Brickwork 3 and Associated Studies
Brickwork 3 and Associated Studies
9 780333 519578
BRICKWORK 3
AND ASSOCIATED STUDIES
Related volumes
Brickwork 1 and Associated Studies ~ Harold Bailey and David Hancock
Brickwork 2 and Associated Studies S
David Hancock
Senior Lecturer
Stockport College of Technology
Second Edition
palgrave
macmillan
© (The estate of) H. Bailey and D. W. Hancock 1979, 1990
Published by
MACMILLAN EDUCATION LTD
Houndmills, Basingstoke, Hampshire RG21 2XS
and London
Companies and representatives
throughout the world
This book is printed on paper suitable for recycling and made from fully
managed and sustained forest sources. Logging. pulping and manufacturing
processes are expected to conform to the environmental regulations of the
country of origin.
CONTENTS
4. Step Construction 31
9. Quantities of Materials 108
Requirements for brick and concrete steps 31
Bricks and mortar 108
English and Flemish bonds 112
5. Drainage 35 Blocks and mortar 112
Volumes of concrete 114
Subsoil drainage 35 Dry material requirements 115
General principles of drainage 39 Number of floor tiles or paving slabs 116
Drainage systems 45 Bricks for paving 119
v
vi Contents
Some Useful Conversion Factors 121 Answers to Multiple Choice Questions 130
This series of three volumes is designed to provide an introduction to the brickwork craft and the construction
industry for craft apprentices and all students involved in building. All too often, new entrants to the construction
industry are expected to have a knowledge of calculations, geometry, science and technology irrespective of their
previous education. It is the authors' aim to provide a course of study which is not only easily understood but is
also able to show the relationship that exists between technology and associated studies.
The construction industry recognises that the modern craftsman, while maintaining a very high standard of
skills, must be capable of accepting change - in methods, techniques and materials. Therefore it will be necessary
for apprentices to develop new skills related to the constant advancements in technology.
This third volume concludes the complete Craft Certificate course for the City & Guilds of London Institute,
and includes the many other areas of work in which the craftsman is required to demonstrate his ability.
To become a highly skilled technician in the modern construction industry, the apprentice should recognise
that physical skills must be complemented by technology, and that planned methods of construction must be
used in all work situations.
The apprentice and young craftsman will be able to appreciate the diversity of the bricklayer's craft, and to
relate his own abilities and ambitions to the immense scope offered by today's construction industry.
H. BAILEY
D.W.HANCOCK
ACKNOWLEDGEMENTS
The authors wish to acknowledge the assistance and cooperation of: The Clay Pipe Development Association Ltd,
for figures 5.19, 5.20 and 5.21; S.G.B. Scaffolding (Great Britain) Ltd, for figures 6.6 to 6.21, 6.29 and 6.33;
Hilti Ltd for figures 6.26, 6.27 and 6.28; The Brick Development Association, for figure 6.30; Walter Somers
(Materials Handling) Ltd, for figures 6.40, 6.41 and 6.42.
vii
1
SAFETY ON SITE
1
2 Brickwork 3 and Associated Studies
Table 1.1
Numbers of employees
Item
1-5 6-10 11-50 51-100 101-150
Guidance leaflet
Individually wrapped
sterile adhesive 20 20 40 40 40
dressings
Sterile eye pads with
attachments 2 4 6 8
Sterile coverings for
serious wounds (where 2 4 6 8
applicable)
Safety pins 6 6 12 12 12
Medium sized sterile
unmedicated dressings 3 6 8 10 12
Large sterile
unmedicated dressings 2 4 6 10
Extra large sterile
unmedicated dressings 2 4 6 8
Notes
1. The provision of triangular bandages and also sterile coverings for serious wounds
is recommended. However, where the triangular bandage is sterile, this product
satisfies both requirements.
2. Scissors are not to be kept in a first aid box. These should be kept in a locked
drawer under the supervision of the first aider, along with any tablets such as
aspirins, paracetamols etc.
4 Brickwork 3 and Associated Studies
The following basic principles of first aid should Before a hoarding can be erected in any· public
be the minimum common knowledge of all. thoroughfare, the contractor must obtain a licence
from the Local Authority who must be provided with
(1) Check for dangers, and ensure complete safety
full constructional details of the hoarding prior to
exists before proceeding.
issuing a licence, which usually takes between 10 and
(2) Ensure the casualty is breathing.
20 days.
(3) Check for circulation. Is there a pulse?
A hoarding is of course a temporary structure,
(4) Stop severe bleeding; the loss of three pints of
consisting basically of posts, rails and sheeting of
blood can result in loss of life.
some kind (see figures 1.2 and 1.3). It should be not
(5) Never move a casualty with a back injury unless
less than 2 m in height, and if it needs to be higher
there are other dangers.
than this it may also require rakers and anchors
(6) With electrical injuries, turn off at plug or mains.
(figure 1.4). Concrete posts (spurs) may be used for
(7) Turn an unconscious or semi-conscious casualty
the initial supports, let well into the ground and held
into the recovery position (figure 1.1).
in position by a mass concrete surround. Timber
(8) Immobilise fractures in the position found. Do
posts are bolted to these spurs and connected by
not attempt to straighten broken limbs.
horizontal rails which in turn support the sheeting
(9) Reassure all casualties. Stay with them and send
(figure 1.4). Scaffold tubing too is useful for hoard-
by-standers for help.
ings, faced for example with corrugated sheeting. A
To conclude this chapter on safety, the authors hoarding should be painted white and bulkhead warn-
feel the need to stress the importance in the correct ing lights should be attached at intervals along its
use of plant, equipment, tools and apparel. All site length.
personnel should ensure that all safety aids are used
whenever there is the slightest possibility of an acci-
dent occurring.
When measuring the efficiency of a completed
construction project, it is necessary to take into
account the following:
(a) Did any accidents occur during the project?
(b) Were any injuries of a serious nature incurred?
(c) What were the total operative hours lost through
accidents?
(d) Could the accidents have been avoided? Were
adequate precautions taken? Has remedial action
been taken?
No less important to safe work on a construction
site is the protection of the public outside the site.
75 X 50 rails
corrugated
sheeting etc.
100 X 75
anchors
surround in
well-rammed
exc. material concrete
or mass spurs set in
concrete .. mass concrete
mass concrete surround
Figure 7.5 Where a hoarding encroaches on a footpath Figure 7.6 Scaffold with fanguard
2
DECORATIVE AND FUNCTIONAL
FEATURES
In the construction industry designers are now taking edge rather than the upper edge in order to provide a
advantage of the modern technology that enables the perfectly straight line (figure 2.1d).
manufacturers to supply materials considerably
superior in quality to those available years ago. The Dog-tooth Courses
result is that many newly constructed buildings have
fas;ades consisting of contrasting-coloured bricks with Dog-tooth courses are another means of forming a
surface textures chosen to suit the particular environ- decorative effect on the face of brick walls; the dog-
0
ment. toothing is obtained by setting each brick at 45 to
While colour and texture have improved we find the wall face. Dog-tooth courses may be projecting,
that many buildings lack the decorative aesthetic flush or recessed from the wall face. Bricks are used
qualities that are to be seen in older buildings; decora- flat or on end (figure 2.2); they should be set to line
tive face bonds are seldom used, and buildings now and checked for accuracy and position with a triangu-
constructed with drab and plain face areas could be lar templet (figure 2.3).
greatly enhanced by including decorative features in To provide a more decorative effect and increase
the brickwork. the depth of band, continuous courses of dog-toothing
are often used (figures 2.2 and 2.4). It is also common
practice to form dog-tooth courses between the over-
sailing courses. When bricks are laid flat to form dog-
STRING, DENTIL AND DOG-TOOTH COURSES tooth courses in walls one brick thick, half bats are
used to form the dog-toothing, thus allowing for a
String Courses fair face to be obtained on the opposite face of the
wall. When the wall is over one brick in thickness, a
These are sometimes known as band courses and are stretcher course can be used at the back of the dog-
used to provide a distinct horizontal break in the tooth courses.
fas;ade of a building. They form subdivisions and
interrupt the continuity of the facework, usually at
storey height. A string course may be recessed, flush DECORATIVE TREATMENT OF QUOINS
or projecting, and soldiers are often used for this
purpose. Any decorative feature passing right round a The external quoinsofa building are perhaps the most
building around storey height, possibly consisting of obvious position to create a decorative feature, yet in
contrasting bricks or a different bonding arrangement, modern construction this is rarely seen to be done.
is called a string or band course. See figure 2.1a, b. To create a decorative effect with a quoin, irrespective
of the bonding arrangement of the walling, does not
Dentil Courses greatly increase the cost of labour, and the appear-
ance of a simple return quoin can be greatly enhanced
These are header courses, with alternate headers either
by the formation of either:
projecting from the wall face or recessed. The projec-
tion or recess is usually kept to 19 mm, increasing to (a) an indented or recessed quoin
a maximum of 27 mm (figure 2.1c). Soldiers are (b) a rusticated quoin.
occasionally used for this purpose (figure 2.1d).
In order to form a string or band course, dentils (1) Indented or Recessed Quoins
can be used between oversailing courses (figure 2.1f).
When building projecting string courses such as these, These are formed by recessing a number of brick
the bricklayer's line must be fixed on the bottom courses at the quoin over a short length of walling.
6
Decorative and Functional Features 7
la) Ib)
projecting headers
forming a dentil course dentil course formed
Ie) within projecting band
courses
Id)
The height of the recessed work usually comprises pends in a vertical line. Certain other recessed bricks,
one, two or three courses and the depth of the recess too, will need to be cut.
is rarely in excess of 20 mm since unless the bricks
are very dense and weather-resistant any exposed (2) Rusticated Quoins
arrises will tend to suffer from frost attack.
It will be obvious from figures 2.5 and 2.6 that the These can basically be described as being the opposite
quoin bricks of the recessed work are cut on both to recessed quoins. Here the selected brick courses
header and stretcher faces in order to keep the per- project over a short length and the projection once
8 Brickwork 3 and Associated Studies
templet
templet used to set
2·course dog-toathing dog-toathing course
Figure 2.3
Figure 2.4
Decorative and Functional Features 9
Figure 2.5 Indented or recessed quoin in English bond Figure 2.6 Indented or recessed quoin in Flemish bond
Figure 2. 7
70 Brickwork 3 and Associated Studies
PATTERN WALLING
Pierced Work
strapwork
coffering
Figure 2.73
constructed of concrete blocks. These blocks are pro- A brick panel can be formed with a brick frame
vided with a recess to accommodate the walling blocks. around the panel, or the panel can be formed within a
Plinths and copings can also be used to obtain in- recess in the walling. When a frame is used the base and
creased stability and increase the decorative effect of sides should always be constructed before the panel is
the walling (figure 2.20). inserted, and should be formed with lines whenever
possible (figure 2.21). If the panel is to project, the
brickwork courses at the back of the recess are built
using the bricks flat, but if a sunken or recessed panel
DECORATIVE BRICK PANELS is required, the courses of brickwork at the back of
the recess should be formed with brick on edge and
The use of the panelled surface has long been a method block indenting into the brick walling on each side.
of increasing the decorative qualities of walling. The
use of the sunken or raised panel is often seen as a
method of forming a feature in plain areas of walling Bond for Panels
and between piers. Placing of panels should be done
with the utmost care. The dimensions and shape of Brick panels can be formed with basket-weave or
the panel should coincide with the area of brickwork herringbone bonds. Although diagonal and other
involved. Heavily sunken or too great projections bonding arrangements can be used, the designer
often dilute the decorative effect intended for the usually favours the former to provide the decorative
feature. effect required (figure 2.22).
Decorative and Functional Features 13
Figure 2.75
14 Brickwork 3 and Associated Studies
are all the same and occur on both sides of the panel
(figures 2.23-2.26).
Single, double and feather herringbone panels are
set out at 45°. Diagonal lines, vertical and horizontal
centre lines are required before setting out can begin
(figure 2.24). The same procedure is also used for
diagonal basket weave but normal basket weave and
diagonal herringbone require only vertical and hori·
zontal guide lines.
I I 1 j 1 I
• to.~
,....- .....~
... I-.,-'-'
1-"'" •...
I--- " ',' '.' " ' .. - .,, .'
~
I--'-----r--f ...
~" ~".
f-- .,. " . . '..
~ ~
"
.....
~.
'~'
:"
..~.:. ';.' '.~.:' '.•
I--'-........,
r--'-.......'*f ..•., .- •.: '. I I--'--.........,f ..
".'
:' '"
-~ ;. ',: ...~~ ~ "
f---''---,......-f
.... :.:' :..../.; ,.
1--'-....,.,."",: /' ," .... ,.
--
-',' :.:.. ' '~::.> . ,. ~.'" .~~ /,~ ..
~.}--'--r-t I--'----......."!!.
.•• ' ,
",:. I
I-~-r-.~:""!.~ . ;: :, ~ ..~..[
~-
I--'--T:'-f' :~:' i·
r '. : .. -
r'
1--'--........-1
'.~'.", ':';1 -
I--'----....."..":-,!.:-
....
I 1 1 I I j 1 j J.~l,--,IL-',-----,l• ....,J1---l1---l1---L1--l.--LJ_-,--
1_-1--1....,
Figure 2.78 Internal decorative wall in diagonal herringbone bond using brick on edge
courses and projecting contrasting bricks
~~,J.L--.....\verticaland
horizontal working
lines for building
panel frame
line pins
Cutting the first three bricks for a single herring- 2 Measure the exact length of one of the bricks,
bone panel (marked 1 , 2 and 3 in figure 2.26) mark the same length from the corner onto the
often causes problems, but these are quite straight- other brick and mark across in pencil.
forward. The complete method is explained in figure 3 Cut the bricks using a lump hammer and bolster.
