D6391-11 Standard Test Method For Field Measurement of Hydraulic Conductivity Using
D6391-11 Standard Test Method For Field Measurement of Hydraulic Conductivity Using
1. Scope conditions when trapped air is not present (3). This test method
1.1 This test method covers field measurement of hydraulic develops the “field-saturated” condition.
conductivity (also referred to as coeffıcient of permeability) of 1.5 Experience with this test method has been predomi-
porous materials using a cased borehole technique. When nantly in materials having a degree of saturation of 70 % or
isotropic conditions can be assumed and a flush borehole is more, and where the stratification or plane of compaction is
employed, the method yields the hydraulic conductivity of the relatively horizontal. Its use in other situations should be
porous material. When isotropic conditions cannot be assumed, considered experimental.
the method yields limiting values of the hydraulic conductivity 1.6 As in the case of all tests for hydraulic conductivity, the
in the vertical direction (upper limit) if a single stage is results of this test pertain only to the volume of soil permeated.
conducted and the horizontal direction (lower limit) if a second Extending the results to the surrounding area requires both
stage is conducted. For anisotropic conditions, determination multiple tests and the judgment of qualified personnel. The
of the actual hydraulic conductivity requires further analysis by number of tests required depends on among other things: the
qualified personnel. size of the area, the uniformity of the material in that area, and
1.2 This test method may be used for compacted fills or the variation in data from multiple tests.
natural deposits, above or below the water table, that have a 1.7 The values stated in SI units are to be regarded as the
mean –3hydraulic conductivity less than or equal to 1×10–5 m/s standard unless other units specifically are given. By tradition
(1×10 cm/s). in U.S. practice, hydraulic conductivity is reported in cm/s
1.3 Hydraulic conductivity greater than 1×10 –5 m/s may be although the common SI units for hydraulic conductivity are
determined by ordinary borehole tests, for example, U.S. m/s.
Bureau of Reclamation 7310 (1)2; however, the resulting value 1.8 All observed and calculated values shall conform to the
is an apparent conductivity.
--`,`,,,`,`,``,,``,`,`,``````,,,-`-`,,`,,`,`,,`---
guide for significant digits and rounding established in Practice
1.4 For this test method, a distinction must be made between D6026.
“saturated” (Ks) and “field-saturated” (Kfs) hydraulic conduc- 1.8.1 The procedures in this standard that are used to specify
tivity. True saturated conditions seldom occur in the vadose how data are collected, recorded, and calculated are regarded
zone except where impermeable layers result in the presence of as the industry standard. In addition, they are representative of
perched water tables. During infiltration events or in the event the significant digits that should generally be retained. The
of a leak from a lined pond, a “field-saturated” condition procedures do not consider material variation, purpose for
develops. True saturation does not occur due to entrapped air obtaining the data, special purpose studies, or any consider-
(2). The entrapped air prevents water from moving in air-filled ations for the objectives of the user. Increasing or reducing the
pores, which may reduce the hydraulic conductivity measured significant digits of reported data to be commensurate with
in the field by as much as a factor of two compared with these considerations is common practice. Consideration of the
significant digits to be used in analysis methods for engineering
design is beyond the scope of this standard.
1
This test method is under the jurisdiction of ASTM Committee D18 on Soil and
Rock and is the direct responsibility of Subcommittee D18.04 on Hydrologic 1.9 This standard does not purport to address the safety
Properties and Hydraulic Barriers. concerns, if any, associated with its use. It is the responsibility
Current edition approved Nov. 1, 2011. Published January 2012. Originally of the user of this standard to establish appropriate safety and
approved in 1999. Last previous edition approved in 2006 as D6391–06. DOI:
10.1520/D6391-11.
health practices and determine the applicability of regulatory
2
The boldface numbers in parentheses refer to the list of references at the end of limitations prior to use. This test method does not purport to
this standard. address environmental protection problems, as well.
Copyright © ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States
--`,`,,,`,`,``,,``,`,`,``````,,,-`-`,,`,,`,`,,`---
FIG. 1 Schematic of Borehole Test Showing Borehole Flush with Base (Methods B and C, Stage 1 of Method A) and with Extension for
Stage 2 of Method A
FIG. 2 Falling Head Standpipe (Methods A and B) (a) and Mariotte Tube (Method C) (b) Used for the Flow Assembly
--`,`,,,`,`,``,,``,`,`,``````,,,-`-`,,`,,`,`,,`---
--`,`,,,`,`,``,,``,`,`,``````,,,-`-`,,`,,`,`,,`---
NOTE 1—For the Flat Auger, Do = D + 50 mm where D is the inside diameter of the borehole casing. For the reamer, Do = D – 1 mm.
