How To Perform Bow Tie Analysis
How To Perform Bow Tie Analysis
Bow tie analysis (BTA) is an increasingly popular tool used to graphically display
hazard scenarios and the barriers that protect against them so that necessary
actions can be taken to protect their integrity.
A procedure for conducting BTA is described in the Primatech white paper, How
to Perform Bow Tie Analysis .
BTA consulting
PHA software
Technical certification
Glossary of Terms
Barrier: A control measure or grouping of control elements that on its own can
prevent a threat developing into a top event (prevention barrier) or can mitigate
the consequences of a top event once it has occurred (mitigation barrier). A
barrier must be effective, independent, and auditable. Also called an
Independent Protection Layer .
Barrier details: Information on the function, type, elements, criticality, owner, and
performance data for a barrier.
Mitigation barrier: A barrier located on the right-hand side of a bow tie diagram
lying between the top event and a consequence. It may only reduce the
magnitude of a consequence, not necessarily terminate the scenario before the
consequence occurs.
Pathway : A bow tie arm on which barriers or degradation controls are located. A
Main pathway is an arm connecting a threat to the top event, or the top event to
a consequence. They contain barriers. Alternative terms are Prevention pathway
and Mitigation pathway . Arms connecting degradation factors to a barrier are
termed Degradation pathways. They contain degradation controls.
Prevention barrier: A barrier located on the left-hand side of a bow tie diagram
lying between a threat and the top event. It must have the capability on its own
to completely terminate a threat sequence.
ABBREVIATIONS
Abbreviation Meaning
BTA Bow tie analysis
PFD Process flow diagram
PHA Process hazard analysis
PSM Process safety management
P&ID Piping and instrumentation drawing
QC Quality control
Introduction
Bow tie analysis (BTA) involves the construction of diagrams that depict how
prevention and mitigation barriers and controls (i.e. safeguards) protect against
threats (i.e. initiating events) that can cause hazardous events, and the adverse
impacts (i.e. consequences) that can arise from them. Bow tie diagrams have
various uses including communicating process hazards to stakeholders, helping
to identify safety critical equipment and tasks, barrier management, and incident
investigation.
A bow tie diagram maps the threats that may lead to a hazardous event and its
undesired consequences in a graphical display that resembles a bow tie (see
Figure 1).
Threats appear on the pre-event side (left side) and consequences appear on
the post-event side (right side). The focal point of the diagram is the specific
loss, or hazardous event (top event), that results from a hazard and ties
together the initiating events and the consequences. There is a time progression
from the left to the right of the diagram. Items in the diagram are connected by
pathways or arms. Prevention barriers lie along the prevention pathway which
connects threats to the top event. Mitigation barriers lie along the mitigation
pathway which connects the top event to consequences.
This white paper provides a procedure for performing BTA and constructing bow
tie diagrams.
BTA Procedure
4. Identify consequences.
5. Identify threats.
A statement of the purpose, scope, and objectives helps to ensure a study stays
focused and is performed completely. It helps to avoid the inclusion of
extraneous items and digressions during the performance of the study.
Sometimes the purpose, scope and objectives statement is referred to as the
study charter or terms of reference.
The purpose is the reason(s) why the study is performed. It must be defined
since it affects the way the study is performed, for example, the types of hazards
to be included and the types of consequences to be addressed. It helps ensure
the study outcome is consistent with the intention for the study.
Usually, the study purpose specifies the process or process unit that is the
subject of the study, the intended use of the bow tie diagrams, and their
intended audience, for example, operators, managers, and/or regulators.
Possible study purposes include meeting regulatory or company requirements,
providing resources for training, and assisting in management of change (MOC)
reviews.
Develop bow tie diagrams for the refinery crude unit to communicate major
process hazards to upper management.
The study scope specifies what is included in the study and it may also specify
what is excluded. Several items should be addressed in the scope statement:
- The states of the process during its life cycle that will be addressed
must be identified, e.g. startup, normal operation, shutdown, emergency
shutdown, etc.
- Studies may or may not include the recording of details for barriers and
controls. Although it makes bow tie diagrams more complex and requires time to
formulate the information, it is needed to manage the risks of barriers and
controls.
• Assumptions
- Assumptions may be made during the study planning stage, e.g. preventive
maintenance is performed according to the mechanical integrity program.
Types of scenarios to include : High risk and high consequence scenarios from
PHA as defined by the risk ranking scheme.
