0% found this document useful (0 votes)
34 views

Allocation Problem

The document contains two Microsoft Excel reports summarizing the results of solving two allocation problems using Solver. The first report shows an optimal solution was found with a total profit of $172,000. The second report shows another run with the objective changed to a total profit of $0. It indicates all constraints are satisfied in both solutions.

Uploaded by

Siu Rebecca
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
34 views

Allocation Problem

The document contains two Microsoft Excel reports summarizing the results of solving two allocation problems using Solver. The first report shows an optimal solution was found with a total profit of $172,000. The second report shows another run with the objective changed to a total profit of $0. It indicates all constraints are satisfied in both solutions.

Uploaded by

Siu Rebecca
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 9

Microsoft Excel 16.

41 Answer Report
Worksheet: [1. Allocation Problem (1).xlsx]Model (2)
Report Created: 13/10/2020 7:17:19 PM
Result: Solver found a solution. All constraints and optimality conditions are satisfied.
Solver Engine
Solver Options

Objective Cell (Max)


Cell Name Original Value Final Value
$G$10 Objective Function total profit ($) 0 172000

Variable Cells
Cell Name Original Value Final Value Integer
$B$7:$E$7

Constraints
Cell Name Cell Value Formula Status Slack
$G$13 Woods LHS 40000 $G$13<=$I$13 Binding 0
$G$14 Skilled labour LHS 5000 $G$14<=$I$14 Binding 0
Microsoft Excel 16.41 Sensitivity Report
Worksheet: [1. Allocation Problem (1).xlsx]Model (2)
Report Created: 13/10/2020 7:17:20 PM

Variable Cells
Final Reduced Objective Allowable Allowable
Cell Name Value Cost Coefficient Increase Decrease
$B$7:$E$7

Constraints
Final Shadow Constraint Allowable Allowable
Cell Name Value Price R.H. Side Increase Decrease
$G$13 Woods LHS 40000 3.8 40000 60000 2500
$G$14 Skilled labour LHS 5000 4 5000 333.33333333 3000
Microsoft Excel 16.41 Answer Report
Worksheet: [1. Allocation Problem (1).xlsx]Model (2)
Report Created: 13/10/2020 7:30:09 PM
Result: Solver found a solution. All constraints and optimality conditions are satisfied.
Solver Engine
Solver Options

Objective Cell (Max)


Cell Name Original Value Final Value
$G$10 Objective Function total profit ($) 172000 0

Variable Cells
Cell Name Original Value Final Value Integer
$B$7:$E$7

Constraints
Cell Name Cell Value Formula Status Slack
$G$13 Woods LHS 0 $G$13<=$I$13 Not Binding 40000
$G$14 Skilled labour LHS 0 $G$14<=$I$15 Binding 0
Microsoft Excel 16.41 Sensitivity Report
Worksheet: [1. Allocation Problem (1).xlsx]Model (2)
Report Created: 13/10/2020 7:30:10 PM

Variable Cells
Final Reduced Objective Allowable Allowable
Cell Name Value Cost Coefficient Increase Decrease
$B$7:$E$7

Constraints
Final Shadow Constraint Allowable Allowable
Cell Name Value Price R.H. Side Increase Decrease
$G$13 Woods LHS 0 0 40000 1E+030 40000
$G$14 Skilled labour LHS 0 80 0 2000 0
A B C
selling price 5 4 25
quality level 8 7 6

Price of raw materials


Raw material 1 Raw material 2
6 3

production from 1 unit of input of raw materials


A B
Raw material 1 2 3
Raw material 2 1 2

unit of input required for C


C
A 2
B 3

Production and sales


Raw material 1 Raw material 2
unit used 0 0
A B C
Unit produced from raw m 0
>= >=
Units used
Units produced
Units sold
<= <= <=
Max 2000 2500 800

Constraint Level obtained Level required


>=
Question 1

Cost of woods 1.5

Decision Variables Unfinished table Finished table Unfinished chair Finished chair
Xut Xft Xuc Xfc
0 0 0 0

unit profit ($/unit)


Objective Function 70 160 35 130

Availability Constraints
Woods 40 40 30 30
Skilled labour 2 2 5 4
total profit ($)
0

LHS RHS
0 <= 40000
0 <= 5000
Allocation Problem

Decision Variables Chairs Desks Tables


C D T
0 300 25
Constraints on Demands <= <= <=
360 300 100

unit profit ($/unit) total revenue ($)


Objective Function 15 24 8 7400

Availability Constraints on Hours LHS RHS


Fabrication hours 4 6 2 1850 <= 1850
Assembly hours 3 5 7 1675 <= 2400
Shipping hours 3 2 4 700 <= 1500

(LHS=Usage) (RHS=Availability)
(RHS=Availability)