Imc Pipelines Loop 2
Imc Pipelines Loop 2
SERVICE PROVIDED BY
1. PREFACE:
Pre- Commissioning cleaning (Detergent flushing & Acid cleaning) of Butadiene pipe lines loop
2 at IMC LIMITED, APM TERMINALS, PIPAVA PORT GUJARAT. The objectives of the process
are to remove Rust, Oil & Grease, and other impurities. The complete process is carried out as
per approved procedure by M/s. IMC LIMITED, & M/s. ARUDRA ENGINEERS PVT LTD.
The Detergent flushing process was carried with coronil-100, this was followed by acid
cleaning carried with coronil-92B and CITRIC ACID, and passivation was done by SODIUM
NITRATE and TSP. The entire system cleaning was carried out as per the following steps;
2. PROTOCOL REPORT
System Volume: 275 M3 and temporary pipe volume: approx. 15 M3
1 Cold water(service water) flushing was carried out on 27.08.2018
2 Heated soft water flushing was carried out on 28 .08.2018
3 DEGREESING of BUTADINE Pipelines loop2 was carried out from 29.08.2018
Chemicals used coronil-100(0.05-0.1%) = 150 liters.
4 Pigging after Detergent flushing was carried out on 29.08.2018
5 ACID CLEANING:
Note: Loop 2 has been divided into Two parts due to temperature not attained on
vapor line as per the approved procedure.
LOOP II => LOOP II A, LOOP II B.
7 LOOP II A:
7a.ACID CLEANING:
Inhibited acid cleaning was carried out for Loop II A on 30.08.2018
Coroni-92 B(0.2%) > 340 Litters
Citric acid (3%) > 5500 kgs
TSP > 600 KGS
PIGGING was carried out at ship loading line on 31.08.2018
SIGNATURE
NAME
7b.CITRIC RINSING:
Citric acid Rinse was carried out on 31.08.2018. chemicals were used citric acid
(0.2%) =340kgs, TSP=150kgs.
7c.PASSIVATION:
Passivation was carried out on 31.08.2018.
chemicals used were : 1)Sodium nitrate (3%) = 5000 kgs
2)TSP = 2250 KGS
LOOP II B:
8a.ACID CLEANING:
Inhibited acid (Citric acid 2-3%) cleaning was carried out for Loop II B on 01.08.2018
Coroni-92 B (0.2%) > 260 Litters
Citric acid (3%) > 3900 kg
TSP > 850 Kgs
8 8b.CITRIC RINSING:
Citric acid Rinse was carried out on 01.09.2018. chemicals were used citric acid
(0.2%) =260kgs, TSP=100kgs.
8c.PASSIVATION:
Passivation was carried out on 01.09.2018.
chemicals used were : 1)Sodium nitrate (3%) = 3900 kgs
2)TSP = 3750 KGS
INSPECTION& CONCLUSION:
The pre-commissioning Detergent flushing & acid cleaning of Butadiene
pipelines loop 2 were successfully completed. And the completion criteria were
as per the approved procedure. The completion criteria were jointly checked by
M/S IMC LTD, M/S. DNV, M/S ARUDRA and JD Engg (OPaL Surveyor).
SIGNATURE
NAME
23:40 System filling started with Treated water in order to completely remove service water
from system through pigging.
01:20 System filling stopped for pig insertion at jetty side
02:30 Pigging started from jetty side after completion of pig insertion (10” ship loading line)
05:10 Pig received at receiver end and pump have stopped
05:20 4” pigging started in precooling line from jetty side along with heating.
06:20 4” pig received at receiver end and pump stopped along with burner to remove PIG.
SIGNATURE
NAME
4.DETERGENT FLUSHING:
Date:29/08/2018
NAME
Note: Loop 2 has been divided into Two parts due to temperature not attained on
vapor line as per the approved procedure.
SIGNATURE
NAME
As Fe PH C)
(o
(%)
(ppm) INLET
(Hrs)
OUTLET OUTLET
13:15 0.2 156 3.8 76
14:00 2.3 6026 3.7 77
15:00 3.2 6981 3.3 74
16:00 3.3 7092 3.5 68
17:00 3.07 6249 3.4 64
18:00 2.09 6311 3.4 62
19:00 2.08 6311 3.3 61
20:00 System Draining started.
20:40 System Draining completed.
21:00 Pig insertion started at Jetty end (10” ship loading line)
22:15 Pig insertion completed.
22:20 Pigging started by filling Treated Water along with temperature 41 oC
01:10 Pigs received at receiver end and pump stopped.
SIGNATURE
NAME
7.PASSIVATION :31.08.2018
10:30 Return PH Checked 10.2 after adding TSP.
Heating System started to raise the temperature.
System temperature is 57oC.
10:35 3 % Sodium nitrate addition started.
11:55 Sodium nitrate addition completed.
Total 5000 kgs of sodium nitrate added.
TIME PH TEMPERATURE REMARKS
12:00 10.00 65 oC
13:00 9.98 63 oC
14:00 9.91 63 oC TSP 800 KGS ADDED
15:00 9.87 63 oC
16:00 9.6 62 oC TSP 600 KGS ADDED
17:00 9.61 62 oC
18:00 9.57 62 oC
19:00 9.54 61 oC
19:05 Drained into Neutralization pit.
LOOP II A ACID CLEANING (PRECOOLING AND VAPOR LINE):
DATE: 01/09/2018
16:00 Filling started at LOOP IIB circuit.
16:20 Filling completed and continuous flushing started
Continuous flushing stopped and recirculation started along with temperature.
TIME TEMPERATURE (oC)
19:00 53
20:00 54
21:00 55
22:00 56
System temperature is 56oC.
22:30 Coronil 92B addition started
22:40 Coronil 92B addition completed. Coronel – 92B = 260 LTRS added. (0.2 %)
23:40 Citric acid 3900 Kgs addition started.
24:40 Citric acid addition completed and TSP addition started to increase Ph.
01:00 TSP Addition completed.
NAME
OUTLET OUTLET I
01:30 2.9 4743 3.1 68
02:00 2.6 5585 2.9 65
02:30 2.8 3853 3.5 64
03:00 2.7 3970 3.6 62
04:00 2.6 5026 3.5 61
04:30 2.6 5082 3.5 61
05:00 2.6 5138 3.5 60
05:30 2.6 5138 3.6 60
05:45 System Draining started.
07:00 System Draining completed by filling Treated water
SIGNATURE
NAME
7.PASSIVATION :01.09.2018
17:00 Return PH Checked 10.2 after adding TSP.
Heating System started to raise the temperature.
System temperature I/L 57oC and O/L 50oC
18:10 Sodium nitrate addition started.
19:30 Sodium nitrate addition completed.
Total 3900 kgs of sodium nitrate added.
INSPECTION& CONCLUSION
SIGNATURE
NAME