Possible restrictions on the number of top events : Address only scenarios from
the PHA study for the process.
Inclusion / exclusion of barrier and control details : Details are not recorded for
barriers or controls.
• Brainstorming by a team
• Basic
- Only the hazard, top event, threats, and consequences are identified.
- Adds degradation factors and controls to the standard bow tie diagram.
• Enhanced
• Multi-level
The level of analysis used is determined by the purpose of the study. For
example, if the purpose is communication of hazards, basic bow ties may be
sufficient whereas if the purpose is barrier management, enhanced bow ties will
be needed.
A team is led by a facilitator who guides the study and controls and motivates
team members. The facilitator must be knowledgeable in BTA and PHA,
possess facilitation and communication skills, and be able to understand the
process or operation being studied.
A scribe records the bow tie diagrams and documents discussions, The scribe
must be proficient with the means of recording the study and be able to
understand the technical discussions. The facilitator may act as the scribe.
The other team members formulate the bow tie diagrams under the guidance of
the facilitator. They should be subject matter experts in one or more aspects of
the process, such as engineering, operations, controls, maintenance, safety, etc.
Collectively, they must understand the full range of barriers and controls
deployed. Team members must attend all study sessions.
Studies can be recorded using pencil and paper, paper with sticky notes,
graphics software, or custom commercial software. Several custom commercial
software programs are available. They support different levels of display of bow
tie diagrams while storing details of barriers and controls.
Paper with sticky notes offers flexibility at a low cost while custom commercial
software provides convenience, but at a price. The size of computer screens
does limit what can be represented and viewed easily with software. Bow tie
diagrams become increasingly difficult to view as their complexity increases.
This issue may have the unfortunate result of constraining the depth and
breadth of the analysis to what can be conveniently viewed on the computer
screen. Paper or white board approaches may do a better job of encouraging
creative and expansive thinking for the initial construction of bow tie diagrams.
The following items should be addressed with the team before beginning the
construction of bow tie diagrams:
• Process description
Training may be needed if the study participants are not familiar with BTA.
The hazard is shown in a bow tie diagram to provide clarity as to the source of
risk. Also, it defines the coverage of the bow tie diagram.
The potential for harm from a hazard is realized when control over the hazard is
lost, resulting in a hazardous event, or top event. A common type of top event in
process safety is one involving loss of containment. A hazard may result in
multiple top events. Each top event is described in a separate bow tie diagram.
An example of a bow tie diagram for a plant that contains a volatile hydrocarbon
in a pipeline under pressure is shown in Figure 2 for the hazard:
The hazard and top event are the starting point for constructing a bow tie
diagram. They must be defined carefully to ensure a useful bow tie is
constructed.
- A hazard represents the potential for harm. Thus, flammability is a hazard but
fire is not.
• Be specific
- Generic hazards lead to generic bow tie diagrams which are of limited value.
- The level of detail provided for the hazard determines the level of detail in the
bow tie diagram.
• Specify the circumstances under which the hazard occurs (mode of operation,
concurrent activities, etc.)
• Do not confuse the hazard (potential for harm) with the top event (loss of
control over the hazard), or the consequences (actual harm).
- Generally, do not define top events so narrowly that multiple bow tie diagrams
are needed so that each one contains few threats and consequences.
- Also, do not define top events so broadly that the bow tie diagram has too
many threats and consequences making it complex.
- Less obvious top events may require some care to ensure the optimum one is
selected.
- Choose the best point in the time sequence of events to ensure a balance of
threats and consequences that does not skew the bow tie diagram to one side
or the other and provides for the correct placement of prevention and mitigation
barriers.
One top event may have multiple consequences. Usually, trivial consequences
are excluded from the analysis. Typically, consequences are identified by
consulting PHA studies or brainstorming.
- Harm or damage from the realization of a hazard, e.g. operator fatality (actual
harm), not a toxic chemical release (not actual harm)..
• If all the barriers for different pathways are the same, consequences can be
combined and shown for a single pathway. This practice reduces the size of the
diagram, which supports more effective communication.
Threats are reasons for loss of control of the hazard leading to the top event. A
threat leads directly to the top event if the pathway is not prevented. Each
pathway from a threat to the top event represents a single scenario that could
directly and independently lead to the top event. Usually, there are multiple
threats for each top event. Threats are placed on the left side of the bow tie
diagram.
- Causal relationship between the threat and the top event must be clear without
additional explanation.
- A threat is not sufficient if it can only cause the top event in combination with
another threat.
