Tandulwadi (Ghat) L.M.I. Tank Balance Work With D.S.R. 2007-2008

The document provides an abstract of work items and costs for balance work on the Tandulwadi L.M.I. Tank. It lists 25 work items with quantities, rates, and amounts. The total cost for all work items is Rs. 59,85,521.00.

Uploaded by

pravin munde
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views2 pages

Tandulwadi (Ghat) L.M.I. Tank Balance Work With D.S.R. 2007-2008

The document provides an abstract of work items and costs for balance work on the Tandulwadi L.M.I. Tank. It lists 25 work items with quantities, rates, and amounts. The total cost for all work items is Rs. 59,85,521.00.

Uploaded by

pravin munde
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

1

Tandulwadi (Ghat) L.M.I. Tank


Balance work with D.S.R. 2007-2008.

ABSTRACT

Qty. Item Particular Rate Amount


1 2 3 4
3136 Item No.1 :- in soft soil 21.50 67424
etc. complete.
117 Item No. 2 :- Providing & filling 366.00 42822
drain with sand etc. complete.
61 Item No.3 :- Providing & filling 366.00 22326
drains with gravel etc. complete
8 Item No. 4 :- Providing & filling 533.00 4264
drains with metal etc.complete
3 Item No. 5 :- Providing & filling 118.00 354
drains with boulder etc. complete
698 Item No.6 :- Providing & consts. 86.05 60063
Rock toe etc. complete
15571 Item No.7 :- Providing 108.20 1684782
Earthwork in hearting zone etc.
complete.
22462 Item No.8 :- Providing 88.70 1381148
Earthwork in casing zone etc.
complete.
462 Item No.9 :- Providing & laying 93.15 43035
0.15m. quarry spoil
7744 Item No.10 :- Providing & laying 51.30 397267
stone revetment etc. complete
115 Item No.11 :- Providing & fixing 241.25 27744
chainage stone along damline
47.66 Item No.12:- Providing laying 3280.50 156349
C.C. grade M-150 etc. complete
792.16 Item No.13 :- Providing & const. 1172.25 928610
U.D.R.S. masonry in C.M. 1:5
complete
5.22 Item No.14 :- Providing & laying 3494.55 18242
R.C.C. M-100 etc. complete
0.5528 Item No.15 :- Providing & fixing 37823.65/MT 20909
M.S.T.S. reinbankment etc.
complete
122.67 Item No. 16 :- Providing cement 109.95 13488
plaster in c.m. 1:2 etc. complete
226.89 Item No. 17 :- Filling included 366 83042
sand filter. etc. complete
2

2.00 Item No. 18 :- Providing & 5525 11050


filling gouge plate
5.76 Item No. 19:- Providing & filling 44947.65 258898
star steel work etc.
100 Item No. 20 :- Excavation in hard 179.15 179150
cum rock by blasting etc.
55.07 Item No.21 :- Providing & laying 1456.15 80190
U.C.R.S. Masonry in cm. etc.
complete.
44.10 Item No. 22 :- Providing Cons. 45.45 2009
pointing in c.m. 1:2 Prop.
110.57 Item No. 23 :- Providing & 3222.75 356339
laying in situ c.c. M-150 etc.
complete
17.50 Item No. 24 :- laying & jointing 287 5023
R.C.C. 900mm. dia Pip etc.
complete.
1216 Item No. 25 :- Filling 15.95 140995
benches with soil etc.
complete.
Total Rs.59,85,521.00

S.A. Deshpande Sub Divisional Officer Executive Engineer,


Sect. Engr. M.I.Sub Division,Beed Beed Minor Irrigation Divn.Beed
H.Q.Ambajogai.