PCS Safety Beacon
PCS Safety Beacon
Process Safety
Sponsored by
CCPS
Supporters Messages for Manufacturing Personnel
http://www.aiche.org/CCPS/Publications/Beacon/index.aspx
October 2007
We Have Liftoff!!!
What happened?
A plant was doing a pneumatic pressure test on a pipe connected to a tank. There was no blind flange between
the piping being tested and the tank. The tank was isolated from the pressurized piping with a closed block valve.
The block valve leaked, allowing the pressure from the pneumatic test to leak into the tank. The tank (which
either did not have a pressure relief device installed, or the pressure relief device was too small) was
overpressured, and it failed at the bottom. The tank lifted into the air and came to rest on the top of the plant.
Isolate equipment from pressure — leave the rockets to the space program!
AIChE © 2007. All rights reserved. Reproduction for non-commercial, educational purposes is encouraged. However, reproduction for the
purpose of resale by anyone other than CCPS is strictly prohibited. Contact us at [email protected] or 212-591-7319.
The Beacon is usually available in Chinese, Danish, Dutch, English, French, German, Gujarati, Hebrew, Hindi, Hungarian, Italian,
Japanese, Korean, Malay, Persian, Portuguese, Russian, Spanish, Swedish, and Thai. For more information, circle 103 on p. 83.