Appendix 8 - Typical Project Execution Plan
Appendix 8 - Typical Project Execution Plan
Project Name:
Client:
Page 1 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
1 PROJECT SUMMARY
2 SUBCONTRACTING
There are portion on this Project that will be subcontracted. Works due to its nature requires Specialize
Contractors to perform it. However, BCC shall employ its own supervisors to oversee and take control of the
works that will be subcontracted.
BCC shall award the Works to a nominated subcontractor through a tendering process. Subcontractors shall be
screened and evaluated to align with the project requirement. BCC is associated with several specialized
subcontractors who have performed similar works in previous projects.
BCC shall submit to CLIENT the profiles of these nominated subcontractors for their approval prior to award of
any subcontract works. Final selection shall be done based on their technical & commercial capabilities as well
as their previous track records.
2.1.1.2 Scope
This Subcontract Plan is applicable to all phases of the project. BCC and all subcontractors will adhere to
the approach outlined in this document. The approach to managing the subcontractors will be based on
the following guidelines:
• A project office will be established to effectively support the needs of the subcontractors
• Effective channels of communications will be clearly defined and established
• A Statement of Work will be developed jointly by BCC with each subcontractor taking responsibility for
deliverables and services outlined in its areas of responsibility
• Subcontractor will have its responsibilities and authorities clearly defined in the Statement of Work
• Subcontractor will have its deliverables identified and required content clearly specified in the
Statement of Work
• Subcontractor will have the services it is responsible for providing clearly identified and described in
the Statement of Work
Page 2 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
• All constraint imposed on the subcontractor will be clearly identified in the Statement of Work,
including the schedule and budget constraints
• Subcontractor will have requirements for quality clearly identified to it in the Statement of Work,
including the requirement to allow independent quality inspections of materials and processes
• All products and services provided by the subcontractor will be subject to the acceptance of BCC and
the CLIENT.
• Subcontract will contain appropriate terms and conditions
• Adequate facilities will be provided to meet the needs of the subcontractors
2.1.2 SUBCONTRACT MANAGEMENT
2.1.2.1 Management
Clear and unambiguous subcontracts will be established. Subcontractors will have a legally binding, written
contract that defines the parties involved, the scope of the contracted work, the appropriate terms and
conditions which will be imposed on both BCC and the subcontractor and the final acceptance process.
The work of subcontractor will be coordinated by BCC to assure that the efforts of all parties are integrated
into a cohesive whole. A Project Master Schedule will be developed that establishes schedule constraints
and identifies contractual and significant internal milestones. Intermediate schedules will be established
that clearly show key project interfaces and the interdependencies of the work efforts. Meetings will be
conducted on a regular basis to provide visibility into work being performed.
Subcontractor will have a single point of contact with BCC for contractual matters. The subcontractors are
expected to identify their own single point of contact for contractual matters. Subcontractor personnel will
be free to interact with BCC personnel as needed to fulfil the subcontract.
Subcontractor organization will identify the responsibilities and authorities of their project staff. This
information will be published in a project contact sheet. Informal, mutually beneficial contact is
encouraged. However, to avoid schedule slippage, the interdependencies of subcontractor efforts will be
identified on the intermediate schedules. These intermediate schedules will make the formal interfaces
visible.
BCC will prepare a WBS Level Progress Report for submission to CLIENT. A copy will be provided to
subcontractors. This report will present the progress of WBS elements expressed as a percentage complete
and an indication of whether the work is ahead of or behind schedule.
2.1.2.3 Review
Clear points of visibility into the work that the subcontractors are doing is crucial to reducing the risk of
inappropriate work being done resulting in unplanned, costly rework. These points of visibility are
established at regular periodic intervals and at key project milestones.
On an as-needed basis, BCC may request an informal review of subcontractor progress. This would involve
discussions with the subcontractor’s Functional Manager or the subcontractor’s point of contact for
contractual matters. These reviews will be held at the request of the Project Manager. They will only be
Page 3 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
requested if cost or schedule variance exceeds the threshold identified in the Standard and Procedure
Manual.