FIG. 3 Schematic of Apparatus Used as Flat Auger (Borehole Excavation) and Reamer (Borehole Extension in Stage 2 of Method A)
6.2.3.3 Sock—The sock protects the soil at the bottom of the standpipe. Nominal 13-mm components have been satisfactory
casing from disturbance when water is introduced and prevents for tests with a 100-mm diameter casing.
collapse of the borehole extension for Stage 2. A non-woven 6.3.2 Standpipe—The standpipe shown on Fig. 1 should be
geotextile, filled with pea gravel or other highly pervious only as tall as needed to apply a maximum head (measured at
material has been found satisfactory. The hydraulic conductiv- the bottom of the casing) equal to or less than the head
ity of all sock materials shall be at least ten times the allowable by hydraulic fracturing considerations; the hydraulic
anticipated hydraulic conductivity of the tested stratum. Wires head at the bottom of the casing should not exceed 1.5 times
or other suitable means for retrieving the sock should be the total overburden pressure at that level. The standpipe must
provided. be transparent and strong enough to withstand wind forces.
6.3 Pressure/Flow System: Clear Schedule 40 PVC has been found satisfactory. Inside
6.3.1 Flow Monitoring System—The flow monitoring sys- diameters of 10 to 20 mm have been satisfactory for tests
tem illustrated in Fig. 2 consists of a standpipe or Mariotte tube conducted with a 100-mm diameter casing. For 300-mm-
and scale composed of metal or plastic components. All diameter casing, standpipes with an inside diameter between
connections shall have a diameter of at least 75 % that of the 50 and 100 mm have been satisfactory. The diameter may need
polytetrafluoroethylene (PTFE) tape, refill hose, funnel to fit 7.2 The layer being tested must maintain its full thickness at
refill hose, 100-mL plastic cylinder flask. least 3 m horizontally in all directions from the center of the
6.4 Temperature System—A device for measuring tempera- test.
ture 60.5 °C with a range sufficient to cover the anticipated air 7.3 Stratification or the plane of compaction should be
and water temperatures during the test and long enough to essentially horizontal.
extend to the bottom of the TEG. 7.4 If a compacted fill is being tested, the test area shall be
6.5 Survey Equipment—Surveyor’s level and rod, and a 15 covered with clear or white plastic immediately after the final
to 30-m tape. lift is placed.
6.6 Miscellaneous: 7.5 Compacted fills shall be underlain by a soil layer no less
6.6.1 Plastic Sheeting—Clear or white plastic sheeting, permeable than intended for the fill or a permeable layer such
nominal thickness at least 0.1 mm. Provide one 3 by 3 m sheet as a geotextile, geocomposite drain, or sand layer. Such
per test, including the TEG. conditions shall be recorded, together with the phreatic surface,
6.6.2 Water Supply—Preferably water of the same quality as if any, within the fill. See Practice D1452 for determining the
that involved in the problem being examined but having a phreatic surface. Where no such bottom condition exists, the
turbidity of 5 nephelometric turbidity units (NTU) or less. Only nature of the underlying soil and depth to the groundwater
potable water should be used if there is a possibility that the phreatic surface shall be furnished. The thickness of the tested
introduced water could enter the groundwater regime. All material near each test location shall be determined to 610 mm
water to be introduced into the test apparatus shall be allowed before-and-after survey or post-test borings.
to stand open at least 12 h prior to use for deairing. See 8.3.3 7.6 In natural deposits, the stratigraphic sequence shall be
for temperature requirements. determined by borings, or test pits, or both to at least 1 m below
6.6.3 Antifreeze—Where air temperatures below freezing the proposed bottom level for Stage 2 and the position of the
are anticipated, an antifreeze solution may be used as the phreatic surface in the tested stratum shall be determined.
permeating fluid in lieu of water. The temperature-kinematic Borings or test pits shall not be made within 3 m of the test
viscosity relation of the solution must be determined and used location before the test; any borings within 10 m of the test
in the appropriate equations of Section 9. Ethanol (ethyl location shall be grouted prior to testing. Any test pits within
alcohol) in potable form has been used in Table 1. Ethanol at this distance shall be backfilled prior to testing. Test pits shall
concentrations of 1:1 or stronger can cause structural changes not be made closer to the test location than half the test pit
in the soil and should not be used. Groundwater pollution may depth.
shall be used where there is seepage of groundwater into the maximum water level above ground surface shall not exceed
borehole at or above test level. The casing shall be pushed (not the height equal to the depth of embedment of the casing.
