam supports at least 3000 mm into the crown at a horizontal
distance of not less than 3000 mm or 10 times pile diameters (whichever is
greatcr) from the closest face of the test pile and from any reaction piles or
supports for the weighted box of platform shall be provided. The beam must be
free to move horizontally at one end,
A clear distance of 150 mm to 300 mm from the test pile to the references beam
or any projection used to support LVDT shall be maintained, The beam and
projections should be at about the same elevation as the attachments to the pile
on which the measuring devices will bear. The LVDT supports to references
beam shall be attached so as to allow the stem of each device to rest on a
attachment to the pile sides. Hardway and pile attachment for [VDT devices
shall be mounted using such materials as brass, aluminium or 303 series stainless
steel, to avoid magnetic interference which the instruments. The pile attachments
aie angles, about 75 mm x 100 mm with the 100 mm dimension projecting from
the pile. For round pile, these attachments shall be placed on the perimeter of the
pile at a 120 degrees and an equal radial distance. For pile of other cross section,
the attachments shall be placed at a convenient location as approved by the 8.0.
Observation of any movements of the reference beam uF beats shall be made
and checking of the movement of the pile head relative to a remote reference
datuin shall be ade and stopped at wianiniunn Tad for each foading,
10.9.4.5 Auxiliary Systems
‘This measuring system shall consist of one or more of the following: wire, mirror
and scale; surveyor's level and target road; or, as altematives, electical or optical
levels.
1) Wire, mirror and scale
Pile movement shall be determined by means of a single strand of wire
drawn in front of graduated seale mounted on a mirror This scale, at
Teast 150 snm long and machine-divided in graduations of 250 um, is
mounted on a 75 mm x 150 mim mirror with metal and glass bonding
adhesive or electrical tape. The mirror shall he attached directly ta the
pile oriented so that the mirror face is parallel to the reference beam. The
mirror shall be mounted to the wire between the ends of the reference
beam, with ove cud fixed and the uther is placed over a pulley with a
‘weight in order to maintain tension. The wire shall be located so that it is,
level and within 20 mm of the mirror face.
ii) Optical levelling method
‘An optical levelling method by reference to a remote datum may be used.
Where a level and levelling rod are used, the level and scale of the
levelling rod shall be chosen to enable readings to be made to within an
accuracy of 0.5 mm. A scale attached to the pile or pile cap may be used
instead of levelling rod. At least two (2) reliable independent datum
10.24JKRISPJ/2010-S10
points shall be established. Each datum point shall be so situated as to
permit a single setting up position of the leve! for all readings.
No datum point shall be located where it can be affected by the test
Joading or other operations on or off the Site
Alternative Systems
Any other type of electrical or optical gauge yielding a precision
equivalent to the primary system is acceptable as and alternative,
provided prior written approval is obtained from the S.O.
10.9.4.6 Measurement of Li
TThe test load shall be measured by a single load cell or proving ring calibrated in
divisions not exceeding 1% of the maximum load to be applied. If an electronic
transducer is used, each reading shall be immediately saved so that in case of
power failure the readings are not lost.
‘The load cell or proving ring shall be calibrated in
Certificate of Calibration shall be made available.
ely prior Wo Ue test aud
All increments of load shall be maintained to within 1% of the specified load.
A spherical seating of appropriate size shall be used to avoid eccentric loading.
Care shall be taken to avoid any risk of buckling of the load application and
teasing systeu, Load ineasusing and application devices shall be in short axial
length in order to secure stability. The Contractor shall ensure that axial loading
is maintained.
The loading equipment shall enable the load to be increased or decreased
simvotlly or W be held constant at any required value.
10.9.4.7 Measurement of Settlement
Settlements shall be measured by use of a reference heam or wire supported
independently of the load test pile, reaction pile or piles supporting reaetion
loads. Settlements shall be measured to the nearest 0.1 mm for reference beams
tor 0.5 smn for reference wites. The reference beam supports shall be located at
least 3 mm from the load test pie, reaction ple or pile supporting reaction loads.
‘The reference beams or wires ahell be protected from the effects of temperature
changes.
10.9.5 Testing Procedure
10.
1 Gene
Maintained Load Tests shall be conducted on test piles as sclected by the §.0.
‘The loading tests shall be carried out in accordance with Sub-Seetion 10.9.5.2.
810-35UKRISPS/2010-510
Prior to the performance of any load test, the Contractor shall submit to the 8.0.
for his approval. working drawings showing the method and equipment he
proposes to use in the performance of the load test and the measurement of
settlements. Such submission shall include design calculations of lateral supports
or other methods to be used in ensuring against buckling. Horizontal supports to
ensure bucking stability shall be provided 10 the pile to be loaded whenever the
ratio of the unsupported height to the least cross-sectional dimension is 20 or
‘more. Horizontal supports shall provide full support without restraining the
vertical movement of the pile in any way.
10.9.5.2 Maintained Load Test
‘The Maintained Load Test shall be carried out as follows: -
i) Te Full Test Load (PTL) on a pile shall be twice the Working Load
(WL) noted on the Drawings and it shall be as specified in Table 10.3 of
thie Specification.
Following each application of an increment of load, the load shall be
‘maintained at the specified value for not less than the period shown in
Table 10.3 and until the measured rate of settlement ina period of
30 minutes is Jess dian 0.5% of the current cumulative setlement which
has occurred, subject to a minimum settlement rate of 0.05 mm in
30 minutes. The rate of settlement shall he calculated from the slope of
the line obtained by plotting values of settlement versus time and