Every two weeks, the Project Manager will meet with representative of the subcontractor organization to
discuss issues of concern to either party. The subcontractor representative is usually a senior or
intermediate employee of the subcontractor who is not directly involve in the delivery of the products and
services.
At key contractual milestones, a formal review will be conducted to provide visibility into the direction of
the project to all parties. Topics covered depend on the milestone but could include the overall project
schedule, an overview presentation of the key points contained in the project deliverables, a briefing on
the quality of work achieve date, a briefing on the budget and schedule status or a briefing on the current
configuration status.
2.1.3 ACCEPTANCE
2.1.3.1 Acceptance by BCC
All products and services provided by the subcontractors will be subject to approval by BCC.
BCC Quality Assurance staff will review all subcontractor deliverables for adherence to content
requirements and standards. Evaluation criteria used by the Quality Assurance staff are published and
documented. This evaluation will identify any significant deficiencies that would preclude the acceptance
of the deliverable. The identified deficiency must be addressed to the satisfaction of the Quality Assurance
staff.
When the deliverable is deemed to be acceptable by BCC, it will be signed by the Project Manager. The
deliverable will then be submitted to the CLIENT for their final acceptance.
CLIENT will review project deliverables (including subcontractor deliverables). CLIENT will coordinate
review comments and identify any significant deficiencies that would preclude the acceptance of the
deliverable. The identified deficiencies must be addressed to the satisfaction of CLIENT.
Subcontractor invoices must meet the format and content requirements for invoices as set out in the
Terms and Conditions of the contract between BCC and the subcontractor.
Subcontractors will submit monthly invoices reflecting the area accomplished on the project. If no
deliverables were included in the efforts for that invoice period, payment will proceed. If a deliverable is
included in the invoice period, payment of that invoice will be subject to the acceptance of the deliverable
product by both BCC and the CLIENT. When the deliverable is accepted by BCC and the CLIENT, payment of
subcontractor invoices will be authorized.
Page 4 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
3 MATERIALS PROCUREMENT
The Materials Procurement Strategy describes the potential strategies for the different procurement options
available in this project. The Materials Procurement Plan addresses project material requirements, their
procurement and movement will define the proposed procurement and traffic responsibilities of the CLIENT
and BCC.
• Commercial Department shall consolidate the material take-off from the drawings, and prepare the
material requisition indicating the material description, unit, quantity and other specifications, data
sheets, etc.
• Prepare the complete bid package with the commercial terms and conditions, instruction to bidders
(Vendors) and any technical descriptions of the materials and documents to be provided. This shall
also include Spare parts requirements, Capital Spares (if applicable), Non-material Requirements and
relevant QA/QC documents.
• Forward inquiries to Bidders (Vendors) and answer immediately their queries and clarifications.
• Expedite the Bidders (Vendors) to submit their quotations on time (date as provided in the RFQ).
• Host pre-bid vendor conference if required to clarify the technical issues and queries for engineering
and complex equipment.
• Joint meeting with Vendor, Project, and Discipline Engineers, to match the technical conformity of the
offered material/equipment. If the vendor’s technical offer conforms to the specific requirements,
Engineering Department will approve the Vendor’s Technical Proposal.
• Transmit to vendors any additional information and/or clarification that are not cleared nor complied
in the MR/RFQ requirements.
• Receive the commercial bids and evaluate the suitable bid considering the project schedule
requirements and the price, and place LOI or PO to the successful bidder.
• Issue the unpriced vendor acknowledge PO to CLIENT for review, approval, and records.
• If requested by CLIENT, the technical bids and the technical evaluations done therein will be issued for
review, approval, and records.
• Expedite the fabrication and delivery of items, and to transport the items to site warehouse or to site,
for storage, consumption, or installation.
