Part 2/ Section All fans, AHU, Pumps engineering calculations shall have safety
6 Bi / Clause have a safety factor of 20 % in load calculations and same shall be factor of 15% for calculating operating point and heat load
14. 4.1.12 validated during the Testing & Commissioning calculations shall have a safety factor of 10% and same shall be
Page no. 20 of validated during the Testing & Commissioning.
67
Part 2/ Section Water-cooled chillers shall operate during revenue hours and Air Water-cooled chillers shall operate during revenue hours and Air
6 Bi / Clause cooled Chillers shall operate during non-revenue night hours. cooled Chillers shall operate during non-revenue night hours. Also
16. 5.6.1 air cooled chillers shall operate 24 X 7 during winter period.
Page no. 25 of
67
(1) Property Development at Bhaisali and Anand Vihar
shall include chilled water supply and return pipe connections with Station:-
PD area is shown in tender drawings at Anand Vihar & Bhaisali
energy meter and motorized valves; and, fresh air supply duct
station above the station box other than the transit area.
terminated at the boundary of each retail zone under 200 m2. For retail Construction of ECS TVS and Electrical Services are not in the
Part 2/ Section scope of work of this contract. Since construction of PD area
for every 200 m2. SCADA system shall log the usage of the cooling will be done subsequently at a later stage, only the space
6 Bi / Clause
17. planning coordination for Chiller plant will be required to be
5.6.5 energy and report to NCRTC for billing purpose. Chilled water shall be
carried out by this Contractor with the interfacing contractors.
Page no. 26 of 67 provided during revenue service hours.
(2) Property Development at Begumpul Station:-
PD space on Mezzanine floor at Begumpul (not on
platform /concourse): space provision for power supply,
Airconditioning, Smoke extraction , Chiller plant, utility
Gallery, shafts etc. to be done such that the concessionaire