2.30: If an electric saw is used, the offcut will be too
small.
Stand two bricks on edge, face upwards, perfectly 4 The smallest offcut from the two bricks used will
square to each other and leaving a 10 mm cross fit perfectly in the position shown.
joint between the two.
Decorative and Functional Features 17
,, /
/
/
/
.?_.... _...,7:_-,.L-;>.,-
y
.= ~~ for checking
opening, less the
thickness of a
mortar joint on
all four sides
timber templet--jl-f>-~~~'~
can be adjusted
and positioned to
suit bonding of
panel
Figure 2.28 Use of timber templet for setting out and marking decorative panels
1.
2.
3.
Building-in
I
feather herring bone feather herring bone
Figure 2.32
brick·on-end
sotdiers forming
band on plinth course
required. If the wall is built in stretcher bond, the only; this brick is really one of two bevelled
width of the cavity is increased below the offset closers.
course and the correct width of cavity is formed at (3) It is acceptable to use header over header or
the level ofthe plinth course. For solid walls the ,;ollar stretcher over stretcher provided that there is a
joint is increased in width to obtain the same effect. lap of 56 mm (figures 2.34b and 2.35).
The above method has its disadvantages because (4) If necessary the plinth courses can consist of
the offset formed provides a ledge that is always vul- courses of stretchers, even if this is different
nerable to weather penetration even when a mortar from the walling bond.
fillet is applied. To provide a better form of weather- (5) The courses of brickwork below the bottom
ing, plinth courses are normally formed with purpose- plinth course must always be considered last and
made splay bricks, which can be obtained in headers, bonded accordingly. This may involve the use of
stretchers and returns. Bonding these special plinth broken bond, but this must be a secondary con-
bricks and plinth courses has always posed consider- sideration, and the inclusion of cut bricks cannot
able problems for the craftsman, but the problems always be avoided (figure 2.33e and 2.34c).
can be greatly reduced by applying the following
Figure 2.38 illustrates a decorative quoin constructed
rules for bonding plinth courses.
with plinth courses and inverted splay bricks.
Rules for Bonding Plinth Courses
(1) Always consider first, and bond in the course of CORBELLING BRICKWORK
brickwork immediately above the top-most
plinth course. It may be necessary during building operations to
(2) It is permissible to use a queen closer on the face increase the thickness of walls, or form, or increase
of the wall, at a return quoin, for one course the dimensions of attached piers. The operation,
(b) 2-plinth courses formed on both faces using external (e) l-plinth course on both faces with
returns on quoin external return on quoin
Figure 2.35 Plinth courses used to form an attached pier in Flemish bond
piercings_ _...p...lIM''-
Figure 2.37 Method of forming plinth courses with splay bricks and offets, incorporating
pierced walling and diapers
22 Brickwork 3 and Associated Studies
~
~I\ concrete
<;,cf,~("" slab
-?
corbel templet
Figure 2.45 Figure 2.47 Methods of terminating attached piers
24 Brickwork 3 and Associated Studies
I I I I I
I I J
where wall courses
II J J. J.
j are an odd number
I the tumbled courses
weathering __ must also be an odd
fJ :::r ~ number; where wall
I J courses are an even
I I number so are the
r 1 )-"'---+-L:>.-+---'-+...---l.-J
tumbled courses
I I II
I I I
elevation side elevation
Figure 2.48
I I I I
I---
Figure 2.49
9 tumbling
I courses
~~
I I f-L- I
I
r--
bond
adjusted
here
front elevation end elevation
plan of course 2
Figure 2.50
Decorative and Functional Features 25
\.
~-----f2
"r---------; 2
:h-'.........,........,.~-----__i-
drip
" 11
'I
I I
steel square I~building line
to check tumbled
courses at right-angles I line of wall face
to inclination
radius of ----t+I:)4--,-Y--+--'--r-l
circle used to
provide projection
for drip.
max. radius 32 mm
Figure 2.53 Building tumbled-in work: method of Figure 2.54 Building tumbled -in work: use ofgun or
setting out the tumbling courses stock to assist in the aligning of tumbled courses,
with the bevel providing the angle of cut for the
tumbled courses
(6) all tumbled courses should be at right-angles to courses are all at right-angles to the inclination (figure
the inclination (figures 2.48 and 2.53). 2.53). The angle formed between the tumbled and
the horizontal courses is obtained with a bevel, which
can then be used to mark the angle of cut (figure 2.54).
To build tumbled-in brickwork it is necessary to erect To ensure that good effective weathering is pro-
building lines to provide the lines for the inclination; vided it is essential that all tumbling-in courses are
a gun or stock should also be formed, which can be completely parallel to the angle of inclination, other-
used to check the surface of the work and also as a wise water may rest on any ledges that are formed.
gauge rod for the tumbled courses (figures 2.53 and Cement mortar should be used and the bricks should
2.54). To comply with rule 1 it may be necessary to be capable of resisting weather penetration. When
adjust the courses of the tumbled-in work, by either tumbling-in work is accurately carried out, the
increasing or reducing the bed joints. buttress will always be a decorative and functional
Checking the tumbled-in courses during erection is feature that demonstrates the skills of the bricklayer
carried out with a steel square to ensure that the craftsman.
3
REINFORCED BRICKWORK
Figure 3.2 Reinforcing short returns using Exmet Figure 3.3 Horizontal reinforcement using Brickforce
walling 26
Reinforced Brickwork 27
This is similar in appearance to Brickforce but used to This is a stainless steel or galvanised wire mesh supplied
strengthen cavity walls. It is supplied in strips 3150 mm in 25 m or 75 m rolls, in widths ranging from 50 to
long, the width of each strip being 222 mm. Four 300 mm. Some typical uses of Bricktor are:
main wires run parallel along the length of the strip,
(1) Carrying brickwork over door openings. By
joined by welded cross wires at 450 mm centres,
incorporating the mesh in the bed joints, conven-
which take the place of conventional wall ties in
tional lintels can be omitted, often to the benefit
cavity walls (figures 3.4 and 3.5).
of the appearance (figure 3.6).
(2) Bonding and strengthening corners and inter-
sections of walls.
(3) Tying of walls to reinforced concrete frames.
(4) Resisting cracking of walls in areas of uneven
settlement.
(5) General control of shrinkage and thermal crack-
ing.
L.-....J
o
o Figure 3.6 Using Bricktor over door openings
o
o
-2Sar7Sm
"'"
222.5
w.llfon:. •
All dlrntnSiOnS In mill
Hoop-iron Reinforcement
POSITIONING OF REINFORCEMENT
Minimum
Clear span of opening Number of courses height of brickwork
(m) reinforced above opening
(mm)
1.2 2 600
1.3 3 (figure 3.17) 750
1.8 3 900
2.0 4 1075
6-mm-dia. stirrups
fixed on 9-mm-dia.
~~'b.L"'~I~"T wall ties rod every alternate
course
9-mm rod
Figure 3.13 Wall ties fixed on 20 mm rod on every
alternate course Figure 3.14 A reinforced brick lintel
Steps are formed to provide access from one level to Building Regulations 1985 and the minimum going,
levels above and should be designed to prevent un- pitch, maximum and minimum rise and width are
necessary fatigue or physical discomfort. Steps may now determined by the type and use of the building.
be formed in brickwork, concrete or a combination The dimensions given in figure 4.1 refer to domestic
of both materials. buildings only.
To understand the construction of any type of step Steps can be supported by walls or concrete
work it is necessary to have a knowledge of the (figures 4.2-4.4). They can be built in during con-
following definitions. struction or fixed at a later date.
Riser The vertical face between consecutive treads.
Tread The upper surface of a step. Concrete Steps
Rise The vertical distance between consecutive steps
or between step and landing. When concrete steps are built into the walling, either
Pitch line The notional line that connects the nosings during construction or later, it is necessary to provide
of all treads. a gauge staff, which should be formed to suit the
Pitch The angle formed between pitch line and the brickwork courses and the height of the risers (figure
horizontal. 4.2). When the steps are fixed at a later date, the wall
Nosing The front edge of a step or tread. should contain recesses, formed in the brickwork or
Going The horizontal distance on the plan between sand courses, to accommodate the concrete steps
the nosing of a tread and the nosing on the tread above. (figure 4.2).
Flight Part of a stairway, or ramp, which may consist Concrete steps, when formed as precast units, can
of a step or consecutive steps. have stepped or sloping soffits, the latter having
Parallel Steps of uniform width. squared seatings at each end to rest on the walling
Width The distance between the nosing and the face (figures 4.3, 4.5 and 4.6).
of the riser (figure 4.1).
Brick Steps
REQUIREMENTS FOR BRICK AND CONCRETE Brick steps should be built of durable bricks, which
STEPS should be able to resist abrasion and weather and
should be set in cement mortar suitable for the type
All steps must be built or formed to comply with the of brick used.
total
max.
220 mm rise of
min. _;;,;st::!eP::.--::::========_ _.....L _
75mm
Figure 4.1 Building Regulations requirements for step construction
31
32 Brickwork 3 and Associated Studies
gauge rod
for steps
and
brickwork
L...o',[/"'~:;oI<l"""''b.L.J:"7''''---
recess for step
.. ...--sand courses
Balustrades
...
.....:::::.- soffit line
r---L~/:"",-,_
prevents slip
Figure 4.6
~ ....... handrail
~balusters
The object of a drainage system is to convey foul, through this drain or otherwise to ensure that no sub-
waste or surface water to the sewer or other place of soil water entering such a drain causes dampness of
disposal without danger to health. This means that the site of the building.
the pipework must be airtight and watertight in order Drainage of subsoil water may be necessary for
that both solid matter and liquid matter are removed any of the following reasons
from a building without foul odours escaping, except
where this is part of the design (see figure 5.35). (1) to prevent surface flooding and thus improve
Definitions of water types are as follows (figure 5.1) conditions for building
(2) to lessen the amount of dampness occurring in
Surface water The run-off of natural water from the foundation brickwork
ground surface, including paved areas, roofs and un- (3) to prevent foundation trenches from becoming
paved land. waterlogged
Ground water In permeable ground the surface water (4) to increase the stability of the subsoil and the
will percolate downwards towards the water table, ground surface
being held temporarily in suspension. (5) for agricultural purposes
Subsoil water Water occurring naturally below the (6) to lessen the humidity that can occur when
ground surface, the depth varying with the season. buildings are erected on damp sites.
Waste water The discharge from lavatory basins,
baths, sinks, etc., that is, water not classed as surface Systems
water and not contaminated with soil water.
Soil water The discharge from soil appliances such as The following are the usual methods of carrying out
water closets, urinals, etc. subsoil drainage, depending on the location of the site
and the conditions prevailing.
Natural
ground water Trenches are excavated and pipes laid to follow the
natural contours on the site with branch drains dis-
charging into the main drain as necessary (figure 5.2).
water table -4~>77"77?~~'77.;"77777.77'>".:I
subsoil water ~~~~~~;.u..u..<.~e<...<..,..
Figure 5.1
SUBSOIL DRAINAGE
Herringbone
fan
Figure 5.5
1/
V Moat or Cut-off
V
V Subsoil drains are laid around a proposed building,
V thus intercepting the flow of subsoil water (figure 5.6).
V
V
/
hernngbone
Figure 5.3
Parallel
On a smaller site, branches from one side only may be moat or cut-off
sufficient (figure 5.4).
Figure 5.6
Figure 5.4
Pipes
backfill
C1ayware
Figure 5.9
~ black bando:g]f- --JI
A : s : : ]-Jlt......t..1-J&t......t..-1--i-...JI
(c) perforated c1av pipes
Figure 5.8
Clay Drainpipes
subsoil drain
Types of clay drainpipe available include butt-jointed,
'seconds' and half and fully perforated pipes (figure Figure 5.10
5.8c). Butt-jointed pipes normally have a tile over the
joint to prevent direct ingress of silt, and seconds
(identifiable by the black band) are laid open-jointed
with level inverts (figure 5.8b). Where the half-perfora-
ted pipes are used the perforations are usually kept in
the underside so that the pipes will not silt up due to
fine particles moving downwards with ground water. hardcore
Other kinds of pipe for subsoil drainage include or rubble
concrete porous, perforated vitrified, pitch-fibre per-
forated and polythene slotted pipes. They are usually
laid to follow the fall of the land where possible and
in trenches to a minimum depth of 600 mm. After
surrounding the pipes with hardcore or rubble the
pipework is then covered with an inverted layer of french drain
turf, which acts as a filter, and the trench is filled
with permeable soil (figure 5.9). Figure 5.11
Alternatively, the trench can be filled to just below
ground level with hardcore (figure 5.10), or a french
drain can be used, which usually consists completely Soakaways
of hardcore (figure 5.11).
The outfall from a subsoil drainage system should $oakaways are pits that are excavated in permeable
be led to a stream if possible, to soakaways where the
soil and suitably prepared to receive ground water.
ground is sufficiently permeable, or to a waste-water
drain via a catchpit (figure 5.12). (1) The pipework is led into the pit, which is filled
38 Brickwork 3 and Associated Studies
catchpit
Figure 5.12
0.2m
/
/
soakaway: hardcore .i ...
topsoil
. v v •
(2) Precast concrete sections are placed where 0.8 m stiff clay
required and excavation is carried out from the
inside, the sections sinking under their own
weight. These have a large, easily calculated stony soil
capacity but costs are incresed (figure 5.14).