3.1.1 Material Substitution
For any proposed material substitution on cases the required specifications are not available in the market,
BCC will follow the process (as described in the Procurement Plan) for the procurement of the equivalent
and CLIENT’s approved substitute. Necessary approval as required by the CLIENT will be processed and
obtained by BCC insourcing such substitutes.
Page 5 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
The long lead items will be processed first, since the delivery of such equipment/items is expected to take
more than 24-28 weeks, and the items mostly li on the critical path, and such items require monitoring and
control to avoid any slippage in the schedule delivery. Procurement department shall float advance RFQ’s for
such items, without waiting for formal approved PR submittal reviewed and approved by the CLIENT.
The critical items are those which are processes next, however the exact specification and quantities may be
not firmed up till the date of IFC issue, such items will be processed only to the stage of draft PO issue, the
firm PO will be issued after the specification and quantities are firmed up.
The bulk materials will normally be processed after the issue of IFC, such materials are mostly available ex-
stock, off-the shelves or with considerably less delivery times up to 6-8 weeks.
3.1.7 Expediting
BCC shall ensure that the Inspectors of the CLIENT shall have a free access to BCC’s and its Vendor’s offices
and works. During expediting, BCC shall be responsible for giving complete and reliable information on the
Purchase Order status. The information will include shipping schedule, issuance and progress status of any
orders, critical orders, and the expected arrival dates.
4 PROJECT SCHEDULING
Page 6 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
4.1.2 Responsibilities
BCC Project Control Department shall be responsible for planning and scheduling of work activities and
required resources in the construction execution and mechanical completion of the contract activities based
on the Project Critical Milestone Dates as shown in Contract Requirements. BCC Planner or Scheduling
Engineer shall coordinate with the CLIENT for any changes on schedules in the work phase and shall make
adjustment/updating on the current project situation. He shall also be responsible for periodical progress
reporting, schedule updating and to include delay analysis if setbacks on schedules are encountered during
the contract execution. Any revisions to the Project Schedule shall be subject to approval by the CLIENT.
4.1.3 Methodology
For an effective control of project activities, the Planning and Scheduling Unit will be using the aid of
MICROSOFT EXCEL or PRIMAVERA PROJECT PLANNER SOFTWARE for the preparation of computer operated
CPM and BAR Chart Schedules as time saving and useful tool in Project Management. The planning phase
involves the listing of task of job, which must be performed to bring about the completion of the project
milestones. Resource requirements for materials, equipment and manpower are determined in this phase
and duration for each is made. Scheduling is done by interconnecting of all necessary activities of the project
in the logical order as input to the Computer Software Program with its corresponding early and late
occurrences of start and finish dates and the computer handles processing of the data. Control is a function,
which is a periodical review of the difference between schedule and the actual performance as the aspect of
review and evaluation and pursuing corrective actions to prevent overall delay impact to Project Target
Critical Milestone Dates.
BCC Work Schedule shall be comprised of separable portions or aggregated levels of detail of the integrated
network as follow:
Specific Construction Work Breakdown Structure (WBS) shall be prepared by the Planning & Scheduling
Engineer and submitted to the CLIENT for review and approval, as basis of progress evaluation and reporting.
The summarized proposed work schedule for the execution of this project is attached in this document. The
schedule shown reflects the planned time required for completing various activities of the project within the
Key Milestone requirements of the CLIENT.
Page 7 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
4.2 PROGRESS MEASUREMENT AND SCHEDULE CONTROL
BCC’s Project Control Department shall ensure accurate progress measurement and effective schedule control
throughout the project life. They will address/monitor issues regarding work breakdown structure, progress
reporting system, progress measurement and schedule control, and Critical Path Method (CPM) scheduling
requirements.
BCC will carry out progress measurement in accordance with the project schedule. BCC will prepare the
progress report based on the progress measurement system described in Work Breakdown Structure. The
completion of the weighted activities within their level in the appropriate phases (Engineering, Procurement,
and Construction) will form the basis for the performance measurement at the desired levels.
