BILLING NO.2 - Daanlungsod-Calangahan Detailed

1) This report provides an update on the concreting and road improvement project on the Daan Lungsod-Calangahan Road in Tuburan, Cebu from August 1 to September 30, 2021. 2) The contractor, April Rose Enterprise & Builders, has completed PHP 9.7 million worth of work to date against the revised contract amount of PHP 47.9 million. 3) Significant work accomplished this period includes the excavation of 8,069 cubic meters of surplus soft rock and the construction of 445 square meters of unreinforced Portland cement concrete pavement.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
102 views1 page

BILLING NO.2 - Daanlungsod-Calangahan Detailed

1) This report provides an update on the concreting and road improvement project on the Daan Lungsod-Calangahan Road in Tuburan, Cebu from August 1 to September 30, 2021. 2) The contractor, April Rose Enterprise & Builders, has completed PHP 9.7 million worth of work to date against the revised contract amount of PHP 47.9 million. 3) Significant work accomplished this period includes the excavation of 8,069 cubic meters of surplus soft rock and the construction of 445 square meters of unreinforced Portland cement concrete pavement.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

REPUBLIC OF THE PHILIPPINES

PROVINCE OF CEBU
OFFICE OF THE PROVINCIAL ENGINEER
CEBU CAPITOL,CEBU CITY
Project Name : Concreting/Improvement of Daan Lungsod- Calangahan Road Section
Location : Tuburan, Cebu Accomplishment Report No. 2
Contractor : April Rose Enterprise & Builders Period Covered: Augist 1 - September 30, 2021
Contract Amount : Php 47,977,390.11 Original Contract Duration 184 Calendar Days
Revised Vontract Amount Php 47,945,925.58
DETAILED ACCOMPLISHMENT REPORT

REVISED CONTRACT PREVIOUS THIS PERIOD TO DATE


ITEM NO. DESCRIPTION
UNIT QUANTITY UNIT COST AMOUNT WT% QTY AMOUNT QTY AMOUNT QTY AMOUNT
A.I.1(6) Provision of Combined Field Office, Laboratory, and Living Quarters Building for the Engineer (Rental Basis) MONTH 6.13 6,783.69 41,584.00 0.09 1.10 7,458.00 2.07 14,012.00 3.16 21,470.00
B.4(I) Construction Survey and Staking ("As-staked" Survey) KM. 4.00 36,741.95 146,967.80 0.31 3.00 110,225.85 - 110,225.85
B.5 Project Billboard / Signed Board EACH 2.00 8,640.89 17,281.77 0.04 2.00 17,281.77 - 17,281.77
B.7(2) Occupational Safety & Health Program LUMP SUM 1.00 80,614.20 80,614.20 0.17 0.18 14,457.98 0.34 27,163.48 0.52 41,621.46
B.8(1) Traffic Managemant MONTH 3.07 14,943.97 45,878.00 0.10 0.55 8,228.12 1.03 15,458.89 1.59 23,687.01
B.9 Mobilization / Demobilization LUMP SUM 1.00 32,792.60 32,792.60 0.07 0.50 16,396.30 - 16,396.30
100(I) Clearing & Grubbing (Incld'g. disposal of waste mat'ls.) hec 0.87 341,625.00 296,530.50 0.62 0.25 85,406.25 0.12 40,995.00 0.37 126,401.25
101(3)c1 Removal of Actual Structures / Obstructions, 0.05m.thk. ACP (Existing Dilapidated / Damaged Old Asphalt Pavement.) SQ.M. 9,156.66 212.60 1,946,710.54 4.06 2,520.00 535,753.13 1,750.00 372,050.78 4,270.00 907,803.91
102(2) Surplus Common Excavation CU.M. 6,787.99 310.97 2,110,889.87 4.40 10,740.75 3,340,097.54 (3,952.76) (1,229,207.83) 6,787.99 2,110,889.72
103(1)a Structure Excavation (Common Soil) CU.M. 1,205.40 283.31 341,503.53 0.71 272.50 77,202.60 30.80 8,726.02 303.30 85,928.62
104(2)a Embankment from Borrow (Common Soil) CU.M. 2,385.34 430.81 1,027,637.80 2.14 110.27 47,505.96 - 110.27 47,505.96
105(1)a Subgrade Preparation (Common Material) SQ.M. 22,680.00 34.37 779,483.25 1.63 6,642.00 228,277.24 - 6,642.00 228,277.24
200(1) Aggregate Sub-base Course, (Shoulders/Carriageway Levelling Coarse Only) CU.M. 966.00 983.77 950,321.17 1.98 55.20 54,304.07 - 55.20 54,304.07
201(1) Aggregate Base Course, 200 mm thk. CU.M. 3,976.00 1,177.76 4,682,765.06 9.77 994.00 1,170,691.27 103.66 122,086.37 1,097.66 1,292,777.64
311(1)c1 Portland Cement Concrete Pavement (Unreinforced ), 0.230m. Thk., 3,500 psi. SQ.M. 17,080.00 1,330.10 22,718,122.95 47.38 2,041.98 2,716,032.73 445.30 592,293.92 2,487.28 3,308,326.65
500(1)b3 Reinforced Concrete Pipe Culverts ( RCPC), Class IV, 910 mm. dia.(36" Ø) l.m 70.00 9,303.77 651,263.96 1.36 24.00 223,290.50 - 24.00 223,290.50
505(2)a Grouted Riprap, Class "A" (Slope Protection/Guard Blocks) CU.M. 587.40 4,300.77 2,526,270.84 5.27 160.00 688,122.80 166.55 716,292.83 326.55 1,404,415.63
506(1) Stone Masonry, Class "A" (CB/HW/A//LINED DITCH) CU.M. 939.40 4,994.11 4,691,448.38 9.78 80.64 402,725.03 - 80.64 402,725.03
612(1) Reflectorized Thermoplastic Pavement Markings, (White) SQ.M. 700.40 876.28 613,743.30 1.28 - - -
612(2) Reflectorized Thermoplastic Pavement Markings, (Yellow) SQ.M. 301.50 1,802.00 543,303.57 1.13 - - -
102(3)B Surplus Soft Rock Excavation CU.M. 8,704.09 425.18 3,700,812.50 7.72 8,069.39 3,430,950.22 8,069.39 3,430,950.22
TOTAL 47,945,925.58 100.00 9,743,457.13 4,110,821.69 13,854,278.82
Checked as to Materials:
Prepared: Checked: (as per Test Results Attached) Reviewed: Submitted: Approved:

ANTHONY CHRISTIAN N. YANG ELIPHAZ A. BERNARDO ALEXIS S. ITAO SUSANA L. FERNAN JOANNE TEODORA E. LAO EDGAR E. CARREDO
Project Engineer Project Engineer, PEO Chief, Materials Inspector Area Engineer, North Head, Construction Section OIC, Construction Divivsion