driven) approximately 25 mm into the soil at the bottom of the Check all joints carefully for water leaks by wiping the joints
--`,`,,,`,`,``,,``,`,`,``````,,,-`-`,,`,,`,`,,`---
conductivity, kv , is less than some specified value and the limiting vertical 6.1.5. Prepare the bottom as described in 8.1.3. Measure and
conductivity, K1, is less than that value, Stage 2 in Method A may be record depth (L) and diameter (D) of borehole extension to the
omitted. In such cases, Stage 1 may be terminated if K1 remains below the
specified value for a period at least as long as that given in Table 2
nearest mm.
provided there is no upward trend in the hydraulic conductivity measure- 8.5.4 Replace the Sock—Place the sock to the bottom of the
ments. borehole. Alternatively, but only where an inclusion of high-
8.5 Conduct Stage 2 (Method A only): conductivity material in the tested stratum is of no
8.5.1 Empty the Casing—Remove the top assembly with its consequence, the hole may be filled to 80 mm above the casing
attached equipment. Siphon, vacuum, or bail, or a combination bottom with pea gravel.
thereof, all water from within the casing for tests where the 8.5.5 Reassemble the System—Refill the casing with water
casing is set in a dry hole. Otherwise, siphon, vacuum. or bail as described in 8.3.3, reattach and seal the top assembly with
to the groundwater level of the stratum being tested. Remove its equipment, and refill the standpipe. Concurrently, empty
the sock. and refill the TEG with water having the same temperature
8.5.2 Advance the Borehole—Extend an open borehole hav- (within 1 °C) as that used in the test.
ing the same diameter as the inside of the casing to a depth 8.5.6 Perform Stage 2—Conduct Stage 2 using the same
below bottom-of-casing not less than 1 test diameters and not procedure as described in 8.4. The termination criteria are the
more than 2 test diameters. same. See Fig. 4 for a typical form for recording the data.
8.5.3 Ream the Borehole—Ream the borehole to the desired 8.6 Demobilization—Remove and store the top assembly
depth and diameter using the reamer to minimize sidewall with its attached systems. For tests in compacted fills, empty
smear. Roughen the inside walls using the scarifier discussed in the casing, remove sock and casing, then backfill the resulting
--`,`,,,`,`,``,,``,`,`,``````,,,-`-`,,`,,`,`,,`---
--`,`,,,`,`,``,,``,`,`,``````,,,-`-`,,`,,`,`,,`---
G Œ S D
10–8 – 10–9
F
24 2
4b 2 L 4b 2 L
10–9 – 10–10 48 1 1 11 1
10–10 – 10–11 72 D D D D
G5 5 (7)
F 4b 2
D
2
L
D
1 G Œ S D 11
4b 2
D
2
L
D
2
hole with layers of tamped and wetted bentonite pellets or as F 5 1 2 0.5623 e 21.566 D
L
(8)
directed. Casings for tests in natural deposits can be left as
piezometers or plugged and abandoned like monitoring wells, where:
as directed. L = length of Stage 2 extension below bottom of casing
(cm),
9. Calculation D = ID of Stage 2 extension (casing ID), and
9.1 Method A—Calculate K1 and K2 using Eq 1-11. Alter- b2 = distance from center of Stage 2 extension to top of
nate equations are given in Ref. (6). underlying stratum or groundwater (cm).
9.1.1 Stage 1—Compute K1 using Eq 1 and 2 for each The other terms are as previously defined.
sequential pair of water levels during Stage 1 and graph K1 vs. 9.2 Calculate the time-weighted average <K1>' from the K1
time as shown in Fig. 7 using data recorded in a data sheet data in Stage 1 during the period when K1 appears temporally
simlar to example shown in Fig. 4. invariant (no apparent temporal trend up or down):
K1 5 RT G1
ln
Z1
Z2 S D (1)
n
(K
i51
1,i ~ t 2 2 t 1! i
~ t 2 2 t 1! ,K 1 . 5 n (9)
where: ( ~ t 2 2 t 1! i
i51
G1 5 S DF S DG
πd 2
11D 1
11a
D1
4b 1
(2)
where:
i = designates the ith of n time time increments in the
RT = 2.2902(0.9842T)/T0.1702 and T is temperature in °C, temporally invariant range.