The execution of this Project requires a flexible organization able to ensure comprehensive and consistent
management, planning and control of all aspects of the work.
Page 8 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
The Organizational Chart relevant to Site Activities will be submitted separately. A description of the site
organization functions as well as key personnel roles and responsibilities are presented in the following
paragraphs.
• Representing BCC to the CLIENT, Licensors, Partners and Vendors, and managing all the contractual
aspects.
• Ensuring the review of contractual documents.
• Defining project strategies (Project Execution Plan, Quality Plans, Procurement and Contracting Plan,
Economic Risk Plan, Project Coordination and HSE plans) and supervising the planning and
scheduling of activities.
• Overseeing the project’s cost and time controls through the project organization positions, taking the
necessary actions to achieve the time and mark-up targets established.
• Supervising site activities.
• Supervising project activities regarding aspects relating to quality, health, safety, and environmental
protection, through the project organization positions.
• Ensuring project progress reports, including the financial budget.
• Ensuring project feedback and issuing the project Final Report,
• Moreover, the Project Manager role includes ensuring customer service during the warranty period.
• Ensuring the review of contractual documents.
• Ensuring, during Construction & procurement phase, and relying on the expertise and knowledge of
the Construction Manager, Field Engineering Manager and Project Control Manager, that the
construction organization and planning and on-site commissioning activities are performed, liaising
for this purpose with the other organizations and functions involved in implementing the project.
• Ensuring, insofar as within remit, cost, and time control activities, taking the necessary actions to
achieve the established time and mark-up targets.
• Supervising, insofar as within remit, project activities for aspects pertaining to quality, health, safety,
and environmental protection, through project organization positions.
• Supervising the performance of works on-site.
• Ensuring the application and, where not already arranged in the planning phase, the issue of suitable
procedures for the definition of working methods and site regulations.
• Approving HSE Manuals for construction and commissioning, ensuring their implementation.
• Ensuring the implementation of the Site Quality Control Plan.
• Ensuring compliance with local laws and regulations.
• Ensuring the issue of the Completion Certificates required by contract.
• Ensuring the issue of the plant handover certificate.
• Help the CLIENT during the warranty period.
5.1.2 Construction Manager
The Construction Manager ensures the performance of construction activities carried out on a direct hiring
basis or manages the construction and assembly works to be carried out by BCC, ensuring that time; cost,
quality, health, safety, and environmental protection requirements for the construction activities are met.
Duties include:
Page 9 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
• Participating in project planning and scheduling, liaising for this purpose with other organizations and
functions involved in executing the project and assuring the most suitable solutions in terms of
assembly sequences, works scheduling, constructability, feasibility, etc.
• Preparing and keeping up to date, in accordance with other project plans and schedules, the General
and Executive Plan for construction, defining construction methods, logistics, activity scheduling,
control tools and methods.
• Ensuring implementation for the project of computer systems for the management and control of Site
activities.
• Participating in project review meetings to make sure that construction requirements have been duly
complied with.
• Participating in the preparation of the general HSE Plan, the HSE Plan for the construction and the HSE
Manual for the activities within own area of responsibility.
• Defining personnel mobilization.
• Checking that the procedures defined for Site activities are applied.
• Coordinating and supervising the works carried out on a direct hiring basis or by vendors and ensuring
their accounting, using the services of the Discipline Superintendent positions.
• Checking construction progress weekly, identifying any critical aspects and, where construction
activities are sub-contracted, requesting the necessary actions from the vendors concerned.
• Assisting the Project Manager in verifying and updating works feasibility.
• Ensuring the preparation of work progress reports for the aspects related to the quality of the works
carried out.
• Ensuring the achievement of the mechanical completion objective.
• Assisting the Commissioning Manager during commissioning and start-up phases.