Figure 5.16
Rainwater, Waste and Foul Water unless there is an inspection chamber situated
at that junction
All domestic buildings must be provided with efficient (c) at the highest point of a private sewer unless
drainage systems in order to dispose of rain, waste there is a rodding eye at that point
and foul water. The system must discharge into a Note The maximum distance between manholes
main sewer, a septic tank or a cesspool, depending on on a drain or private sewer is 90 m.
the availability of these alternatives. The sewer is laid (11) Pipes must be laid at depths to prevent acciden-
and maintained by the local authority, usually below tal disturbance or be adequately protected by
the road or footpath, and the house system must be haunching or be surrounded in concrete.
connected to this either at an inspection chamber (see (12) Waste pipes to ground floors must discharge
page 64) or between inspection chambers by means below grating level but above the water seal.
of a saddle (see page 56) fitted to the cheek of the (13) Vent pipes are to be of sufficient height and to
sewer. be fitted at the top with a durable cage to
Septic tanks and cesspools are outside the scope prevent ingress of birds, leaves, etc.
of the craft syllabus but will be covered in an advanced (14) Only one connection per dwelling is made to a
volume. main sewer (figures 5.28-5.33).
(15) Drains should not pass under buildings unless
this is unavoidable, for example, where the
GENERAL PRINCIPLES OF DRAINAGE length of a drain would be substantially increas-
ed or where sufficient fall cannot otherwise be
(1) The drainage layout should be as simple and obtained (figure 5.17).
direct as possible.
(2) Materials used should be hard, smooth, non-
corrosive and true in shape.
(3) Pipes should be laid to falls to give a self-cleans-
ing velocity. This is generally considered to be a
flow of between 0.75 and 3 m/s. While Maguire's
rule is to some extent outdated it gives a flow,
~
depending on the type and condition of the
pipe, of 1.375 mis, that is, where a 100 mm
~
pipe is laid at a fall of 1 in 40, alSO mm pipe is
laid at a fall of 1 in 60, and a 225 mm pipe is
laid at a fall of 1 in 90.
(4) All joints must be airtight, watertight and free
~
-- 0/
,....- ... - -
from internal obstruction.
(5) Lines of pipes between inspection chambers are / t
to be as straight as possible, both horizontally
and longitudinally.
/ I
!
(6) All inlets to drains must have a water seal of at - - - - - - -- - ..... - - - --- I
plan
least 50 mm, except soil and ventilation pipes
alternative routes shown dashed
(see page 63).
(7) Branches should be kept as short as possible. Figure 5.17
(8) The greatest volume in flush should be at or
near the topmost point of the drain where
possible.
(9) All junctions should be made with the flow. Where drains do pass under buildings precautions
(10) Adequate means of access and inspection must must be taken as necessary to prevent damage to, or
be provided. Inspection chambers must be loss of water tightness in, the drain or private sewer
placed by differential movement. The principles to be
(a) at each point where there is such a change followed here are
of direction or gradient as would prevent any
part of the drain being readily cleansed without
such a chamber (1) Surround the pipe in at least 100 mm of granular
(b) on a drain or private sewer within 12.5 m material or other flexible filling.
from a junction between that drain or private (2) An inspection chamber should be placed outside
sewer and another, a private or public sewer, at least one end of the run under the building.
40 Brickwork 3 and Associated Studies
U1j
I·· 'I
10 give !'lOmm space a"
round the pipe British Standards 65 and 540 Part 1 specify the
..."-. ~
11.-'-.-'-.-= J.. mask opening bolh sides requirements for clay pipes and fittings, with or with-
~.- with rigid sheel male".1
out sockets, that are suitable for drains and sewers
under two descriptions
(1) British Standard, for foul sewage and/or surface
water
short length 01 pipe bedded
or in wall. joints Jormed within (2) British Standard Surface Water, for surface water
l50mm 01 either walllace.
Adlacent rocker pipeS 01 only
max. length 60Qmm with
llexible toints and pipes must be clearly marked as such. Pipes and
fittings of either description may be glazed or un-
glazed externally, internally or both.
Part 2 of the Standard specifies the requirements
for flexible joints for pipes complying with Part 1.
polyester
mouldings
-=- ~
rUbb~ rubber
sealing sealing
ring ring
1// ......... -=
(a)' tarred gaskin and cement mortar joint (b) polyurethane joint (c) O-ring joint (d) sleeve joint
JL
c: ==~
straight channel
-==~=:J taper channel
~ taper bend
~~~~b
long 90"
bend
medium 600
bend
short 45
bend
22Yo.° bend 11140 bend
dZ1'iA 1~
(all bends shown are right hand)
1~1'~
~ ~ 1L
~~~
300 short oblique
right-hand
junction 21.:
oblique right-
hand junction 5OO<j
~ tl° ~ ~
~oo 70~
eooL!
~ ~
O
right/left-hand left-hand
double junction double
junction
~~15' 1150
0~
~~1~
~ \}.
~ ~ "
breeches
oblique
junction
double curved
oblique junction
140
165
0
0
Q~
(} ~
Yo. section bends
with splayed ends
~ section bends (right hand) (left hand)
socket
~';,.,
1a.-~ilO
,""'' ' i 1 I \ " rffi
j ,.-n,."\y i n :::a
•
straight pipe taper pipe perforated pipe butt pipe
long bend long bend long bend medium bend short bend rest bend
(11'4° ) (22Y,0) (45°) (60°) (knuckle)
double
socket
~ \1
gully top
rainwater shoe
road gully
gully trap
drain chutes
~ square
saddle
~ oblique
saddle
(1) Ensure that both spigot and socket are free from Laying the Pipes
grit or mud etc.
(2) Insert a clean rubber ring into the O-ring recess. The pipes are laid directly on the bedding material
(3) Apply the special lubricant to the exposed surface and the joints are made with either a straight (sleeve)
of the rubber ring within the socket and to the coupling or a snap-ring joint (figures 5.24 and 5.25).
chamfered area of the spigot end.
(4) Bring spigot and socket into alignment and push Straight Couplings (figure 5.24)
the spigot home (figure 5.22).
The pipe spigots are wiped clean and a coupling is
Pitch-fibre Pipes fitted hand-tight to one spigot of each. Place the first
pipe in position against a suitable stopboard (figure
This type of pipe is flexible, light in weight and 5.26) and fit the spigot of the second pipe into the
generally available in lengths between 2400 and 3040 coupling of the first. A softwood dolly (figure 5.26)
mm. While pitch-fibre pipes are considered unsuitable is placed against the coupling of the second pipe,
44 Brickwork 3 and Associated Studies
which is then driven home with a 1-2 kg hammer. The pushing a pipe with a coupling fitted into the coupling
amount of drive should be 6-7 mm and it is important on a previously laid pipe using a spade as a lever.
not to overdrive. It is possible to complete a consider- Pitch fibre pipes are rarely used nowadays; they are
able length of pipe at ground level if required and to no longer produced in the United Kingdom and are
lower it into the trench afterwards. not mentioned in current Building Regulations.
Note When using these couplings it is necessary to
support the back of a bend or a branch junction while
driving (figure 5.27).
Pipe Bedding and Backfilling
Snap-ring Couplings (figure 5.25) Figure 5.28 shows two suitable methods for rigid
pipes and one for flexible pipes. Each of these will
The snap-ring is placed over the end of a plain-ended satisfy Building Regulations requirements.
pipe with the flat of the ring against the pipe, and the Figure 5.280 requires a high standard of workman-
coupling is pushed on to this, forcing the ring to roll ship. This method must not be used unless accurate
along the pipe. The ring is compressed and jumps into hand-trimming by shovel is possible.
the required position. Pipes are jointed in a trench by Figure 5.28b is generally suitable in all soil con-
before aher
driving driving
~i-
initial contact
~I-
amount of drive
usually 7-12 mm 6-7mm
I
II II
II
II
II
II II
II
II
II
II
II
.
II
II
II
II
II II
Figure 5.26
Drainage 45
DRAINAGE SYSTEMS
~
WG
SP____ both the treatment plant and the diameter of the
""l1J
sewer can be relatively small.
(2) storm overflows are not required,
(3) there is no possibility of water pollution from
overflowing sewage during bad weather, since the
RWG , flow is constant.
yGo----------~~ 0 Disadvantages are
(1) there are two sets of pipes to lay and maintain
(2) there is a risk of connecting to the wrong sewer
(3) the pipe layout may be complicated with pipes
boundary crossing
RG1 (4) the foul sewer is not flushed with rainwater,
I
therefore great care must be taken to ascertain
l Sa
that a self-cleaning velocity is kept to throughout.
combined sewer flow __
key Part-separate System (figure 5.31)
RWG rainwater gully
WG waste gully
SP soil pipe This method is a compromise between the combined
scale 1:200
YG yard gully system and the separate system. One sewer deals with
RG road gully street gullies and as much roof water as possible, the
RWS rainwater shoe
S soakaway other takes foul and waste water and a small amount
Sa Saddle of rainwater, preferably, for example, via a gully at
pipes carrying
rainwater only the top of the system, which will flush the drain as it
flows during wet weather.
Figure 5.29 The combined system
/',
<S )
~" RWG
" v
RWS ./ "" ,
I
I
\ !WG
\
\
sP_ _
)\]
WG
SP........... \\ \
1J:
I
,
I
I
RW~
I
I YG .... I
RWS ' I I
"" , I
YGo----------
tt1 I
I
'~
I
r I
I I
I
I
boundary !
I RG' I
boundary I I
RGT
I
,
I
I
cornbined sewer! I
I Sa
soil sewer
I
I Sa I l :Sa flow'-
I ========~~~====~==========
I Sal flow- top water sewer
========~==================
top water sewer
scale 1:200. scale 1:200
Figure 5.30 The separate system (key as for figure Figure 5.31 The part-separate system (key as for
5.29) figure 5.29)
Drainage 47
Straight Pipes
o~~
SP to top IC 2.6
Lower IC to main 9.0
RWS to lower IC 4.4
" I I RWG
YG to lower IC 2.8 YG<>--_
\
39.0 m
Fittings
I
I
I
I
I
I
VENTILATION OF DRAINS ,
I
I soil sewer
A free circulation of air must be provided through the I top water sewer
pipes forming a domestic drainage system. This is =. "= '":."'=.------------""""=--=-"'=.."'=-~-=.~
accomplished in one of two ways, depending on the Figure 5.33 The separate system (key as for figure
requirements of the local authority. 5.32)
Drainage 49
D
Ventilating with an Interceptor Trap (figure 5.36)
rest bend or
'duck-foot' bend
- saddle
main
sewer
Figure 5.35
boundary
wall
air enters
fresh-air inlet ___
rest
bend (some authorities
prefer two + 450 bends)
- - - interceptor sewer gases
trap
Figure 5.36
50 Brickwork 3 and Associated Studies
INSPECTION CHAMBERS (3) The internal size varies with the depth and the
number of branch drains entering: 600 x 450 mm
The purpose of an inspection chamber is to provide is the minimum, increasing as the depth in-
access for inspection and cleansing. Inspection cham- creases.
bers are constructed from the following materials (4) Where bricks are used, English bond (figure
5.37b) is preferred to water bond (figure 5.37c).
(1) class B engineering bricks
Note In water bond, the bed joints are stagger-
(2) precast concrete sections surrounded in concrete
ed by either forming a half-course rebate around
100-150 mm thick
the outside of the concrete foundation, or start-
(3) in-situ concrete
ing the outer half-brick walling with either a
(4) for surface-water drains, good quality bricks,
course of snapped headers or a course of split
rendered externally where deemed necessary
bricks.
(5) glass-reinforced plastic.
(5) Brick chambers are normally built half a brick
thick where the depth to invert is less than 900
The following notes are relevant to the construction
of inspection chambers. mm (figure 5.370), after which one brick thick
is the minimum.
(1 ) The concrete base must be at least 100 mm (6) All pipes in inspection chambers are to be in
thick, the thickness increasing with depth. channels discharging in the direction of the
(2) The base can be of the same length and breadth flow.
as the overall plan area of the chamber, that is, (7) A brick-on-edge arch should be formed in the
no spread is required. brickwork over pipes more than 150 mm in
scale 1:20
#'
//
// W
//
: ...
I ·.,·" •....;
'" .
'
4~'
c .
I
:, ..:
1// ~~.1:'I.r-------+r.
. ....-~
I-
Jo6"It---JL.....;r-L-r-I----lH"'"
l- '.;.. H.r-----~; .:
.: . ....
1# W
V ,&
//
I-
f-
........
l-
I- ~~ "
.. r - - - - - - M , •
• }t:'
...
.
W
:?; : . ~
~
V/
//
~l
#
,-
.~. ~
.
:
.. ......
"4~ "1 -1:~:' ~
IT:; ~,.•.:}{ Jl~1?i<f ~ I--- ~~\? ,l{ JI/.o.-!~:~
i/;, .,. ;:;.i e.s: )'& ~. . ~ .,••
. .,
I! , I
- -
,,
l- f--
Ip
I ,
I
sectional plan sectional plan sectional plan sectional plan
(s) % brick thick (b) 1 brick thick in (c) 1 brick thick in (d) concrete sections
in stretcher bond English bond water bond surrounded in concrete
75 x 75 mm ---.f--+I
puncheons
page
..
