AI-VO-PRC-004 R1 Procedure For Inspection Deferment
AI-VO-PRC-004 R1 Procedure For Inspection Deferment
Facilitator
Re . Ind:
Date
Endorsed b
OM (D)
roved b
Date:
PROCEDURE FOR INSPECTION DEFERMENT
DOC. No AI-VO-PRC-004 Rev. 1
FOREWORD
This document has been developed under the Asset Integrity Team (P2 initiative),
approved by OM(s’) Management and has been endorsed by EXECUTIVE VP,
OPERATIONS, VO for use as Procedure for Inspection Deferment
It is recognised that there will be cases where addenda, data sheets, or other
clarifications need to be attached to the document to suit a specific application or
service environment. As such, the content of the document shall not be changed or
re- edited by any user (QP or its contractors, suppliers, agents, etc.), but any
addenda or clarifications entailing major changes shall be brought to the attention of
the custodian department.
, ‹
TABLE OF CONTENTS
Page
No.
FOREWORD
1.0 OBJECTIVE ................................................................ 3
2.0 SCOPE ....................................................................... 3
3.0 TERMINOLOGY- DEFINITIONS I ABBREVIATIONS ............ 3
3.1 DEFINITIONS .................................. ... ..................... 3
3.2 ABBREVIATIONS .................................................... 3
4.0 PROCESS / PROCEDURE ............................................... 4
4.1 DR INITIATION ......................................................... 4
4.2 RAT FORMATION........................................................ 5
4.3 PROCESSING AND APPROVING DR ............................. 6
4.4 RECORDS AND IMPLEMENTATION .............................. 7
4.5 DR APPROCAL CERTIFICATE....................................... 7
5.0 REFERENCE STANDARDS AND CODES ........................ 8
6.0 APPENDICES .............................................................. 8
6.1 APPENDIX A: FLOW CHART ........... . ....... ................. .. 9
6.2 APPENDIX B: DEFERMENT REQUEST FORM.................. 10
1.0 OBJECTIVE
The objective of this procedure is to establish and implement system for deferment
of planned inspection for all Static Equipment, Pressure Relief Devices, Piping and
Pipeline.
2.0 SCOPE
AH
Al
DR Asset Holder
PRD
Pressure relief Devices
RAT
Risk Assessment team
RBI
Risk Based Inspection
SAP
System, Application and Product
TA
Turnaround
AH
a) HSE Impact,
b) Inspection/Asset integrity (RBI) assessment,
c) Fitness For Services,
d) Integrated and planned activities,
e) Effects on QP's Operating Philosophy,
f) Plant Operation related Problems, RAT
g) Optimization, and,
h) Any additional financial burden on QP
4.3.4
Depending on the assessment to all, but not limited
to the above, the RAT shall advice either of the
following:
a) Immediate Release of Equipment for Inspection RAT
DR b) Deferred to the date suggested by the
Deferment Request.
c) Deferred to a new date other than requested date.
4.3.5
The RAT assessment results shall be forwarded to
both Asset Holder Manager & Asset Integrity
Manager for approval; and to all RAT Managers for
information
6 APPENDICES
6.1 APPENDIX A Flow chart
ImmediateAH.AsstINSP/AI Asst
RBI/IMS At MGR RAT TeamRAT MGRAH/AI MGR OM AII MGRS
MGR MGR
APPENDIX — B: Deferment request form ^>>Please click here for the fillable form<<<
Deferred lnspecson Date DR lnit›awr Sigr Date Asset holder Ass stant k1anager Sign/Oate
Asset Holder Asset Integrity r Maintenance Redat›ilcy HSE Turn RAT Chairman
Operation Operations Eeq k¥ember btember Member around S›gn@ala
awe ioFr.Los s •z - sgn'Date Sign.''Date Member
s'on/Date .Member Sgn7Date
Remarks :Nil.
Note:
The revision history log shall be updated with each revision of the document. It shall
contain a written audit trail of the reason why the changes/amendments have occurred,
what the changes/amendments were, and the date at which the changes/amendments
were made.