5.1.3 QA/QC Manager
See BCC-TEN-PQP-xxx “Project Quality Plan”
• Collaborating with the Construction Project Manager on the definition of tools and procedures for
detailed scheduling and for monitoring work progress and costs.
• Ensuring the application of above systems on the field.
• Collecting and analysing the data of BCC & vendors activities, pointing out possible problems related to
time and costs.
• Assisting the management in the evaluation of the impact of possible changes on schedule and budget
and in the definition of actions to be taken to minimise or prevent delays.
• Analysing cost tendencies and proposal to minimise construction costs.
• Preparing the general report on work progress for the construction activities, in collaboration with the
other positions interested.
• Maintaining contacts with the Head Office Project Organisation.
• Collecting the documentation regarding change works which influence time and costs.
5.1.5 HSE Manager
See BCC-TEN-HSE-xxx “Health, Safety & Environmental Plan”
Page 10 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
• Ensuring the activities of documents management on Site, managing, and checking the conformity of
technical documentation received from Head Office, making it available to the Site Engineers and
keeping a record of the changes and additions made to the documents, because of construction and
commissioning requirements, until the “as built” drawings are prepared.
• Where necessary, sending proposed design modifications to the competent head office
department/positions for approval, before carrying out the work.
• Notifying the competent head office department/positions of changes made to the documents due to
Site requirements (construction and commissioning).
• Ensuring the analysis of engineering, materials and construction non-conformities encountered on Site
and assuring, where necessary, the involvement of the competent head office
departments/positions in the determination and approval of corrective action/back charges.
• Analysing the technical aspects of the feasibility of the construction work, providing information on
the actual on-Site availability of documents and materials. For this activity, the Field Engineering
Manager is supported by the Discipline Superintendents and by information available on the
Contractor computer system.
• Preparing the “Site query procedure” and coordinating the resolution.
• Coordinating engineering activities for Site procurement.
• Maintaining contact with material suppliers and, liaising with the Construction Manager and
Commissioning Manager, ensuring that suppliers are present during the plant construction, pre-
commissioning, and commissioning phase; ensuring the preparation of the monthly progress to be
submitted for approval to the Project Manager.
5.1.7 Site Engineer
Manages the activity on site (usually operating in the same technical field), to ensure that the established
quality requirements, costs, and schedule are met. These position’s tasks include:
• Participating in the preparation and up-dating of construction plans and schedule for the activities of
his competence.
• Verifying and ensuring the availability and adequacy of technical documents and materials to be
delivered to the BIDDER to carry out the scheduled work, providing for expediting or proposing
corrective actions when necessary.
• Co-ordinating the activities to be carried out by manpower and the various Vendors, consistently with
the other activities, and ensuring proper necessary technical supervision.
• Systematically measuring the amount of work carried out by BCC and monitoring any deviations with
respect to the established schedule.
• Ensuring the bookkeeping and accounting and verifying the work progress/amount of works prepared
by BCC.
• Verifying the availability and adequacy of the resources and facilities available with respect to the
programs to be completed and controlling the BCC productivity, promoting corrective actions when
necessary.
• Ensuring the proper disposition of the non-conformities with the assistance of specialists from the
Head Office when necessary.
• Ensuring the co-ordination of Supplier's representatives.
• Pointing out to management any problems or deviations which he cannot solve, proposing possible
solutions.
• Assisting management in the administration of claims and new prices with BCC.
• Assisting management in contacts with the CLIENT representatives, when necessary.
• Checking procedures and equipment to be used in tests, controls and inspections and agreeing on the
applicable operating procedures with the organization in charge of the works.
• Ensuring the availability of updated inspection, control, and test reports, for the purpose of approvals
of mechanically completed plant systems.
Page 11 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
• Attending the tests, controls and inspections carried out by BCC, checking conformity with the Site
Quality Control Plan, and obtaining the relevant documentation, including that required by European
Directives (where applicable).