'-'
" ,I
" I
"
footprop
Figure 5.40 Tucking boards
Drainage 53
(
Figure 5.45 Inflated air-bag stopper
Figure 5.42 Detail of foot of traveller Note Where this test is being carried out in water-
logged trenches, colouring powder should be placed
in the testing water, and any leaks will then be
last inspection chamber on site and a saddle on the quickly noticed.
main sewer should be tested via a testing junction
installed close to the main sewer, which is sealed off The Air Test (figures 5.46 and 5.47)
before backfilling takes place.
Where water is not available or its disposal is incon-
The Water Test (figure 5.43) venient, this test is considered to be a good alternative.
The test is carried out by firmly plugging each end
This is the most widely used test and is generally of the pipeline and pumping in air until a pressure of
considered to be the most reliable. Where rigid joints 100 mm is indicated on the manometer. The pressure
have been used it is important that at least 24 hours should not fall from 100 mm to below 75 mm during
should elapse before testing, to allow the mortar to a period of 5 minutes. If the pressure does fall below
gain sufficient strength, but flexibly jointed pipes can this a leak is indicated, and if this cannot be located,
be tested immediately. a smoke bomb can be used.
The test is applied by plugging the lower end of
the pipeline with either an expanding rubber ring plug The Smoke Test
or an air bag stopper (figures 5.44 and 5.45), and fill-
ing the pipeline with water to provide a head of 1.5 m A smoke bomb or smoke-generating machine is used
above the higher end. It is important not to subject to supply smoke at the lower end of the system. The
the lower end to more than a 6 m head to avoid over- top of the vent pipe is plugged and the seals in the
stressing the joints. The section of drain should be gullies are removed until smoke is seen emerging. The
drain plug
1/-
L ----'--'
Figure 5.43
54 Brickwork 3 and Associated Studies
U-gauge
t t )' l'
* *'
drain
plug
plug
Figure 5.46
O~-b-/--.L-Z_/~L_/_ _:~6
Figure 5.48
eye
Method 7
~
and jointed (figure 5.50d). { I~ (e)
Method 2
~
(1) Expose both the pi pe that is to be replaced with [] t (d)
(a)
(b)
Ie)
~r---O~I_[]J---I-O~~(] (d)
Figure 5.50
56 Brickwork 3 and Associated Studies
·f :.. ..
Cross multiplying
.:.'. r:
<.:: 30 x fall = 1 x 18
dividing both sides by 30
30 x fall = 1 x 18
Figure 5.53 30 30
Cancelling
cutting mark 3
fall = - = 0.6 m
5
Thus the fall from inspection chamber B to the
saddle is 0.6 m.
fall = actual
. d
distance = ~ =
0.6m
CALCULATION OF INVERT LEVELS gIven istance 30
Sioce
Before any pipes are laid it is necessary to know the
invert level of the drain or sewer to which the con- staff reading at B = 1.6 m
Drainage 57
instrument
T:--l~:
staff staff position staff
m ~--~(H[1-.6oo-m-
_J ~
B
A sectional elevation
Figure 5.55
dwelling
I
I
I
I
I
118.000m
I
I
I
12.000m 1B.OOO m
• ~4
--fi- -fi-
I.C.A. I.C.B.
30.000 m
t - - - - - - - - - - - - - - - - - - - - - .......I
plan
Figure 5.56
depth of invert at saddle = 1.6 + 0.6 (depth at B Thus the fall is 1 in 36, which is quite satisfactory
+ fall) (0.5 in 18 m equals 1 in 36). Sight rails can now
=2.2 m be set up at each end (figure 5.58), and the ground
is excavated. Boning rods are used to obtain the
And since required slope and the pipes are laid.
ground level staff reading at the saddle= 0.9
depth of invert below ground level = 2.2 - 0.9 Note If, when the depth of the inspection
= 1.3 m chambers is checked in the first place, it is
That is obvious that there will be an adequate fall, the
above procedures may be unnecessary.
x = 1.3 m
Having found this it is necessary to relate it to While the foregoing explanations on invert levels
the invert level at the topmost inspection chamber were necessary, it is probable that all that the craft
of the proposed drain to ascertain that the fall student will be required to do is to calculate the total
will be suitable. Assume that the invert level is fall between inspection chambers, given the overall
0.6 m below ground level (see figure 5.57). An length and required fall.
instrument is set up between these points and
readings are taken of 1.600 and 1.4 as shown.
Since the invert level at X is 0.6 below ground Example 5.4
level
A drain is to be laid a distance of 45 m in level ground
fall from invert level at X to invert Y and the fall is to be at 1 in 60. Calculate the total fall
= 0.5 m (2.7 - 2.2) (figure 5.59).
58 Brickwork 3 and Associated Studies
-----
dwelling
r.;;= - staff
position
1.600 m
Oj~m_ __ _ _
Lll.:.-
_
instrument
position
main,.
-l-.--
/
1.4oom
staff position
1.3OOm
v _ -C>
... 18.000m ......
r ------+t·1
sectional elevation
Figure 5.57
sight
rail line of traveller
high sight
r-+--
sight boning rod or high
rail
-;--- --f
/ traveller ~
-- -
.
, '\:-::-.. . -~~-,~~-~-::-:~~---.JL_,.._- ..-...-:~~-~-~~_~~L:-:-:-d •
to be excavated correct level to be excavated
1.000m 18.000
'-1 ..
1.000m
section through trench
section at t
Figure 5.58
ground level
. at 1_
in 60 _ - - -
-- ---
line of draIn _ -
45 m
~l
Figure 5.59
= 750 mm Since
Possibly the invert level may have to be found given invert level at top end = 2.50
the level at one end, the overall distance and the fall. then
invert level at bottom = 2.50 - 1.25
Example 5.5 = 1.25 A.D. (above datum)
The invert level at the top end of a length of drain Use of a Tapered Straightedge
50 m long is 2.50 above datum and the fall has to be
1 in 40. Find the invert level of the bottom inspection Another method of obtaining the correct fall is to use
chamber (figure 5.60). a tapered straightedge in conjunction with a spirit
Drainage 59
ground level
------li-ne-O-f-d-ra-in-a-t-,-in-4Q---_----J=AoO.
---------- -
I- 50m
Figure 5.60
actual distance
fall = - - - - - Therefore, the straightedge should taper by 100 mm,
given distance
say from 150 to 50 mm, in 4 m, and a spirit level
= ~ (4 m straightedge) should be placed on top centre to check the fall
40 (1 in 40) (figure 5.61).
spirit level
tapered straightedge ( 50 mm
_)+-/ IL...:.'--_=~_= _=;0-1. ----,1
150mmIf
c:::j~.==:0 8===JF-
~--
~== :J==j"?n
all collars touching underside
of straightedge
Figure 5.61
6
SCAFFOLDING
Longitudinal braces are lengths of tube fastened at or Guard rails are lengths of tube which must be provided
as near to 45° as possible on the outside of standards where men are liable to fall more than 2 m. They must
to provide stability and eliminate sideways move- be secured on the inside of the standards at a height
ment. They are required every 30 m and must extend of between 0.9 m and 1.125 m and kept permanently
to the full height of the scaffold. It is preferable to in position except for access and loading.
fasten them to putlogs or transoms with double
couplers, or alternatively to standards with swivel
couplers.
Cross Braces
Puncheon
spurs
J
X v;:. ~
puncheon
V- standard - -
opening ground level
.-
Figure 6.4
max. 750 mm
double
couplers couplers
gin wheel
Figure 6.6 Drop-forged double coupler
rope
Universal Coupler (figure 6.7)
Butting Pieces
Scaffold Fittings
putlog holes where required, insert the putlog ends Base Plate (figure 6.14)
secured with hardwood wedges and fit transoms to
the putlog ends as the scaffold is erected. This is a 150 x 150 mm steel plate which is used to
provide a flat, bearing surface for load distribution
Sleeve Coupler (figure 6.12) from standards. It has a central spigot 50 mm high,
This is used to secure a toeboard against a standard. Tiulse are used for mobile scaffold towers and have
foolproof wheel brakes, which cannot be accidentally
released.
Gin Wheel (figure 6.19)
Spanners and Podgers (figure 6.21)
The figure shows a 250 mm steel wheel, with which a
19 mm-diameter rope is used. Its safe working load is These are used for tightening and releasing the nuts
250 kg. on couplers.
66 Brickwork 3 and Associated Studies
Boards
Guardrail --';::::::::::::__.1
Toe board
Putlogs
tYingin~~~~~~~~~~~
Horizontal
Ledger
Longitudinal
brace
Base
plates
~
-l:Jr-
th rougt
~ ti e
/'
-
1.5 m;
j -
~
I
V
:J
1.5m
I
~
putlogs brace \ putlog
double
coupler 1
----,~:i~==~QIl=1 ==!=:::::j ~==::;l~ ~
double
coupler
V
base 2.0m
plate
I
sole
V
plate
c ~ - I~'-
1.8-2.5 m 1.0 m,l
front elevation section
support on the wall on the inside and the putlogs rest materials are stacked on the platform as close to the
on ledgers which are supported by a single row of standard as possible the stress in the ledgers will be
standards on the outside. reduced to a minimum.
To erect a putlog scaffold a standard should be set Fix intermediate putlogs as required with due
up at each end or corner first and intermediate ones regard to the thickness of the planks, and plumb and
lined up from these. The space from the wall should level the scaffolding as it is erected, tightening fittings
allow for the required number of boards and a space at as work proceeds. When the length of the standards
the wall face for a plumb level and for mortar drop- exceeds 6.5 m joint pins or sleeve couplers are used to
pings. The ledgers should be fixed to the standards connect the tubes together. As already mentioned, it is
with double couplers at approximately the height of important not to have all the joints occurring at the
the first lift, which is usually 2 m to allow for walking same height, but to stagger them by using tubes of
below. Subsequent lifts should be no more than 1.5 m different lengths. With a putlog scaffold only one lift
in height. It must be remembered that coupling ledgers must be in use at a time.
end to end with joint pins will provide little strength
in tension and that sleeve couplers are, therefore, to Independent Scaffold (figures 6.24 and 6.25)
be preferred for this purpose. As close to the standard
as possible rest the flat end of a putlog on top of the The independent scaffold is normally used on existing
first lift of brickwork, or wedge it into a raked-out buildings or on structures where putlogs would be in-
bed joint, fixing the other end of the putlog to the convenient. It is so called because it is self-supporting
ledger with a putlog coupler. If bricks or other and carries all the superimposed loads without assist-
Scaffolding 69
guard rail----+I-----t+--+I----I~_£:_.....M
l
transoms~~~
tube wedged in
window opening
for tying in
(alternative method -+~r----tl~"I
to that shown in
figure 6.21)
ledgers -,--~-t+-~~~ ..
transverse ~,'
or cross
brace
10ngitudinall----tt-~o:___++__t_-..../
brace
sole
plates--------''''''tI~~~ sleeve
base
plates coupler
ance from the structure. It consists basically of two (5) Longitudinal and cross braces can now be fixed
rows of standards, two rows of ledgers, transoms, and the base frame removed.
longitudinal braces and cross braces.
When erecting this scaffold for bricklayers, set the Note Both types of scaffold must be securely tied to
inner row of standards about 330 mm from the wall the building at least every 4 m vertically and 6 m hori-
so that the inside scaffold board can be placed on the zontally. This is usually carried out in one of two ways
transoms, projecting beyond the inner standards. Lifts
(1) with transoms passing through window or other
are usually approximately 2 m. It is possible for one
openings, connected to tubes fastened with
man to set up a simple independent scaffold using the
double couplers at right-angles to these inside the
'mattress' method of erection as follows.
structure and close up against the wall (figure
6.22); or
(1) Construct a temporary base frame, the length and
(2) with short lengths of tube wedged in window
width of the required scaffold, and pack up level
openings with reveal pins; not more than 50 per
on bricks, blocks, etc. about 600 mm above the
cent of the ties may be of this type (figure 6.24).
ground.
(2) Fix the four end standards to this frame with Where openings are non-existent and the height of the
double couplers. scaffold is limited, the scaffold should be strutted
(3) Fasten ledgers to these standards and transoms from the ground with raking tubes inclined towards
to the ledgers where required, plumbing and level- the building (figure 6.25).
ling as work proceeds. A reliable method of securing a scaffold to a build-
(4) Intermediate standards are now positioned, taking ing where there are no openings for through ties or
any sag out of the ledgers as necessary. reveal ties is to use a ringbolt. The Hilti ringbolt, for
70 Brickwork 3 and Associated Studies
Figure 6.27
standardS~
[
tranSllerse
or cross
brace
through
tie
longitudinal -
Figure 6.28
brace
Trestle Scaffolds
It consists basically of standards, ledgers, transoms, necessary for rigidity. Figure 6.31 shows the first
diagonal bracing and plan bracing. Some ofthe require- lift of a tubular tower scaffold.
ments for independent tower scaffolds are as follows. (6) Where the height of the tower is more than three-
and-a-half times the shortest side it must be
(1) Standards should be on base plates with sole adequately tied.
plates where required, and should be no more
than 2.5 m apart. Mobile Towers (figure 6.32)
(2) Ledgers must be fixed to standards with double
couplers, the normal height of each lift being Relevant details are similar to those for independent
2 m, which provides headroom for working on tower scaffolds, except for the base plates, which are
intermediate platforms where required. replaced by lockable castors. Other requirements are
(4) Transoms should be fixed to standards where as follows.
possible with double couplers, intermediate tran-
soms being fixed to ledgers with putlog couplers. (1) The maximum height of internal towers is three-
(5) Diagonal bracing should be fixed on all sides with and-a-half times the shortest base dimension,
plan bracing at the base and other levels where while that for external towers is three times these
dimensions.
