Imc Pipelines Loop 2

The document summarizes the cleaning of butadiene pipelines at an IMC Limited facility in Gujarat, India. It describes the multi-step cleaning process including: [1] cold water flushing, [2] heated water flushing, [3] detergent flushing with Coronil-100, [4] acid cleaning using Coronil-92B, citric acid and other chemicals, and [5] passivation. The pipeline system was divided into two loops for cleaning due to temperature issues. The cleaning was completed successfully and met completion criteria checked by the involved companies.

Uploaded by

Kiran Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
89 views

Imc Pipelines Loop 2

The document summarizes the cleaning of butadiene pipelines at an IMC Limited facility in Gujarat, India. It describes the multi-step cleaning process including: [1] cold water flushing, [2] heated water flushing, [3] detergent flushing with Coronil-100, [4] acid cleaning using Coronil-92B, citric acid and other chemicals, and [5] passivation. The pipeline system was divided into two loops for cleaning due to temperature issues. The cleaning was completed successfully and met completion criteria checked by the involved companies.

Uploaded by

Kiran Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 10

PROJECT 1,3 - BUTADIENE GAS STORAGE TERMINAL

EPC & OWNER IMC LIMITED


PERIOD > AUGUST - September 2018

REPORT ON DETERGENT FLUSHING & ACID


CLEANING OF BUTADIENE PIPE LINES
and UTILITIES (LOOP 2)
AT IMC LTD

SERVICE PROVIDED BY

ARUDRA ENGINEERS PVT LTD


No.79, VALMIKI STREET, THIRUVANMIYUR,
CHENNAI, TAMIL NADU, INDIA.Pincode-600041
Phone 044-2490 1623/2445 3425/2443 0705/24430697
Fax-044-2442 4755 E-mail [email protected]
Website-: www.igp-group.com
PROJECT 1,3 – BUTADIENE GAS STORAGE TERMINAL
EPC & IMC LIMITED Page
2 of 10
OWNER
SERVICE BY ARUDRA ENGINEERS PRIVATE LIMITED
REPORT ON DETERGENT FLUSHING & ACID CLEANING OF
BUTADIENE PIPELINES AND UTILITIES (LOOP 2)

1. PREFACE:

Pre- Commissioning cleaning (Detergent flushing & Acid cleaning) of Butadiene pipe lines loop
2 at IMC LIMITED, APM TERMINALS, PIPAVA PORT GUJARAT. The objectives of the process
are to remove Rust, Oil & Grease, and other impurities. The complete process is carried out as
per approved procedure by M/s. IMC LIMITED, & M/s. ARUDRA ENGINEERS PVT LTD.

The Detergent flushing process was carried with coronil-100, this was followed by acid
cleaning carried with coronil-92B and CITRIC ACID, and passivation was done by SODIUM
NITRATE and TSP. The entire system cleaning was carried out as per the following steps;

 Cold water Flushing


 Heated soft water Flushing.
 Detergent Flushing
 Heated water flushing
 Inhibited Acid cleaning
 Mild citric rinsing and Passivation.

2. PROTOCOL REPORT
System Volume: 275 M3 and temporary pipe volume: approx. 15 M3
1 Cold water(service water) flushing was carried out on 27.08.2018
2 Heated soft water flushing was carried out on 28 .08.2018
3 DEGREESING of BUTADINE Pipelines loop2 was carried out from 29.08.2018
Chemicals used coronil-100(0.05-0.1%) = 150 liters.
4 Pigging after Detergent flushing was carried out on 29.08.2018
5 ACID CLEANING:
Note: Loop 2 has been divided into Two parts due to temperature not attained on
vapor line as per the approved procedure.
LOOP II => LOOP II A, LOOP II B.
7 LOOP II A:
7a.ACID CLEANING:
Inhibited acid cleaning was carried out for Loop II A on 30.08.2018
Coroni-92 B(0.2%) > 340 Litters
Citric acid (3%) > 5500 kgs
TSP > 600 KGS
PIGGING was carried out at ship loading line on 31.08.2018
SIGNATURE

NAME

AUTHORITY AEPL IMC LIMITED DNV JDE


PROJECT 1,3 – BUTADIENE GAS STORAGE TERMINAL
EPC & IMC LIMITED Page
3 of 10
OWNER
SERVICE BY ARUDRA ENGINEERS PRIVATE LIMITED
REPORT ON DETERGENT FLUSHING & ACID CLEANING OF
BUTADIENE PIPELINES AND UTILITIES (LOOP 2)

7b.CITRIC RINSING:
Citric acid Rinse was carried out on 31.08.2018. chemicals were used citric acid
(0.2%) =340kgs, TSP=150kgs.