• Helping with the systematic collection of lessons learned on the individual Site.
BCC will prepare a “Project Management Interface Plan” that will effectively handle these interfaces
throughout the project life cycle. This plan will identify and detail the interfaces among existing and new
facilities and among contractors. It will provide oversight of the interaction and information flow between the
major contractors. The main component of the document includes the following:
• Project Information
• Contractor Scope of Works and Interfaces
• Interface Roles & Responsibilities
• Master Interface Register
• Interface Management Process
• Tools for Interface Management
6 PROJECT SAFETY
BCC has a strong Accident Prevention Program and Management leadership that makes a difference in Health
and Safety. At BCC, we are committed to safety above all else, and this commitment is the centre of everything
we do. Our proactive approach creates value for our clients and safeguards our most important asset which are
our employees. Our entire team is dedicated to maintaining a safety-focused and environmentally sound
business; our safety culture is promoted by each member of our team through planning, implementing, and
evaluating safety practices daily.
BCC safety program is proactive and action-oriented; everyone from management to trades people are involved
in making a zero-incident workplace a reality. We use daily pre-task planning sessions, ongoing safety
inspections, weekly safety meetings, safety seminars, special equipment training, safety manual reviews and
email updates to assist in attaining our goal of zero incidents.
BCC supervisors receive trainings and seminars in Fall Protection, Excavation and Trenching, First Aid, and
Confined Space Entry Procedures, Substance Abuse Awareness and Recognition. New employees are required
to complete our New Hire Safety Orientation Program. Our substance abuse program includes Pre-hire, Post
Accident, Fitness for Duty, For Cause and Random Drug and Alcohol Testing. All employees, including
management, are subject to random testing equal to 25% of our annual workforce.
Our safety culture at BCC focuses on keeping motivational messages and emotions at the forefront of
everything we do – every day. Family oriented messages remind us to keep safety at the top of our minds with
poster and banners placed throughout our projects. Bringing our families to the jobsites with this visual
reminder positively impacts how we approach and value safety. Our goal continues to be ZERO ACCIDENTS.
The overall responsibility for Health, Safety & Environment rests at the highest level, however, all individual
employees have important responsibility towards it and must participate in carrying out the following:
Page 12 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
• Comply with all regulations governing Health, Safety & Environment at the job site.
• To take convenient and practical actions to correct or isolate unsafe conditions or work practices.
• To promote Health, Safety & Environment awareness.
• Hold each employee accountable for their individual responsibility to Health, Safety & Environment.
• To assure that employees will accomplish the safe completion of assigned tasks.
• That no task is so important that we cannot take the time to do it safe.
• Protecting of environment by removing all hazardous wastes and by proper housekeeping.
Kindly see Project HSE Plan for a detail information of BCC’s HSE program for this Project.
8 CONSTRUCTION
This addresses project concerns where corresponding plans of action or solutions have not been completely
defined. Concerns for project delivery should be addresses by Project Risk Management, including any unusual
efforts or procedures required for successful project completion. Areas of Concern related to external interfaces
and engineering or operational issues that may affect the resulting capability provided by the project are
highlighted below:
8.1 MOBILIZATION
Mobilization of Construction Management personnel is one of the critical stages of the project. It involves
sourcing and deployment of qualified personnel who are experienced and capable of executing the job.
The Construction Management team will be responsible for the efficient and successful execution of
construction activities. Proper management of allocated and required resources shall be done in consideration
of all components of construction in terms of scope, quality and timely completion whilst complying with
Contractor policies and statutory requirements on business principles, health, safety, and environment. The
team will define the overall objectives in these areas and set the targets to assure timely completion of the
project.
Equipment’s to be deployed shall be certified by a third party in accordance with the CLIENT requirements and
standards. A dedicated team shall handle the processing of all required documents and certifications required
Page 13 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
in accordance with the requirement of the CLIENT. A dedicated equipment supervisor will be assigned at the
project site to supervise the maintenance and repair works of equipment, and to ensure available equipment
is in good operating condition.