(2) When the scaffold has to be moved, force should
Figure 6.37 First lift of an independent tower scaffold
Scaffolding 73
•
E
'"0 co
,...E
~
I
1.22m
-I
end frame
.
1.22 m
I- ~I
end frame
1.22m
-I
open end frame
ledger
distance between the top of one thread and the top has to be rotated through a large distance to raise the
of the adjacent thread is known as the pitch of the load fractionally. For example, if the pitch of the
screw. The length of the lever may be as long as screw is 5 mm and the length of the lever is 900 mm,
900 mm in some cases and it should be clear from the end of the lever moves through a distance of more
figure 6.38 that one complete revolution of the lever than 5Y2 m to raise the load 5 mm; and with an Acrow
will raise the swivel head a distance equal to the pitch. prop, although the lever is only 216 mm long, it turns
With the screw jack little strength is required to through a distance of nearly 1.6 m to raise the load
lift heavy loads. An Acrow prop, for example, works 6 mm (dimensions converted).
on this principle, and although the lever is only about
225 mm long the lifting and supporting capacity is Simple Pulleys
well known in the construction industry.
As is the usual case with lifting equipment, how- With a pulley it is possible for a man to raise an object
ever, we are not getting something for nothing since several times his own mass, on to a scaffold with the
the effort is applied at the end of the lever, and this minimum of effort. The act of bending down and lift-
Scaffolding 75
alternative
handhold
1 m above
platform
4 units
(a)
Figure 6.34 Isometric drawing of a putlog scaffold showing two methods of using ladders
ing a heavy object is difficult and may be dangerous, least five times round the hook and arranged so that
and it is much better to raise the object by heaving the hook hangs 75 or 100 mm below the tube.
downwards on a rope. The simplest form of pulley is With an independent scaffold the support tube
the gin wheel, which consists of a single wheel over must be connected to both standards (figure 6.5), and
which the rope is passed (figure 6.390). The hook with a putlog scaffold, the support tube should be
must be firmly secured to an extended putlog or connected to a standard and braced back to the level
transom with a figure-of-eight wire lashing turned at of mature brickwork. Support tubes to gin wheels
76 Brickwork 3 and Associated Studies
swivel head
~ows
\
reaction
= 500
600
= 0.833
Figure 6.37 Use of folding wedges On the other hand the mass may be given as a load in
newtons in which case multiplication by lOis un·
should be placed as near to a positive tie as possible. necessary.
This load is then attached to one end of the rope and
the effort is applied at the other. Example 6.2
With a gin wheel a man cannot raise an object as
heavy as himself and therefore the main reason for If a load of 800 N is raised by a force of 900 N,
using this lifting appliance is that it is easier and safer calculate the mechanical advantage
to raise a heavy object by pulling downwards on a
rope than it is to pull or carry it up on to a scaffold, MA = force
provided that there is someone at the top to unload. effort
As already explained, to raise a mass of 50 kg, _ 800
which creates a force of 500 N (50 x 10), the operative
900
must be heavier than this; how much heavier depends
to a large extent on the condition of the gin wheel = 0.88
Scaffolding 77
effort
load
load load
load load
(al gin wheel (b I use of two wheels (e) 2: 1 pulley (d) 2:2 pulley (el 3:2 pulley
Figure 6.39 Pulleys (the wheels are shown with different diameters so as not to obscure the ropes)
The velocity ratio (V R) of a pulley is defined as the (50 kg x 10) would be required. The VR would be 2
downward distance moved by the rope due to the ef- since pulling 300 mm downwards would only raise
fort, compared with the upward movement of the the load 150 mm (also, two wheels are being used). In
load. It will be obvious that with a gin wheel the figure 6.39c there are three ropes supporting the load
amounts of upward and downward movement are and, therefore, if the load to be raised had a mass of
equal and, therefore, the VR of a gin wheel is unity. 150 kg the force in each rope would be 500 N (50 kg
x 10) and thus an effort of 500 N would balance a
Note The VR of a simple pulley can also be found load of 150 kg, which creates a force of 1500 N
by counting the number of wheels used in the system. (150 kg x 10). To raise the mass a little extra effort
The efficiency of a pulley is calculated by dividing will be required.
the mechanical advantage by the velocity ratio and
multiplying the result by 100. In the case of example
6.1 Example 6.3
efficiency = MA x 100% Assume that the mass to be raised is 180 kg and the
VR
force required to raise this is 800 N (80 kg x 10).
= 0.833 x 100 Calculate MA, VR and efficiency.
1 mass x 10
MA = .:.-:.:...:..::..-:...---
= 83.3% effort
180 xlO
Using More Wheels =
800
When a hanging pulley attached to a load is supported = 1800
by two ropes (figure 6.39b) the force in each rope is
800
equal to half the force exerted by the mass. There-
fore, to balance a mass of 100 kg an effort of 500 N = 2.25
78 Brickwork 3 and Associated Studies
(This means that a man can raise 21,4 times his own
mass when using this pulley.)
VR = 3 (number of wheels in system)
MA
efficiency = - x 100%
VR
= 2.25 x 100%
3
= 225
3
= 75%
Consider figures 6.39d and e. While these are a little
more complicated, still larger mechanical advantages
can be gained with their use. In figure 6.3ge, for
example, a load having a mass of 250 kg can be
balanced by a force of 500 N (50 kg x 10). This
particular pulley has a velocity ratio of 5 (number of
wheels used in the system).
Mobile Hoists
Fixed Hoists
to the fulcrum and the longer the lever, the less effort mined by multiplying the size of the force by its
will be required to raise the object. The object is distance from the point.
raised because the clockwise moment about the ful- Forces are given in newtons (N) or kilo newtons
crum is greater than the anticlockwise moment. (kN) and distances in millimetres or metres.
Figure 6.44 shows the apparatus necessary for a Figures 6.45 and 6.46 show two identical canti-
simple experiment to study the first order of levers. levered timber beams, each supporting identical
forces of 2 kN. It is obvious that if either beam were
to fail under load, it would be the one in figure 6.46,
since the force is acting at a greater distance from the
fulcrum beam support. The moment produced in figure 6.45 is
force x distance = 2 kN x 1 m
weight
=2 kN m
The moment produced in figure 1.42 is
force x distance = 2 kN x 5 m
t:::=::::::J~--stand
= 10 kN m
Figure 6.44 Figure 6.47 shows a heavy plank supported by a
trestle. A bag of cement is placed at the position
shown. Would the plank remain in its position or
Experiment would the force produced by the bag of cement force
the right-hand side down?
Requirements for the experiment are a timber beam, This would be difficult to ascertain from the figure
measuring 38 x 25 mm, 1 m in length, with holes every shown, but if the cement were moved to the extremity
100 mm; one winged nut and bolt, a stand and various of the plank, that is, on the right-hand side, it would
weights. almost cert.ainly over-balance. The weight of the
cement has not changed but a change has occurred in
Method Set up the apparatus as shown in figure 1.40, its distance from the fulcrum. The moments produced
fixing the fulcrum in a hole between positions 3 and by the bag of cement before and after moving are
8 inclusive. Place a small weight on the short length
of the beam to balance the self weight of the beam.
position 1
Start by hanging a 2 kg weight (creating a force of
20 N, assuming gravity is 10 m/s 2 ) at a distance of moment = force x distance
600 mm to the right of the fulcrum, and a 4 kg weight
= 500 N x 1 m
(force 40 N), 300 mm to the left of the fulcrum. The
beam will be seen to balance. This is because the = 500 N m
clockwise moment (CM) is equal to the anticlockwise
moment (ACM). That is position 2
moment = force x distance
20 N x 600 mm = 1200 N mm (CM)
and 40 N x 300 mm = 1200 N mm (ACM) = 500 N x 2 m
= 1000 N m
Now place a 3 kg weight (30 N) at 500 mm from to
the right of the fulcrum. What force is needed at (assumingg = 10 m/s 2 )
300 mm to the left for the beam '0 be in equilibrium?
Figure 6.48 represents a beam resting on a fulcrum
30 N x 500 mm = 1500 N mm (CM)
and carrying different forces at different positions
and x N x 300 mm = 1500 N mm (ACM) from the fulcrum. Ignoring the self weight of the
beam, will this arrangement produce a balance or will
The force required is 50 N (5 kg). one end be lowered to the ground?
A table can now be drawn up as shown in table 6.1 This can be determined by experiment or calcula-
and different forces applied at varying positions on tion. The .;alculation method would require the
the beam. calculation of moments produced on each side of the
Thus it can be stated that a moment is the turning fulcrum. Figures 6.49 and 6.50 show diagrams of the
effect of a force about a point and its value is deter- anti clockwise and clockwise moments respectively
Scaffolding 81
Table 6.1
Mass (kg) Force (N) Distance Moment Mass (kg) Force (N) Distance Moment
(mass xg) from (N/mm) (mass xg) from (N/mm)
fulcrum fulcrum
(mm) (mm)
2 20 600 12000 4 40 300 12000
3 30 500 15000 5 50 300 15000
500N 400N
! !
I :a
..1
o
I 2m 3m
't .:
ACM CM
Figure 6.49 Figure 6.50
Figure 6.47
500N 400N
J l Figure 6.51
0
,I
A :
I,
2m ,I .. 3m ..
I
Therefore force
l------~~rl~
effort x 4.7 = 4 x 0.3
= 1.2
effort
Therefore
Figure 6.53
& 1.2 (divide both sides by the
ef lort= -
4.7 coefficient of 'effort')
force
= 0.26 kN
Thus an effort of 0.26 kN (260 N) will balance the
load and any addition to this will cause the load to
rise.
f~~~-J~
effort ~fUlcrum
Example 6.5 Figure 6.54
Calculate the effort required to raise the load shown Example 6.6
in figure 6.52
CM = ACM Calculate the effort required to raise the load shown
in figure 6.55.
Therefore
1.5 kN
effort x 1.4= 7 x 0.6
Therefore 1-' _o.800_m_"Q
effort x 1.4 = 4.2
effort
Therefore
Figure 6.55
& 4.2
ef lort = -
1.4 Note Moments are always calculated from the
= 3 kN fulcrum.
Therefore any effort over 3 kN will cause the load to Clockwise moments = anti clockwise moments
rise. Therefore
effort effort x 1.2 = 1.5 x 0.4
load
7 kN -------ri = 0.6
l----~
Therefore
, 1
!
:
0.6
; 0.600
...
m;,'--oIl 1.400 m .: e ffort = -
1.2
~ ~
(
.,;;;'~.~
= 62.5 N
=========:SS --::.c.:-. It will be noted that the effort is in excess of the load.
fulcrum effort 50N
6~--1-+
Figure 6.57
The construction industry provides its craftsmen with resisting movement better than the single unit or one-
a greater variety of work than any other industry. In piece fireback, and obviously the four-section fireback
the construction of new buildings, which is classified is more capable than one comprising two sections.
as new work, employment is provided for approxi- When the craftsman is required to renew an exist-
mately 25-35 per cent of the labour force. In main- ing defective fireback, it is important to inspect and
tenance, repair and alteration, work is constantly determine the area of damage and the cause of the
provided for the majority of building trade workers. trouble.
In the work of maintenance and repair we find that Figure 7.1a shows areas of disintegration in the
situations, buildings and materials are never identical, fireback, with spalling, laminating and sometimes frac-
and techniques that are suitable for a particular tures originating from the worn areas. Where only
situation may not be universally applicable because so slight cracking and a minimum amount of spalling is
many other factors have to be considered. The brick- found, repair can be effected by pointing with patent
layer craftsman should, therefore, be equipped with fire-cement, otherwise complete reinstatement is
the skills that will enable him to cope with the many required.
different problems and varying situations in which he Figure 7.1b shows a very large crack occurring at
may become involved. the centre of the fireback, running from top to bot-
tom. This is caused by lateral pressure on the fireback,
resulting from the absence of a movement joint around
REPLACING DEFECTIVE FIREBACKS the back of the fireback, with consequent pressure
from the infill material.
All types of fireback may become defective because Figure 7.1 c shows a large horizontal crack occurring
of the following causes about half way up the fireback. This is caused by un-
even pressure on the fireback, and is due to movement
(1) abrasion and resistance to heat, which is termed
of the infill material and to the absence of a move-
normal wear and tear
ment joint between the fireback and the tiled surround.
(2) movement of the surrounding infill material, the
Figure 7.1d shows a deep vertical centre fracture
structural hearth, tiled hearth and tiled surround:
and also fractures in the side cheeks. The causes of
if any movement caused is not accommodated it
this defect are the total absence of any movement
will result in damage to the fireback.
joints, badly placed infill material and sometimes the
It is recognised that sectional firebacks are capable of wrong type of infill material.
rr
1\ I /
/ " ,,/
'" (e) (d)
Removing the Fireback man to use a lightweight percussion drill with a chisel
end, or the lump hammer and a 25 mm-diameter cold-
Where the fireback consists of a one-piece unit, steel chisel at least 450 mm long.
removal can easily be effected with the lump hammer
and an 18 mm-diameter cold-steel chisel at least Fixing the New Fireback
250-300 mm long. The cutting-out operation should
be started around the central fracture and the side A four- or six-piece fireback is to be preferred in this
cheeks can be taken out after the centre of the back situation. While it may be just possible to use a one·
has been removed. or two-piece, this is difficult, although not impossible,
It should be noted that before any of the above if the fireplace recess has been constructed to the
operations are begun, it is essential to provide com- minimum dimensions (Volume 2, chapter 11, figure
plete protection for the tiled surround and hearth. 11.6).