7c.PASSIVATION:
Passivation was carried out on 31.08.2018.
chemicals used were : 1)Sodium nitrate (3%) = 5000 kgs
2)TSP = 2250 KGS

LOOP II B:
8a.ACID CLEANING:
Inhibited acid (Citric acid 2-3%) cleaning was carried out for Loop II B on 01.08.2018
Coroni-92 B (0.2%) > 260 Litters
Citric acid (3%) > 3900 kg
TSP > 850 Kgs
8 8b.CITRIC RINSING:
Citric acid Rinse was carried out on 01.09.2018. chemicals were used citric acid
(0.2%) =260kgs, TSP=100kgs.
8c.PASSIVATION:
Passivation was carried out on 01.09.2018.
chemicals used were : 1)Sodium nitrate (3%) = 3900 kgs
2)TSP = 3750 KGS

INSPECTION& CONCLUSION:
The pre-commissioning Detergent flushing & acid cleaning of Butadiene
pipelines loop 2 were successfully completed. And the completion criteria were
as per the approved procedure. The completion criteria were jointly checked by
M/S IMC LTD, M/S. DNV, M/S ARUDRA and JD Engg (OPaL Surveyor).

SIGNATURE

NAME

AUTHORITY AEPL IMC LIMITED DNV JDE


PROJECT 1,3 – BUTADIENE GAS STORAGE TERMINAL
EPC & IMC LIMITED Page
4 of 10
OWNER
SERVICE BY ARUDRA ENGINEERS PRIVATE LIMITED
REPORT ON DETERGENT FLUSHING & ACID CLEANING OF
BUTADIENE PIPELINES AND UTILITIES (LOOP 2)

1.COLD TREATED WATER FLUSHING


27/08/2018
15:45 System filling started with raw water (All circuit open)
17:50 System filling completed and continuous flushing started
22:10 Water Clarity found ok continuous flushing stopped and draining started
23:20 System drain completed.
2. PIGGING:
27/08/2018 & 28/08/2018

23:40 System filling started with Treated water in order to completely remove service water
from system through pigging.
01:20 System filling stopped for pig insertion at jetty side
02:30 Pigging started from jetty side after completion of pig insertion (10” ship loading line)
05:10 Pig received at receiver end and pump have stopped
05:20 4” pigging started in precooling line from jetty side along with heating.
06:20 4” pig received at receiver end and pump stopped along with burner to remove PIG.

3. HOT Treated WATER FLUSHING :28 .08.2018

07:00 System recirculation started.


07:15 Heating system started to raise the temperature
Time Temperature
Inlet
10:20 41 oC
11:20 42 oC
12:20 43 oC
13:20 45 oC
14:20 46 oC
15:20 46 oC
16:50 50 oC
19:20 55 oC
22:00 Continuous flushing started.
23:10 Water clarity found ok and continuous flushing stopped.

SIGNATURE

NAME

AUTHORITY AEPL IMC LIMITED DNV JDE


PROJECT 1,3 – BUTADIENE GAS STORAGE TERMINAL
EPC & IMC LIMITED Page
5 of 10
OWNER
SERVICE BY ARUDRA ENGINEERS PRIVATE LIMITED
REPORT ON DETERGENT FLUSHING & ACID CLEANING OF
BUTADIENE PIPELINES AND UTILITIES (LOOP 2)

4.DETERGENT FLUSHING:
Date:29/08/2018

12:00 Recirculation started


12:05 Coronil -100 addition started
12:10 Coronil -100 addition completed
Chemicals added:
Coronil-100 => 150 ltrs (0.05

PH TEMPERATURE Total Alkalinity


1:00 8.1 54 175ppm
2:30 8.2 46 175ppm
3:30 8.2 45 200ppm
4:30 8.4 47 225ppm
5:30 8.2 46 225ppm
6:30 8.3 45 225ppm
7:30 8.2 48 225ppm
08:30 8.3 52 200ppm
09:30 DETERGENT FLUSHING COMPLETED And Draining started for pre cooling line
and ship unloading line.
10:30 Drain completed.
11:30 Pigging started for vapor line (8” line)
14:00 Pigging completed for vapor line and filled with Treated Water.