• Manpower Camp
• Site Offices
• Laydown Yard
The TCF shall be removed at contract completion and areas will be reinstated to original conditions.
Lay-down area shall be maintained clean and organized to keep the material in safely and correct manner.
Wooden pallets or racks will be used to support rebars, plywoods, pvc pipes, etc. to avoid contact with the
ground. Material kept in open shall be covered with tarpaulin sheets to avoid direct exposure to weather.
• First Aid, Ambulance, and medical service as per HSE Plan as required under this contract at Camp
Accommodation, office, and work site.
• Site area lighting during night shifts.
• Fire prevention and firefighting services.
• Construction site sanitary and hygiene arrangements.
Construction activities likewise shall be executed as per the construction master schedule which will be
prepared and submitted for Contractor approval.
Page 14 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
During Construction, Site Engineers and Inspectors check all work for conformity to specifications, drawings,
Contract documents, workmanship, and material suitability.
• BCC shall carry on all the necessary clearing, grubbing and demolition (if applicable) within the site area.
Unnecessary materials shall be removed from site. We confirm that such works shall start after site
possession and securing of the related approval and permits.
• Protection of the working area by providing barricades and signage to properly direct worker and
equipment and avoid untoward incidents.
• Survey control points will be inspected and verified data shall be transmitted to BCC by the CLIENT. BCC
then develops temporary control points to mark the alignment of the baselines in area in compliance to
schedule. Marking will be established by the surveyors using the survey control points to identify the
exact locations and measurement of the required excavation.
• Excavation will be done as per excavation Method statement which shall be submitted for CLIENT
approval. Excavation shall be done to the lines and grades or elevation, as indicated in the IFC Drawings.
Excavated material shall be used for backfilling providing it passes the required tests. Unsuitable
material shall be removed and be replaced by suitable one.
• Dewatering (if necessary) shall be done via submersible pumps in wells distributed around the perimeter
of the excavation. Water will be pumped to the near by evaporation pond. Dewatering shall be
subcontracted to a Professional Specialist.
• Blinding concrete, membranes, or such other protection as specified on the drawings shall be placed
following the completion of excavation and compaction works, clearing the soil tests and as soon as it is
approved by the QC Inspector.
• Waterproofing shall be done by a Specialized Subcontractor using materials approved by the CLIENT. The
waterproofing activities are mainly in the foundation stage, wherever the concrete touches surrounding
soil and on the roof.
• Foundations and building works. Substructure works will be divided into different areas. Those areas will
be separated by construction joints and therefore can follow different schedule of work once they reach
the superstructure level.
Method of statement for concrete works shall be prepared prior to any concrete pouring and shall be
approved by the CLIENT.
QA/QC procedure covering all the activities related to the concrete works shall be submitted to the
CLIENT for approval. BCC will provide to the CLIENT all the sampling and testing activities carried out in
the field and/or in the laboratory.
A bar bending schedule shall be submitted to CLIENT for approval. The number, size, form, and position
of all steel reinforcing bars, ties, links, stirrups, and other part of the reinforcement are to be in
accordance with the drawings and kept in the correct position in the forms without displacement during
the process of vibrating, tamping, and ramming the concrete in place. The approved spacers shall be
used during the process. The concrete cover shall not exceed tolerance unless particularly otherwise
specified.
Formworks shall be made of conventional wooden or steel forms. Formworks shall be prepared for
concrete placing after the control of axes, elevation, alignment, and the necessary strengthening have
Page 15 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
been carried out. All formworks’ systems shall be strengthened by scaffoldings and working platforms.
The CLIENT shall approve the works.
Backfilling will be made on top of foundations to bring the construction to the required levels, prior to
proceeding with the different floor plans.