d = ID of standpipe (cm), 9.3 Calculate the time-weighted average <K2>' from the K2
D1 = effective diameter of Stage 1 (cm), equals ID of casing data in Stage 2 during the period when K2 appears temporally
under dry hole conditions when no inward seepage was invariant (no apparent temporal trend up or down):
--`,`,,,`,`,``,,``,`,`,``````,,,-`-`,,`,,`,`,,`---
diameter of casing: (K
i51
2,i ~ t 2 2 t 1! i
a = +1 for impermeable base at b1, ,K2. 5 n (10)
= 0 for infinite (+20D1) depth of tested material, ( ~t 2 2 t 1! i
= –1 for permeable base at b1, and i51
K2 5 RT G2
ln
Z1
Z2S D (3) min H 1 n
( ~ Z 2 Z ti! 2 J (12)
~ t 2 2 t 1! n i51 i
G2 5 S Dd2
16FL
G3 (4)
subject to the unbiased constraint
n
FIG. 7 Example of K1 (a) and K2 (b) vs. Elapsed Time for Stages 1 and 2 from Method A
--`,`,,,`,`,``,,``,`,`,``````,,,-`-`,,`,,`,`,,`---
FIG. 8 Example of Z vs. Time (a) and K vs. Trial Number (b) for Falling-Head Procedure in Method B
--`,`,,,`,`,``,,``,`,`,``````,,,-`-`,,`,,`,`,,`---
conductivities exhibit no temporal trend and differ by no more 10.1.1 A data sheet indicating the method (A, B, or C) that
than 25 %. was used and the data that were collected,
9.5 Method C—Compute the hydraulic conductivity using 10.1.2 A graph of K1 and K2 (Method A) or <K> (Methods
the following equation (7) using data recorded in a data sheet B and C) versus time,
similar to example shown in Fig. 6. 10.1.3 Average values <K1> and <K2> (Method A) or <K>
9.5.1 Calculate K for each time increment using Eq 15. (Methods B and C),
π ~ d 2s 2 d m2 !~ Z 1 2 Z 2 ! 10.1.4 Thickness of layer tested,
K 5 RT (15)
2.75D H b ~ t 2 2 t 1 ! 10.1.5 Description of material beneath the layer tested.
References
(1) U.S Department of the Interior, Bureau of Reclamation, Earth (5) Trautwein, S. and Boutwell, G., “In-Situ Hydraulic Conductivity Tests
Manual, Part 2, Third Edition, 1990. for Compacted Soil Liners and Caps,” Hydraulic Conductivity and
(2) Bouwer, H., “Rapid Field Measurement of Air Entry Value and Waste Contaminant Transport in Soils, ASTM STP 1142, ASTM
Hydraulic Conductivity of Soil as Significant Parameters in Flow International, 1994, p. 184–223.
System Analysis,” Water Resources Research, Vol 2, No. 4, 1966, pp. (6) Chapuis, R., “Shape Factors for Permeability Tests in Borehole and
729–738. Piezometers,” Groundwater, Vol. 27, No. 5, 1989.
(3) Reynolds, D. and Elrick, D. E., “A Method for Simultaneous In-Situ (7) Trast, J. and Benson, C., “Estimating Field Hydraulic Conductivity of
Measurement in the Vadose Zone of Field-Saturated Hydraulic Compacted Clay,” Journal of Geotechnical Engineering, Vol. 121,
Conductivity, Sorptivity and the Conductivity-Pressure Head No. 10, 1995, pp. 736-740.
Relationship,” Groundwater Monitoring Review, Vol 6, No. 4, 1986,
(8) Chaisson, P., “Methods of Interpretation of Borehole Falling-Head
pp. 84.
Tests Performed in Compacted Clay Liners,” Canadian Geotechnical
(4) Bouwer, H., “Intake Rate: Cylinder Infiltrometer,” Methods of Soil
Journal, Vol. 42, 2005, pp. 79-90.
Analysis, Part 1 Physical and Mineralogical Methods, Agronomy
(9) Hvorslev, M. ( 1951), Time Lag and Soil Permeability In Ground-
--`,`,,,`,`,``,,``,`,`,``````,,,-`-`,,`,,`,`,,`---
Monograph No. 9, American Society of Agronomy, Madison, WI,
1986, pp. 825–844. Water Observations, US Army Corps of Engineers, Vicksburg.
ASTM International takes no position respecting the validity of any patent rights asserted in connection with any item mentioned
in this standard. Users of this standard are expressly advised that determination of the validity of any such patent rights, and the risk
of infringement of such rights, are entirely their own responsibility.
This standard is subject to revision at any time by the responsible technical committee and must be reviewed every five years and
if not revised, either reapproved or withdrawn. Your comments are invited either for revision of this standard or for additional standards
and should be addressed to ASTM International Headquarters. Your comments will receive careful consideration at a meeting of the
responsible technical committee, which you may attend. If you feel that your comments have not received a fair hearing you should
make your views known to the ASTM Committee on Standards, at the address shown below.
This standard is copyrighted by ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959,
United States. Individual reprints (single or multiple copies) of this standard may be obtained by contacting ASTM at the above
address or at 610-832-9585 (phone), 610-832-9555 (fax), or [email protected] (e-mail); or through the ASTM website
(www.astm.org). Permission rights to photocopy the standard may also be secured from the Copyright Clearance Center, 222
Rosewood Drive, Danvers, MA 01923, Tel: (978) 646-2600; http://www.copyright.com/