5. CITRIC ACID CLEANING :01.08.2018


SIGNATURE

NAME

AUTHORITY AEPL IMC LIMITED DNV JDE


PROJECT 1,3 – BUTADIENE GAS STORAGE TERMINAL
EPC & IMC LIMITED Page
6 of 10
OWNER
SERVICE BY ARUDRA ENGINEERS PRIVATE LIMITED
REPORT ON DETERGENT FLUSHING & ACID CLEANING OF
BUTADIENE PIPELINES AND UTILITIES (LOOP 2)

Note: Loop 2 has been divided into Two parts due to temperature not attained on
vapor line as per the approved procedure.

LOOP II => LOOP II A, LOOP II B.

LOOP IIA => SHIP LOADING LINE and PRE-COOLING LINE.


LOOP IIB => VAPOR LINE and PRE-COOLING LINE.

LOOP II A ACID CLEANING (PRECOOLING AND SHIP LOADING LINE):


DATE: 01/09/2018
15:00 Filling started at LOOP IIA circuit.
17:00 Filling completed and circulation started along with heating.
TIME TEMPERATURE (oC)
18:00 40
20:00 50
22:00 55
03:00 59
05:00 63
07:00 64
09:40 64
09:40 System temperature is 64oC
09:50 Coronel – 92B = 340 LTRS added. (0.2 %)
11:20 Citric acid (3%)5500 Kgs addition started.
12:15 Citric acid addition completed and TSP 600 Kgs started to increase Ph.
12:45 TSP Addition completed.

Time CITRIC ACID Total iron Temperature Remarks

SIGNATURE

NAME

AUTHORITY AEPL IMC LIMITED DNV JDE


PROJECT 1,3 – BUTADIENE GAS STORAGE TERMINAL
EPC & IMC LIMITED Page
7 of 10
OWNER
SERVICE BY ARUDRA ENGINEERS PRIVATE LIMITED
REPORT ON DETERGENT FLUSHING & ACID CLEANING OF
BUTADIENE PIPELINES AND UTILITIES (LOOP 2)

As Fe PH C)
(o
(%)
(ppm) INLET
(Hrs)
OUTLET OUTLET
13:15 0.2 156 3.8 76
14:00 2.3 6026 3.7 77
15:00 3.2 6981 3.3 74
16:00 3.3 7092 3.5 68
17:00 3.07 6249 3.4 64
18:00 2.09 6311 3.4 62
19:00 2.08 6311 3.3 61
20:00 System Draining started.
20:40 System Draining completed.
21:00 Pig insertion started at Jetty end (10” ship loading line)
22:15 Pig insertion completed.
22:20 Pigging started by filling Treated Water along with temperature 41 oC
01:10 Pigs received at receiver end and pump stopped.

CITRIC RINSING: 31.08.2018


02:40 Pump started after removed pig from 10” ship loading line
02:50 Burner started and temperature is 46 oC,
04:00 Circulation started for citric rinsing.
04:10 Citric addition started. Percentage=0.2%, 340 kgs.
04:20 Citric acid addition completed.
04:25 TSP Addition started to increase 3.5 PH
PH ACID STRENGTH (%) TOTALALKALINITY (PPM) TEMPERATURE (oC)
06:00 3.2 0.2 250 55
07:00 3.3 0.25 350 55
08:00 3.5 0.3 450 54
08:00 TSP addition started (850Kgs) for neutralization process.
09:00 TSP addition completed.

SIGNATURE

NAME

AUTHORITY AEPL IMC LIMITED DNV JDE


PROJECT 1,3 – BUTADIENE GAS STORAGE TERMINAL
EPC & IMC LIMITED Page
8 of 10
OWNER
SERVICE BY ARUDRA ENGINEERS PRIVATE LIMITED
REPORT ON DETERGENT FLUSHING & ACID CLEANING OF
BUTADIENE PIPELINES AND UTILITIES (LOOP 2)