This can be done with sacking over the hearth and Assuming the four-piece has been selected, before
drapes over the tiled surround, which will prevent any it is placed in position expansion joints must be
chipping or spalling of the tiles should they be struck formed on either side at the back of the new tiled
by particles from the fireback. surround where the new fireback abuts. These joints
consist of lengths of fibre glass rope which have been
Removing the Infill Material cut to the height of the new fireback and soaked in
waterglass.
Removing the infill material may require the crafts- The two firecheeks and base back section (figure
7.2c) are stood in position with fibre glass string
between each joint, and a further expansion joint is
formed by wrapping corrugated cardboard around the
back. This material will later disintegrate with the
heat, leaving an open joint between the infill and the
fireback which will allow movement to take place
without causing stresses to be set up and eventual
cracking to occur.
The infill should consist of broken brick and lime
two piece four piece mortar, or a weak concrete mix such as 1:4:10
(figure 7.3). If bricks and mortar are used, they
should be built up as high as possible all round before
bedding the top back 3ection - again on fibre glass
~D~
good to the gatherings.
If the fireplace recess is higher than usual, as in
older properties, a hole will need to be knocked
(e) (d) through above the tiled surround to complete the
four piece six piece bricking up. This must be made good later and re-
plastered (figure 7.4).
Figure 7.2 Firebacks complying with BS 1251: Part 1
--LL
I I
~1 Inspection
A suitable type of ladder should be erected and The following faults and failures are recognised as
placed in position to provide easy access to the roof. being common and are often found on existing houses
Because materials may be taken on and off the roof, and old buildings
pole-sided
ladder
(1) leaning chimney pots cautions should also be taken to protect any work, or
(2) loose capping brickwork people below roof level.
(3) cracked and loose flaunching
(4) fractured stacks, showing visible cracks Equipment
(5) spalling and lamination of the stack bricks
(6) deterioration of the mortar joints Where the chimney is of considerable height, scaffold-
(7) leaning chimney stacks ing must be erected around the stack. Timber is
(8) ineffective d.p.c. normally used for roof work, although other methods
The first seven failures are often caused by sulphate can be used to provide the necessary working plat-
attack and may be accelerated by the ineffectiveness form (figures 7.6-7.8).
of the chimney capping where it has insufficient pro-
jection or is badly weathered and formed with weak Taking Down for the Stack
materials. Fault 8 can be considered to be a contribu-
ting factor to some of the other failures. This should be done with considerable care, the dis-
mantling starting with the chimney pot and f1aunch-
Conclusion of the Inspection ing, then the stack itself. All materials should be
removed and taken down to ground level, then placed
Where the condition of the stack is poor, and flue in a position where they will not impede any building
liners are obviously not present, the entire stack operations and also where they can easily be removed
should be taken down to three to four courses below from site.
roof level and rebuilt with suitable new material, with
flue liners inserted during construction. Rebuilding the Stack
Protection Materials
Before any work is carried out on the chimney stack, The type of bricks and mortar should be determined
the fireplaces below should be inspected and sacking with considerable care, taking into account the pre-
should be inserted at the fireplace throat to prevent vious failures, the necessity to combat sulphate attack,
debris entering the room. All roof work should be prevent weather penetration and blend in with the
covered and protected in the area of the stack; pre- appearance of the building. Obviously, flue liners
-- ---
roof cripples
. pole-sided ladder
secured to wall hook
Figure 7.7 Working platform around stack formed with roof cripples (for inspecting only)
brace
must be inserted at the position where rebuilding is (3) Mortar joints should be correctly filled and
begun. should not exceed 6 mm in thickness.
(4) The amount of fall provided for the top surface
Procedure of the sill should be 6 mm per 100 mm of sill
surface.
At the required position below roof level, rebuilding (5) The projection of the sill beyond the brickwork
is begun. When the work reaches 150 mm above the face should be at least 50 mm.
lowest point of intersection between roof and stack, a
tray d.p.c. should be inserted; the mortar joints
around the base of the stack above roof level should Inspection of Sill
be raked out to accommodate the flashings. Flue liners
must be inserted up to chimney pot level and these The sill should be inspected and examined to deter-
must be bedded and jointed in the same mortar that mine the cause of the deterioration.
is being used for the brickwork of the stack. The
surrounding space within the stack should be filled Removal of Sill
with solid material.
At capping level, adequate protection should be Removing a badly defective sill should not cause any
provided, oversailing courses should be formed or a problems for the craftsman and it can be effected
precast concrete slab used to form the entire capping with the normal bricklayer's tools.
as one unit. The chimney pot can then be inserted Cutting out should start at each end, taking out
and fixed. The terminal should be selected with the the first two bricks from each end; the third brick
following in mind: from the end on each side should be left to support
(1) the pot should match the liners used - that is, the sill, and the bricks between should then be taken
both circular or both square on plan out. Temporary packings are then inserted, and the
(2) it should complement the chimney stack and two supporting bricks are removed (figure 7.9).
building below. After this operation has been completed the area
of brickwork below the sill, termed the apron, should
After rebuilding is completed, the sacking can be then be examined and, where repointing is necessary,
removed and the flue examined for draught by light- raking out and cleaning should be carried out at this
ing a low fire. If the results are good, the scaffolding stage.
above roof level can be taken down, and the roof
completely cleaned off, with all protecting covering
removed, and the building waste taken away. Reinstatement of Sill
window frame
gauge marked
on support to sill
Before any operations are carried out on the face of Where scaffolding is required for defective brickwork
the building, it is important that a close inspection to be repointed, cleaned and reinstated, careful con-
of the walling should be carried out. sideration should be given to the type of scaffolding
that will be most effective. It is important that
Inspection of the Building Face scaffolding should be completely safe and should
comply with the Construction Regulations. The main
It is very important to determine the position of the functions of scaffolding are as follows.
walling and to recognise the amount of weathering or
atmospheric pollution that the walling is required to
(1 ) Fatigue for operatives using the scaffolding should
be reduced to a minimum.
withstand; the amount and type of deterioration of
the wall surface, the number of laminated bricks and
(2) It should be possible for all work above ground
level to be carried out in an economical manner.
the condition of the mortar joints should all be care-
fully determined and assessed. Factors that should (3) Cleaning operations should not be impeded and
the scaffolding should provide protection for the
also be considered are as follows.
work, and also for persons who are at ground
(1) Where staining of the brickwork face is evident, level.
Maintenance, Repair and Fixing Equipment 91
Protective measures should be carried out before any Oil Stains Sponge or poultice the area with white
form of work starts on the building face. They may spirit, carbon tetrachloride or trichlorethylene. Where
consist of masking out all existing mastic pointing, staining is severe, use several applications.
glass, paintwork, timber and decorative features.
Masonry and ironwork should also be protected. Efflorescence Allow weather to take its natural
course, but brush off with a fibre brush when the
efflorescence is at its maximum. After a reasonable
period wash down each week for a period of one
Cutting Out and Reinstating Defective Bricks
month and allow the walling to dry out before further
wetting is contemplated.
This operation should be begun at the top of the
building and worked down to ground level. The bricks Point Stains Apply a patent paint remover as instruc-
on each lift should be cut out and replaced before ted, or use a solution of trisodium phosphate, 1 part
work is begun on the lift or platform below. to 5 parts of water (by weight). Allow the paint to
soften and remove with a stiff fibre brush, washing
down afterwards with soapy water.
Repointing Mortar Stains When possible use a softwood scraper
and wash down with a diluted solution of hydrochloric
Before this operation is begun it is often advisable, acid, 1 part to 10 parts of water (by volume).
when large structures are involved, to point panels at
the base of the walling. These are termed sample Lichens and Mosses First brush off with a stiff fibre
panels and they are used by the architect to determine brush, then use a patent moss killer as instructed, or a
the type of mortar that will be the most suitable for solution of zinc or magnesium silicofluoride, 1 part to
the building. Whenever possible sample panels should 40 parts of water (by weight).
be at least 1.0 m 2 and labelled with
(1) the type of sand and cement used Rust or Iron Stains First wash down with a solution
(2) the cement-sand ratio of oxalic acid, 1 part to 10 parts of water (by weight).
(3) the water content If the brown staining does not respond it is probably
(4) the type and amount of colouring used. a manganese stain.
Panels should be pointed and viewed after a minimum Manganese Stains Brush down the staining with a
period of 72 hours, otherwise a complete appreciation solution of 1 part acetic acid, 1 part hydrogen per-
of the panel is not possible. oxide and 6 parts water (by volume). Apply a second
The type of pointing joint is also selected by the application only after a period of 3 days.
architect, and it is determined by
Lime Stains Treat as for mortar stains.
(1) the weather and degree of exposure
(2) the condition of the brickwork face Smoke or Soot Stains Use a fibre brush and brush
(3) the decorative requirements down gently. Apply a wash of household detergent,
(4) the need for economy in the pointing operations. and where staining is heavy use trichlorethylene as a
Obviously the sample panels are formed with the poultice.
pointing joint selected, which then allows its qualities
to be appreciated. Tor or Bitumen Stains Use a stiff fibre brush and
scrub down with an emulsifying detergent. When the
area is dry it may be necessary to apply a paraffin-
soaked sponge.
Cleaning Brickwork before Repointing All brickwork should be completely washed down
whenever any forms of acid have been applied. This
Brickwork staining is often caused by external sources may cause efflorescence but it will only be shortlived.
although it can also be due to salts in the bricks or
mortar. To remove stains on brickwork requires con- Commercial Cleaning
siderable knowledge, skill and care, otherwise the use
of wrong techniques or materials may cause perman- This is only economical where large areas of walling
ent damage to the entire face of the walling. are to be cleaned, otherwise it may be very expensive
92 Brickwork 3 and Associated Studies
Choice of Method
Block Indents
~
I I
I I
I
I I TT
---
Figure 7.14 Increasing wall lengths by the toothing
I
I
I
I I
I
L
I
method I I I I
I I
I I _:l-.L..y-
slip or butt joint
.~.:
l "---- joint
wedges--~
100
x
25 mm
32mm
100
x
ground level (::__ , t ground level
\-----'-----
25mm
l'X·C··
prop
..
(:.; :
-----\:'
.. . . .
r·::>~- ~'7 -7'~-;-..L.- __
50mm
Figure 7.24 Rag bolt with nut and ragged base fixed
Figure 7.22 Fixing a single cantilever bracket in hole and surrounded by concrete
Maintenance, Repair and Fixing Equipment 97
I
I
I
check all walls I
for alignment I I
I I
I I
I I
I I
I rag I
-~~-----------------=6-
"'~ :0 ;~~~ bolts :
---------------------j
timber templet
-f--
I I
I I
I I
I 900 I
to"~ I-~O"
\ ,
plan
diameter of the top of the bolt is formed to fit into Kango. The use of the lump hammer and cold-steel
the hole or slot at the base of the machine. chisel, although useful for drilling and cutting a single
hole, would be uneconomical where severaJ holes are
required.
Setting Out After the holes are formed, cleaning out is then
required (figure 7.26) and the sides of the concrete
It is important that considerable care is exercised at should be adequately damped. The timber templet,
the setting-out stage, before the rag bolts are fixed. which positions and supports the bolts, is then placed
Measurements should be checked, levels taken, square- according to the engineer's drawings (figure 7.27).
ness ascertained and, where there is any doubt, checks The bolts are suspended from the templet in the
should be made again. It cannot be overstressed that holes below and a concrete mix of density equal to
accuracy is of the highest importance since any error that of the existing concrete floor is then made. Where
could prevent the efficiency and functioning of the the diameter of the holes is less than 100 mm the
machinery. It is obviously very necessary to construct aggregate size for the concrete should not exceed
a timber templet, which can be used to aid the setting 12 mm but 18 mm aggregate can be used for larger
out and to assist with fixing operations (figure 7.25). holes. The water content of the concrete should be
Hole drilling should be carried out with a light- reduced to produce a minimum of laitance. The con·
weight Kango, but where the concrete is excessively crete is then placed around the bolt and compacted
thick and very dense, it is advisable to use a heavy with a 19 mm-diameter rod and the surface is finished
vacuum cleaner or
suction pump
() ()
ground level ground level
sides of hole
shou Id be cu t
straight
timber templet
off with the steel float. It is important to cure the removed and the templet gently lifted from the bolts.
concrete around the bolts and a minimum period of Threads should be checked for cleanliness and where
72 hours should be allowed. necessary covered with a suitable grease; before leav-
The removal of the timber templet should be ing, it is again advisable to carry out another check on
undertaken with considerable care. The nuts are all the bolts for level, position and dimensions.