• Precast hollow core panels and beams will be subcontracted to a specialist company, following approval
by the CLIENT. The Subcontractor shall supply and erect the precast items with the assistance of BCC
personnel. Some of the works will be erected by Large Cranes and the rest with long reach, properly
sized Mobile Cranes. QA/QC procedure covering all the activities related to the precast concrete works
shall be submitted to CLIENT for approval.
• All Architectural, sundry, and finishing works shall be installed/constructed in accordance with the
approved finishing schedules and materials. Selection of finishing materials will be based on the
requirements of the Project.
• Electrical, Plumbing, and Mechanical rough ins shall be in accordance with the drawings. Piping layouts,
raceways as well as all necessary support and fittings for these services shall be as per the project
standards and specifications. These services rough ins shall be installed by a skilled technician.
Coordination with different discipline is needed in performing this works.
All cables and pipes shall be laid according to the schedules indicated in the drawings. Fixtures and
equipment shall be in accordance with the project specifications and is approved by the CLIENT.
Installation, testing and commissioning shall be under the direct supervision of the Discipline Engineer.
• Landscape, roads, curbstones, sidewalks and other external works shall start once the building is erected
and equipment are installed and the need for large mobile cranes is over.
The work activities described above are not intended to be either complete or in strict sequence of
operations but only as a guide to the overall planning and scheduling operations.
8.4 DEMOBILIZATION
BCC shall, on completion of the project demobilize the manpower, equipment, and surplus material.
Demobilization shall be done strategically by:
Page 16 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
• Relocation or reassignment of direct & indirect manpower
• Removal of all temporary structures and temporary installations.
• Removal of all tools and equipment and the property of BCC and their sub-contractors.
• Return of all Saudi Aramco tools and equipment if any
• Return of any excess Saudi Aramco materials if any.
• Return of all Saudi Aramco Security Passes.
• Removal and disposal, at the relevant disposal site, of any waste and the cleaning of the work areas.
The development and execution of the Pre-commissioning and Mechanical Completion Plan is the responsibility
of the Project Manager with inputs from Inspection, Proponent, etc. The Project Manager is to provide
oversight to ensure that planning is performed as activity that is planned and tracked.
The main components of the Pre-commissioning and Mechanical Completion Plan include the following:
• Detailed Pre-commissioning Schedule illustrating all major pre-commissioning activities and their timing
and duration (to be aligned with the tail-end construction schedule).
• Pre-commissioning procedures for all testing and inspection required under the mechanical completion
checklist for each system, including the applicable pre-commissioning forms. The procedure should
cover all disciplines (for example buildings, electrical system, instrumentation, mechanical systems, etc.).
• Identification of the Mechanical Completion Packages, which describe the limit and scope of the system.
This is to include drawings that indicate the system boundaries and isolation locations.
• Vendor Representative Requirements.
• Master of the Punch List/Exception Item List Database
• Pre-commissioning Status Tracking System
• System Turnover Sequence – Provides a conceptual plan of the breakdown of the facility into systems
and the sequence in which these systems will be checked out and turned over to the Proponent. Also,
this must include specific plans to implement Partial Mechanical Completion, if applicable.
• Project Manager
The Project Manager shall implement this lesson learned reporting procedure and review for further
improvements.
• Department Heads
Page 17 of 18
PROJECT NAME: CLIENT:
LOCATION:
DATE:
DOC NO: BCC-TEN-PEP-xxx REV NO: 00
The department heads of the project organization shall participate in the lesson learned discussion
and bring all the important experience whether successful or not successful to be recorded and shall
serve as guidelines in other future projects.
• Site Engineers/Supervisors/Foremen
The Site Engineers, supervisors and foremen are the frontliners in the field, they shall bring first-hand
information and detailed experience which are very essential to record in the lesson learned report.
Participants of a lessons learned session are typically the Project Manager and project team. It may also
include the Client or Vendors as appropriate.
Lessons learned are captured so they ultimately become part of a historical database for both the project
and other BCC projects.
Page 18 of 18