7.PASSIVATION :31.08.2018
10:30 Return PH Checked 10.2 after adding TSP.
Heating System started to raise the temperature.
System temperature is 57oC.
10:35 3 % Sodium nitrate addition started.
11:55 Sodium nitrate addition completed.
Total 5000 kgs of sodium nitrate added.
TIME PH TEMPERATURE REMARKS
12:00 10.00 65 oC
13:00 9.98 63 oC
14:00 9.91 63 oC TSP 800 KGS ADDED
15:00 9.87 63 oC
16:00 9.6 62 oC TSP 600 KGS ADDED
17:00 9.61 62 oC
18:00 9.57 62 oC
19:00 9.54 61 oC
19:05 Drained into Neutralization pit.
LOOP II A ACID CLEANING (PRECOOLING AND VAPOR LINE):
DATE: 01/09/2018
16:00 Filling started at LOOP IIB circuit.
16:20 Filling completed and continuous flushing started
Continuous flushing stopped and recirculation started along with temperature.
TIME TEMPERATURE (oC)

19:00 53
20:00 54
21:00 55
22:00 56
System temperature is 56oC.
22:30 Coronil 92B addition started
22:40 Coronil 92B addition completed. Coronel – 92B = 260 LTRS added. (0.2 %)
23:40 Citric acid 3900 Kgs addition started.
24:40 Citric acid addition completed and TSP addition started to increase Ph.
01:00 TSP Addition completed.

Time CITRIC ACID Total iron Temperature Remarks


(Hrs) (%) As Fe PH (o
C)
(ppm)
SIGNATURE

NAME

AUTHORITY AEPL IMC LIMITED DNV JDE


PROJECT 1,3 – BUTADIENE GAS STORAGE TERMINAL
EPC & IMC LIMITED Page
9 of 10
OWNER
SERVICE BY ARUDRA ENGINEERS PRIVATE LIMITED
REPORT ON DETERGENT FLUSHING & ACID CLEANING OF
BUTADIENE PIPELINES AND UTILITIES (LOOP 2)

OUTLET OUTLET I
01:30 2.9 4743 3.1 68
02:00 2.6 5585 2.9 65
02:30 2.8 3853 3.5 64
03:00 2.7 3970 3.6 62
04:00 2.6 5026 3.5 61
04:30 2.6 5082 3.5 61
05:00 2.6 5138 3.5 60
05:30 2.6 5138 3.6 60
05:45 System Draining started.
07:00 System Draining completed by filling Treated water

CITRIC RINSING :01.09.2018


07:00 Chemical transfer Pump started.
07:05 Burner started and temperature is 46 oC
Circulation started for citric rinsing.
07:10 Citric addition started. Percentage=0.2%, 260 kgs.
07:20 Citric acid addition completed.
07:30 TSP Addition started to increase 3.5 PH
PH ACID STRENGTH (%) TOTALALKALINITY (PPM) TEMPERATURE (oC)
08:00 3.3 0.3 390 60
08:30 3.4 0.22 335 60
09:00 3.5 0.2 223 59
13:30 TSP addition started (total 3750Kgs) for neutralization process.
16:00 TSP addition completed.

SIGNATURE

NAME

AUTHORITY AEPL IMC LIMITED DNV JDE


PROJECT 1,3 – BUTADIENE GAS STORAGE TERMINAL
EPC & IMC LIMITED Page
10 of 10
OWNER
SERVICE BY ARUDRA ENGINEERS PRIVATE LIMITED
REPORT ON DETERGENT FLUSHING & ACID CLEANING OF
BUTADIENE PIPELINES AND UTILITIES (LOOP 2)

7.PASSIVATION :01.09.2018
17:00 Return PH Checked 10.2 after adding TSP.
Heating System started to raise the temperature.
System temperature I/L 57oC and O/L 50oC
18:10 Sodium nitrate addition started.
19:30 Sodium nitrate addition completed.
Total 3900 kgs of sodium nitrate added.

TIME PH TEMPERATURE REMARKS


20:30 10.00 65 C
o

21:30 9.98 63 oC TSP 200 KGS ADDED


22:30 9.91 63 oC
23:30 9.87 63 oC
00:30 9.6 62 oC
01:30 9.61 62 oC
02:30 9.57 62 oC
03:30 9.54 61 oC
19:05 Drained into Neutralization pit.

INSPECTION& CONCLUSION

The pre-commissioning Detergent flushing & acid cleaning of Butadiene


pipelines loop 2 were successfully completed. And the completion criteria were
as per the approved procedure. The completion criteria were jointly checked by
M/S IMC LTD, M/S. DNV. M/S ARUDRA and JD Engg (OPaL Surveyor).

SIGNATURE