8
PAVING
Europeans are extremely fortunate in being able to The usual method of cutting unreinforced concrete
enjoy and appreciate areas of paving, which have been slabs is with the hammer and chisel or portable electric
their heritage for many centuries. saw, but the need to cut reinforced slabs should
Paved surfaces allow the pedestrian to move with always be avoided because failure is almost certain
the minimum of fatigue, they complement and en- owing to the reinforcement.
hance buildings and decorative features, and have
stood the test of time when used for roads. It is an Stone Slabs
accepted fact that, in comparison with other forms of
construction, the merits of the paved surface are the These are usually made from sandstone or Yorkstone
least recognised. The skills of the designer and crafts- and they are produced with sawn surfaces. The sizes
man do not receive the appreciation that they deserve. of stone slabs vary, but for normal highway construc-
This is possibly because the pedestrian accepts and is tion 900 x 600 x 75 mm slabs are used. Stone paving
familiar with the paved surface. It is to be hoped that slabs are now considerably more expensive than con-
this trend is now being reversed and that people are crete slabs but they are often more resistant to abra-
becoming more aware of the aesthetic qualities and sion and possess more decorative qualities. A disad-
importance of the paved surface. vantage with stone slabs is that they easily become
Before considering the type of paved surface that stained, and constantly increasing costs tend to
is to be constructed, it is necessary to obtain the preclude their use, especially for public footpaths; as
following information renewal becomes necessary the concrete slab is usually
used as replacement.
(1) the total area of paving required
Stone slabs are usually cut with the hammer and
(2) whether the situation is external or internal
pitching chisels. Before laying and fixing any type of
(3) the type of traffic expected
paving it is necessary to determine the amount of fall
(4) the decorative requirements
or slope required to remove surface water. This is
(5) the amount of abrasive resistance required for
normally between 1 in 40 to 1 in 60, but the amount
the surface
of fall provided should not increase the physical
(6) the requirements for removal of surface water.
effort of walking. The direction of traffic is required
When the requirements have been determined, the to determine the direction of the joints in the paving
types of material can then be selected. Paved areas are (figure 8.1).
normally formed with the following materials: con-
crete slabs, stone slabs and paving bricks. Laying Concrete Slabs
99
100 Brickwork 3 and Associated Studies
wall
concrete slabs
900 x 600 mm
fall: 1 in 60
Figure 8.1 Paving slabs on mortar, sieved clinker ash and concrete sub-base
Treatment of Concrete and Stone Slabs Tools and Equipment for laying Paving Slabs
When stacking and storing concrete or stone slabs it is The hardcore base is usually positioned with normal
necessary to stack them on edge to ensure complete excavating tools - shovels, picks and hammer - but
dryness of the slabs, therefore, whenever possible, for consolidation a rammer or punner is necessary.
these paving materials should be covered with light- These are hand or mechanically operated.
weight sheeting. Slabs are usually laid with the beedle or mawl,
wall
Figure 8.2 Method of laying slabs on sieved clinker ash and consolidated hardcore
Paving 101
~hich is a large rubber-headed hammer. Paved areas the paviors are used to combat abrasive wear and tear,
are normally levelled with the aid of the Cowley level or for domestic use, either external or internal, and
and wooden pegs, although boning rods are often also where a decorative appearance is necessary to
used. Straightedges used for checking the slabs are provide the aesthetic qualities required by the archi-
often tapered to the amount of fall required (figure tect.
8.3). Brick paving is formed with bricks laid on edge or
flat; although the pressed brick is obviously the better
type of pavior, wire-cut bricks are often used laid on
BRICK PAVING edge or flat.
For industrial use engineering bricks or paviors are
This is the most attractive and decorative form of necessary. The surface of special paviors, produced to
paving. Because of the great variety of clays found in withstand very abrasive wear and acids, and also to
European countries, a considerable variation in colour provide a non-slip surface, is often chequered or im-
and texture can be obtained. The flexibility of bond- pregnated to form a dimpled pattern. This type of
ing arrangements allows the geometrical patterns to brick should be produced to meet the requirements
enhance the colours of the paving. Brick paving can of BS 3679. When cutting is required an abrasive
be used for industrial flooring, where the qualities of wheel, that is, a brick saw, should be used.
rubber-headed mawl
12 -mm bed-t===:d"==~=:d:::.="±'==1
125-mm concrete
Figure 8.4 External brick paving
d_p_c.
125-mm concrete sub-base
ground level
Figure 8.6 Membrane formed behind movement joint Laying and Forming Joints
concrete base
12-mm mortar bed
working Iines-.......
,/
/./ ,/ ./
,/
,/ ,/ ,/
./ ,/ ,/
/' ./
working platform
above paving
U - - - - l U _+-_---'L.....<~=--"-____"-~-"-_..."---"-~:_"'"--"--"'-'''--oU-M:----
U ' J _ _ ground level
not more
than
150mm
This should be carried out after the required area has Paving work should only be performed when other
been paved, but during the same day. The mix ratio craftsmen have completed their operations. It should
for the jointing mortar should be the same as for the be programmed as a finishing operation and only the
bedding mortar, but with a minimum water content, actual decorative finishing should be performed after
and the mortar should be semi-stiff. the paving work. During the entire operation of paving
Another method of jointing used for paved surfaces it is essential for the craftsman to work above the
is to use a semi-dry mix, and gently brush over the level of the paving, that is, while he is laying the bed,
surface of the paving with a fibre brush. The disadvan- placing and fixing the bricks, and also tamping and
tage of this method is that compaction of the joints jointing. With this method the craftsman is never in a
may not be complete, also staining of the surface can position where he may disturb the bedding or cause
occur. any misalignment of the paving (figure 8.8).
When designing the paving the direction of the joints After the jointing operation has been completed, the
should always be considered. When the paving is finished work should be allowed to mature. This is
required for industrial use and to withstand abrasion assisted by curing. Where it is deemed necessary the
the paving units should always be bonded and longit- floor surface can be protected with light timber bat-
udinal joints should be eliminated. The transverse tens and polythene sheeting. After a period of 24
joints should always be at right-angles to the direction hours, the surface can be damped by applying a fine
of the traffic (figure 8.5). spray of water. This treatment should be continued
for a further 72 hours and, for complete maturity,
Movement joints the surface should be closed to all traffic for another
48 hours.
These should always be inserted where the sub-base
and the paved surface abut any walling, piers, columns Brick Paving Patterns
or machinery, or when the paved area exceeds 6.0 m
in any direction. Obviously, the size of the bay will Patterns for paved areas are usually determined by
determine the amount of movement, which will also the following
be influenced by thermal activity and the movement (1) the area involved
of the paving materials themselves. (2) the surface resistance required
To accommodate movement, a joint should be (3) the decorative requirements.
formed around the perimeter between the paving and
walling by the insertion of timber battens. These are While the same bonding arrangements are obtained
withdrawn before the curing stage and a movement with both bricks on edge and bricks laid flat, the
joint is inserted. The materials used to accommodate decorative appearance in each case may be quite
movement in paving are butyl rubber, polyurethane different. The brick on edge contains more joints and
and silicone rubbers. Where necessary the surface of yet possibly provides a stronger surface area. The
the joint can be protected by forming a sealing joint patterns should always be arranged to enhance the
of polysulphide compound (figure 8.9). area involved. A Flemish or stretcher bond arrange-
f"~Oi li i iT-li1IF:I i iIi~.lI I I IlIi; m;lili _liliIil_I~I+.I~ I_-!I~ I_~ p;. .JliliO iIiIi~ ~f{P
12-mm mortar bed I...
150-mm concrete
1-...- 1--'--- , - I-
L_
~
f- 1---,-
I--- I-
- ' - - ...... '-
'----
Til
basket·weave with diagonal basket·weave single herringbone with
bricks laid on edge with bricks laid on edge bricks laid on edge
-- ._- ----
-=-~T _.I - - .
f :::1. _ -
Figure 8.11 Decorative brick paving with bricks laid flat with brick on end to form edging
------,---------------,.----- - - - - - --_._--
concrete or
stone slabs
Figure 8.13 Circular brick paving used as a decorative feature. The bricks are laid on end with
kidney stones or exposed aggregate as infil/
ment is often suitable for large areas of paving, while often the case that a different type of mortar is
narrow areas are enhanced by a diagonal or herring- required for each material used to form the paving.
bone arrangement. When setting out the bonding The following recommendations should be kept to
pattern it is essential to eliminate the amount of brick when laying compound paved areas.
cutting, therefore rectangular areas should normally
be set out from a base line, and square areas from the (1) Always set out the brick paving first.
centre. Both methods will normally ensure that cut (2) Check that the dimensions for slabs do not in-
bricks, where required, will be the same size and occur volve considerable cutting.
around the perimeter of the area. It may also be (3) The brick paving should always be laid first and
advisable to adjust the thickness of joints because on jointing should be completed before a start is
large areas this can eliminate a considerable amount made on laying the other paving materials.
of cutting (figures 8.10 and 8.11). (4) Where the paving is internal, and longitudinal
joints separate the different paving materials,
movement joints should be inserted between the
different materials.
(5) The completed paved area should be matured
COMPOUND PAVING
before traffic is allowed on the paved surface.
Paved areas formed with more than one material are When there is a requirement for brick paving to con-
termed compound paving. Designers are now using tain pockets of concrete infill, the paving should be
combinations of bricks, concrete slabs and often flints completed and pointed before the in-situ concrete
and kidney stones (figures 8.12 and 8.13). When the infill is placed. During placing of the concrete it is
craftsman is required to lay areas of compound good practice to protect the brick paving around each
paving, it is important that considerable care is exer- pocket with lightweight plastic sheeting to prevent
cised at the setting-out stage and when jointing. It is staining of the brick paving.
9
QUANTITIES OF MATERIALS
To calculate the number of bricks and the amount of Calculate the number of bricks and the amount of
mortar required for any project, the procedure is quite mortar required to complete the area of walling
straightforward. shown in figure 9.1.
(1) Calculate the area of brickwork, deducting from
this figure the area of any openings. The area is
found by multiplying the length by the height
and it is important to carry out all calculations in
metres. For example, if a window opening is given
as 600 mm by 600 mm these figures must be
multiplied as 0.6 x 0.6 m.
(2) Multiply the area by the number of bricks per
square metre, where
Example 9.2
-- r---
Calculate the number of bricks and the amount of
mortar required to complete the area of walling E
co
shown in figure 9.2. E N
N
I. 2m _I
\. 5.5 m
-I
Figure 9.3
Area of brickwork = total area - area of doors
and window
total area = length x height
5.5
= 5.5 x 2.8 2.8
1100
=15.4m 2 440
1540
Figure 9.2
Area of window = length x height
Area = length x height =2 x 1.5
= 8.6 x 2.5 8.6 = 3 m2
2.5
= 21.5 m 2 1720 Area of door = length x height
430
2150 =lx2
and Therefore
amount of mortar = 656 kg (0.656 tonnes) 5% = 184.7
= 3879
E and
M
N
amount of mortar = 3.879 tonnes
(3 tonnes, 879 kg)
Example 9.5
E
.... Calculate the number of bricks and the amount of
,...;
mortar required to complete the brickwork shown in
figure 9.5.
i
7.2 m
I· -I
Figure 9.4
{
= 53.28 m2 5040
288
5328 3.8m
= 61.56 x 60 61.56 = 16 m2
60 Number of bricks = area x number/m 2
= 3693.6 369360
= 16 x 120
= 3694 (nearest one
above) = 1920
Add 5% Add 5%
10% = 369.4 10%=192
Quantities of Materials 777
= 2016 - (4 x 0.225)
and = 2.8 + 2.2 - 0.9
amount of mortar = 2.016 tonnes =5 -0.9
(2 tonnes, 16 kg) = 4.1 m
It should be noted that the area could have been Area = length of centre line x height
found by multiplying the length of the centre line by
the height. =4.1 x 1.1 4.1
1.1
= 4.51 m2 410
Example 9.6
41
451
The inspection chamber shown in figure 9.6 is to be
built in engineering bricks class B and is one brick Number of bricks = area x number/m 2
= 4.51 x 120
= 541.2
= 542 (nearest one above)
E
Add 5%
10% = 54.2
Therefore
5% = 27.1
-
"':
Example 9.7
Exnmrfe 9.S
Fiaure 9.7
A wall 5 III long alld 2.5 IT! high jsto be built in Flemish
loon'1 (me brick thick, Calculate the number of facings
It will be notic~d by referring to e\~amplE' 9.6 that .1fVi ~~(.:4nYn~··ln5 I"f':(.luired .
this is the same length of centre line, d.nd a c!09:-r
examinatioll will revp.~1 thilt this is exactly th<;> nm<:-
illsper.tion r.:hamber, only in this case the intern;)1 :: 5 y 2.5
dimensions have been given. Thus calculations fr"1ll
this point are exactlv as shown in example 9.6. =1?.5 m~
Where walls are built one briel- thick and over with ;::: 1500
English or Flemish bond, the number of bricks reo
r'j'm,her 0f fadngs ~~ 12.5 x 80
quired per square metre, assuming :j filiI' fa,·.,. is
necessary on onE' side" only is :: 1000
English bond 90 Huml:>er "f C()mmons :: 1500 - 1000
Flemish bond 80 ::: 500
Therefore, to calculate the number of faCings and
commons required for any area of walling, the pi rj
EHOfYS AND MORTAR
cedure is as follows.
(1) C.kul;lJe the area of brickwod:. There are ten 450 )( 100 x 215 mm blocks per square
(2) Calculate the total number of bricks reqlljr·~1 metrf" which is a very convenient number for use in
(ilr'ea', 11IJI11ber IrT' '2) r:~II'Hh,j·"·qs. '\s with brickwork the procedure is: find
Quantities of Materials 113
Calculate the number of 215 x 100 x 215 mm blocks Calculate the number of 100 mm blocks required to
and the amount of mortar required to build figure 9.8 build the internal leaf of the gable shown in figure 9.9,
including 5 per cent for wastage. including 5 per cent for wastage. Calculate also the
amount of mortar.