- When two or more threats are required together to cause the top event, they
should be combined into a single threat.
• If the barriers for different threats are the same, the threats can be combined
on a single pathway
- A barrier failure by itself does not lead to the top event, unless a barrier failure
is truly an initiating event.
• Do not exclude threats just because there are many barriers in place to protect
against them
Barriers are measures to prevent or mitigate top events. They appear on the
main pathways of the bow tie diagram. The barrier function is the task or role of
a barrier, e.g. relieve pressure. A barrier system is a combination of barrier
elements that collectively provides the full functionality required of a barrier. A
barrier element is an individual component of a barrier system. It usually detects
the existence of a threat, decides what action is needed, or takes the action that
is needed.
Barriers must have the ability to prevent or mitigate a top event on their own and
they must meet certain validity requirements. Bow tie practitioners usually
identify barriers along the timeline for each threat by consulting PHA studies and
applying barrier validity requirements.
• Effective
• Independent
• Auditable
Barriers are the central element of a bow tie diagram. They must be defined
carefully to ensure a meaningful bow tie is constructed.
- Also, active barriers must provide all elements of “detect, decide, act”.
• Keep the number of barriers low by tailoring the bow tie diagram
- Often, a list of barriers is used outside the context of the bow tie diagram so
reliance cannot be placed on the context to show their meaning.
• Consider recording set points, if applicable
• Place barriers on the correct side of the top event where they deliver their
function or effect
- Barriers that act to prevent the top event from occurring are placed between
the threat and the top event.
- Barriers that act to mitigate the top event are placed between the top event
and the consequences.
• Address those prevention barriers that prevent the threat from ever occurring
or stop a threat that has occurred from leading to the top event
• Address those mitigation barriers that stop the consequence from occurring or
reduce its magnitude
• Place barriers on the bow tie diagram in the time sequence of their operation
• Generally, the same barrier should not appear on both sides of the top event
• Do not include multiple barriers that share common cause failures on the same
prevention or mitigation pathway
Degradation factors and controls are drawn in the bow tie diagram below the
barrier to which they apply. They lie along a degradation pathway leading to a
barrier. Multiple degradation factors can apply to a single barrier and multiple
degradation controls can apply to a single degradation factor.
The BTA team identifies existing degradation factors and controls using their
knowledge of the process.
An example of a bow tie diagram with degradation factors and controls for
prevention barriers is shown in Figure 7. An example of a bow tie diagram with a
degradation factor and controls for a mitigation barrier is shown in Figure 8.
Degradation factors and controls can be an important part of a bow tie diagram.
They must be defined carefully to ensure their meaningful management.
• Do not place degradation controls on main pathways in the bow tie diagram
- The underlying reason for the failure needs to be specified so that analysts can
be sure degradation controls address the specific problem.
• Avoid unnecessarily repeating the same degradation factor and its controls on
recurring barriers
- Reference the first occurrence.
• Recognize that some degradation factors are not specific to a particular barrier
but may impact multiple barriers
Details for barriers and controls include information on the function, type,
elements, criticality, owner, and performance data for a barrier or control. They
are recorded using the knowledge of the team and by referencing appropriate
process documentation. However, the details are not recorded directly on bow
tie diagrams owing to space limitations.
On completion, bow tie diagrams should be reviewed to confirm that they meet
the requirements of the project charter, ensure the full ranges of threats and
consequences are addressed, and verify that they are structurally correct. There
should be no degradation controls on a main pathway or ineffective barriers.
Also, consistency of barriers and controls across diagrams should be confirmed.
- Prevention barriers are favored over mitigation barriers but the latter are
needed too in case the former fail.
- Often it is better to resolve deficiencies in existing barriers rather than add new
ones
- Each extra barrier adds complexity and must be managed throughout its life
cycle.
- Particularly true if the new barrier will be subject to the same degradation
factors that reduced the performance of the existing barriers.
Once bow tie diagrams are considered final, a QC review should be performed.
Typically, a checklist of pertinent questions is used.
Closing Comments
The likelihood that bow tie diagrams will be constructed correctly is increased if
a formal procedure is followed for their construction. However, BTA is an
iterative process in which pathways are split and combined, and other
adjustments are made, according to the judgment of the analysts to produce
what is viewed as an optimum diagram. However, there is no single ‘right’
answer. Moreover, bow tie diagrams are not intended to capture every aspect of
safety management systems. The intent is to focus on primary barriers and
controls.