Week 1 - Topic 7 - 1-7 Process Clean Utilities
Week 1 - Topic 7 - 1-7 Process Clean Utilities
Session 1-7
Table of Contents
1 Process Support and Utilities .................................................................... 3
1.1 System Impact Descriptions ............................................................... 3
1.2 System Layout and Routing ................................................................ 5
1.3 Design Considerations ........................................................................ 5
2 References .............................................................................................. 10
If process air has direct contact with the product, the consequence of
exposing the product to oxygen also should be considered. If the impact of the
air is deemed to be critical then pump selections should take this into account.
For example, the use of barriers, etc., on diaphragm pumps should be
considered rather than increasing a utility specification.
Instrument Air
As it is unlikely that instrument air would be in direct contact with the product,
these systems normally should be designed in accordance with GEP.
However, consideration should be given to the need for filtration of exhaust air
to protect classified areas.
Breathing Air
Plant Air
As plant air is normally used to power hydraulic tools, etc., it should not be in
direct contact with the product and these systems should normally be
designed in accordance with GEP. However, consideration should be given to
the need for filtration of exhaust air to protect classified areas.
Heating/Cooling Mediums
Heating and cooling systems,
including steam, cooling and chilled
water, glycol systems, and thermal
fluid systems, normally will not
contact the product and should be
designed in accordance with GEP.
Selection of the heat transfer media
should consider the potential risk of
leakage. Monitoring for system
leakage should be considered. Temperature control module
Clean Steam
Clean steam will usually have a direct impact
on product quality and should be designed,
constructed, commissioned, and qualified to
meet a defined specification. The required
steam quality should be chosen to ensure no
product contamination. Materials of
construction should be 316 Stainless Steel,
having appropriate surface roughness.
Pipework should be passivated prior to use.
The potential for microbial growth should be
eliminated and steam traps should be
minimized; where used they should be of a
hygienic design. However, the distribution
pipe work and equipment to be sanitized
should ensure condensation is removed
adequately to ensure all areas reach the
required temperature for sanitization.
Purified water should be used as feed for the
Clean steam generator clean steam generator.
CIP Systems
The CIP system should ensure no product contamination could occur.
Cleaning chemicals (e.g., detergents) should be removed by subsequent
steps in the cleaning cycle, such as final rinsing using treated water. For multi-
product API facilities, the CIP system should not introduce contamination from
previous cleaning cycles. The materials of construction should be consistent
with the quality specification. The CIP distribution system design should allow
sampling of the CIP stream for qualification and operational purposes.
Vents
Vents not dedicated to one process are a potential source of cross contamination.
The potential for backflow in both normal and abnormal processing conditions should
be given careful consideration to prevent contamination from the environment. This
can occur, e.g., when depressurizing a reactor into a common header system.
Materials of construction for the vent line should be suitable for the service and
resistant to the various vent gases and vapors that may be encountered.
Drains
Drains should be designed to GEP and the appropriate standards. Materials of
construction for drain lines should be suitable for the service and resistant to the
various waste steams the drains will see. It is preferable to design-out the need for
drains in cleanrooms. However, should drains be required, it is typical to have sealed
drains, which are opened only during times of clean down or firewater release.
Where drains are provided in Level III areas, there will be a requirement to sterilize
these as necessary.
Waste Handling
Waste handling systems not dedicated to one process are a potential source of cross
contamination. The potential for backflow in both normal and abnormal processing
conditions should be given careful consideration. Materials of construction for the
waste handling system should be suitable for the waste being handled.
2 References
(2007)