------0------
IJT~I
E
co
Iii
Example 9. 72
Note This must be divided into two parts, as shown
A strip foundation for a boundary wall is 12.5 m by the dotted line. The volume of each part is then
long, 600 mm wide and 150 mm thick. Calculate the calculated separately and the parts are added together
volume. to obtain the total volume.
Volume = length x breadth x depth Volume A = length x breadth x depth
= 12.5 x 0.6 x 0.15 = 0.9 x 0.35 x 0.125
=7.5xO.15 = 0.315 x 0.125
=1.125m 3 = 0.039375 m 3
Quantities of Materials 115
Volume B = length x breadth x depth wrong to simply add 50 per cent, because this too
will suffer from mixing shrinkage. For example
= 0.6 x 0.5 x 0.125
1 m 3 + 50 per cent = 1 .5 m 3
= 0.3 x 0.125
BUT shrinkage is 50 per cent= 0.75 m 3
= 0.0375 m 3
which produces only 0.75 m3
Total volume =A +B
WRONG! (we needed 1 m 3 )
= 0.039375 + 0.0375
The correct method is to multiply by 1~0 as follows:
= 0.076875 m 3
1 m3 x 100 = 2 m3
50
DRY MATERIAL REQUIREMENTS Shrinkage is 50 per cent = 1 m 3
this produces 1 m3
Concrete (which is what was required)
When concrete is to be mixed on site it is sometimes Example 2
necessary to determine the amounts of cement, fine
and coarse aggregate for ordering purposes. While the How many cubic metres of dry materials are required
absolute volume method is the most accurate, because to make 6 m 3 of concrete if the mixing shrinkage is
it involves the use of specific gravities it is dealt with 25 per cent.
in the advanced volume. The following method gives Here again if we simply add 25 per cent to 6 m 3
figures slightly in excess of those required.
The density (mass per cubic metre) of well-com- this gives us 7.5 m 3
pacted concrete is approximately 2400 kg/m 3 , and but shrinkage is 25 per cent = 1.875 m 3
therefore if the mix is to be 1 :2:4 the density should
which produces = 5.625 m 3
be divided by 7 since there are seven parts (1 + 2 + 4)
to give the amount of cement required. This is doubl- WRONG! (we needed 6 m 3 )
ed for the amount of sand and multiplied by 4 for the
coarse aggregate. For example Again the correct method is to multiply by 1~~ as follows:
6m 3 x 100 =8m 3
cement = 2400 '7 7 = 342 kg (just under 7 bags) 75
and shrinkage is 25 per cent = 2 m 3
sand = 342 x 2 = 684 kg
giving 6 m3
stone = 342 x 4 = 1368 kg
(which is what was required)
Similarly, if the mix is to be 1 :3:6 and the density is
2400 kg/m 3 , the density is divided by 10 since there Therefore, given a shrinkage rate of:
are 10 parts (1 + 3 + 6) to give the amount of cement.
This is multiplied by 3 to obtain the amount of sand
and by 6 to obtain the stone. For example
(a) 10 per cent, multiply the required volume by 1:
(b) 20 per cent, multiply the required volume by l~g
cement = 2400 -;- 10 = 240 kg (just under 5 bags)
sand = 240 x 3 = 720 kg (c) 30 per cent, multiply the required volume by l~g
stone = 240 x 6 = 1440 kg (d) 35 per cent, multiply the required volume by 1~
Mixing Shrinkage etc.
content.
Example 9.15
(2) find the area of each tile in square metres Figure 9.12
(3) divide the total area to be tiled by the area of
each tile Area:: rrr 2
(4) add a percentage for wastage where an allowance
::3.142x5x5
is required.
:: 78.55 m 2
Example 9.18
Area of each slab:: length x breadth
A room measures as shown in figure 9.11. Calculate :: 0.5 x 0.5
the number of 300 x 300 mm tiles required to cover
this area. :: 0.25 m 2
Quantities of Materials 117
Example 9.20
E
a>
I- 8m
-I
Figure 9.14
= 0.9 x 0.6 = 20 m2
Figure 9.15 shows the plan of a large kitchen floor The approximate area of an irregular figure may be
which is to be tiled with 150 x 150 mm tiles. The determined by a number of methods, including the
area shown shaded is not to be tiled. Calculate the mid-ordinate rule, the squared paper method, the use
total number of tiles required, making no allowance of measuring instruments, and Simpson's rule. It is
for wastage. usually considered sufficient for craft students to
have an understanding of the mid-ordinate rule which
is explained as follows.
"
f--~_m_......-J I
E
I M
I
1
CD
E
E
.....
[ I
I
I
3m
1_
·1
Figure 9.16
- -70
No. Log
--l
--
0.0225 70
0.0225
1.8451
2.3522
c..,.-_3_m_ _....;9:...;m....;3_m
\-
3m
-,
= 3111 3111 3.4929 Figure 9.17
Quantities of Materials 119
Figure 9.19
number of strips of equal width and the mid-ordinate
of each strip drawn and scaled off as shown. The
length could have been divided into three 4 m wide Note Figure 9.20 shows why the mid-ordinate rule
strips, four 3 m wide strips, twelve 1 m wide strips or, is fairly accurate; the formula directs that the strips
as shown, six 2 m strips; it should be obvious that the are placed end to end and their overall length is then
greater the number of strips, the more accurate will multiplied by the width of the strip.
be the result. One final example is as follows. The irregular
figure shown in figure 9.21 is to be covered with a
layer of concrete 150 mm in depth. Calculate the
volume of concrete required.
Area = width of strip x sum of the mid-ordinates
=4x(5+6+8+10+12+11 +8)
(mid-ordinates averaged)
I
I Area = 4 x 60
I I
I CD I
co = 240 m 2
M: ~ I
I
I Volume = area x thickness
I: m
2m 2~2~m 2m 2:1 = 240 x 0.15
Figure 9.18
=36 m3
Note If the ordinates are all given, the mid-ordinates
may be averaged (figure 9.21). If not they must be
To calculate the area using the formula given scaled off (figure 9.19).
Area = width of strip x sum of the mid-ordinates
= 2 x (2.2 + 2.4 + 2.8 + 3.6 + 4.8 + 10.6)
= 2 x 26.4
BRICKS FOR PAVING
= 52.8 m 2
Figure 9.19 shows an area of land 16 m wide which When brick-on-edge work is being carried out the
has been divided into four strips, each 4 m in width. number of bricks per square metre is as for face brick-
The mid-ordinates are drawn and accurately scaled work, that is, 60; but for brick flat paving there are
off as before. 45 per square metre.
Area = width of strip x sum of the mid-ordinates
= 4 x (6.4 + 10.4 + 12.8 + 14.2) Example 9.23
= 4 x 43.8
Calculate the number of paviors required to pave a
= 175.2 m 2 8.6 m x 7.5 m courtyard with brick flat paving.
120 Brickwork 3 and Associated Studies
__'-'r----..
I'
I
i
I
I
I E
o
~
------_._~
Figure 9.21
= 64.5 x 45
=8.6x7.5
:: 2902.5
= 64.5 m 2 = 2903
SOME USEFUL CONVERSION
FACTORS
121
MULTIPLE CHOICE QUESTIONS
Select your options from the questions below, under- (c) sand limes
line your selection, for example (b), and check your (d) engineerings
answers with those on page 130. -
7. A Y2 brick thick wall is 7.000 x 2.00 m. The
1. The number of site operatives who have lost their number of bricks required will be:
lives during the last eight years because of (a) 960
accidents is just over: (b) 840
(a) 100 (c) 920
(b) 500 (d) 880
(c) 1000 8. The recess in an indented quoin is usually kept to
(d) 2000 a maximum of:
2. When using the third order of levers, the effort is (a) 28 mm
applied: (b) 32 mm
(a) upwards at one end (c) 38 mm
(b) upwards between load and fulcrum
(d) 56 mm
(c) downwards at one end 9. When single herringbone bond is used for rectan-
(d) downwards between load and fulcrum gular panels, the cut bricks on each side will be:
(a) similar
3. Using a pulley, an effort of 400 N will raise a
(b) differing lengths
load creating a force of 700 N. The mechanical
(c) opposite
advantage of the pulley is:
(d) alternate lengths
(a) 0.571
(b) 2.8 10. Clay drains which pass under buildings should be
(c) 28 surrounded with:
(d) 1.75 (a) 200 mm of broken bricks
(b) 100 mm of pea gravel
4. Employees must take reasonable care of the
(c) 150 mm of concrete
health and safety both of themselves and all
other persons who may be affected by their acts (d) 125 mm of sand
or omissions. This is stated in the: 11. The number of facing bricks needed per square
(a) Construction Regulations metre in English, stretcher and Flemish bonds,
(b) Health and Safety at Work Act respectively, are
(c) Building Regulations (a) 120,80,90
(d) Building Safety Manual (b) 80,60,90
(c) 80,90,60
5. A fanguard on a scaffold should have a minimum (d) 90, 60, 80
slope of:
(a) 1 in 6 12. The typical sectional size of a poling board used
(b) 1 in 9 for timbering to trenches is:
(c) 1 in 12 (a) 50 x 25 mm
(d) 1 in 18 (b) 150x100mm
(c) 220 x 37 mm
6. When industrial premises require brick paved (d) 220 x 100 mm
areas, the type of brick most suitable would be:
(a) commons 13. According to the Construction Regulations, the
(b) pressed facings minimum width of a scaffold for men and
122
Multiple Choice Questions 123
29. How many cubic metres of dry materials are (c) 1.750 m
needed to make 4 m 3 of concrete if mixing (d) 1.150 m
shrinkage is 20 per cent?
38. A tapered straightedge is used in conjunction
(a) 4.4
with:
(b) 4.8
(a) sight rails
(c) 5.0
(b) foundation brickwork
(d) 6.0
(c) drain pipes
30. To provide intermediate support for ground floor (d) stepped foundations
joists, the following should be provided:
39. The water-test requires a head of water at the
(a) fender walls
highest point not exceeding:
(b) purlin walls
(a) 1.000 m
(c) loadbearing walls
(b) 1.500 m
(d) sleeper walls
(c) 1.400 m
31. A chimney stack measures 900 x 450 on plan. Its (d) 1.200 m
maximum height including the terminal would be:
40. In drainage systems rigid joints are formed by
(a) 900 mm using:
(b) 1.8 m (a) plastic cement and fibre glass rope
(c) 2.0 m (b) fibre glass rope and cement mortar
(d) 2.025 m (c) tarred gaskin and plastic cement
32. The test on fine aggregate which involves the use (d) cement mortar and tarred gaskin
of a salt solution is the test for:
(a) organic impurities
(b) efflorescence
(c) silt content
(d) mixing shrinkage
33. The minimum projection for a ladder above the
top of a working platform is:
(a) 1.2 m
(b) 1.0 m
(c) 900 mm
(d) 600 mm
34. Leaning chimney stacks often indicate:
(a) sulphate attack
41. The figure illustrates a relieving arch over a lintel.
(b) poor workmanship
(c) defective pointing
The part marked x is the:
(d) roof subsidence
(a) turning piece
35. Cat or crawling ladders are used: (b) core
(a) within buildings (c) centre
(b) in trench excavation (d) intrados
(c) between scaffolds
42. A double coupler is used on a scaffold:
(d) for roof work
(a) to fasten transoms to ledgers
36. A rubber-headed mawl is used to: (b) in all positions where strength is required
(a) compact hardcore fill (c) for all longitudinal bracing
(b) fix paving slabs (d) for all transverse bracing
(c) lay drain pipes
43. If a working drawing is made to a scale of 1 :50, a
(d) level brick paving
length of 7.5 m would be shown on the drawing
37. The vertical height of a ladder is 5.0 m, so the by a length of:
amount of horizontal distance to the foot of the (a) 150 mm
ladder will be: (b) 250 mm
(a) 1.250 m (c) 75 mm
(b) 1.500 m (d) 15 mm
Multiple Choice Questions 125
1 (a) span
(b) spacing
(c) lift
RJ tRR (d) bay
1-
2m
·1·
6m
.I 52. The maximum projection of a scaffold board over
its end support is equal to its thickness multipied
by:
44. What will the reactions be at RL and RR in the
problem shown in the figure?
(a) 2
(b) 3
(a) 3 kN and 1 kN
(c) 4
(b) 4 kN and 2 kN (d) 6
(c) 2 kN and 4 kN 53. Sand-lime bricks are subjected to steam-curing in
(d) 3 kN and 1 kN order to:
(a) harden them
45. Densities of building materials are usually stated (b) dry them before firing
in: (c) lower the moisture content
(a) N/mm 3 (d) ensure an even colour
(b) kg/m 3
(c) kN/m 2 54. The slump test is commonly used to test concrete
(d) kgfm 2 for:
(a) final strength
46. Step irons used in manholes should be spaced at (b) workability
a maximum vertical distance of: (c) water content
(a) 225 mm (d) setting and hardening
(b) 350 mm
(c) 300 mm
55. The elevation shown in the figure is an example
(d) 200 mm
of:
47. The internal surfaces of formwork to concrete
lintels should be coated with mould oil in order
to:
(a) apply a particular finish
(b) prev.ent leakage of cement grout
(c) assist the striking process
(d) produce a waterproof surface (a) English bond
(b) reverse bond
48. The drainage fitting which is used at the bottom (c) English cross bond
of a soil pipe is a: (d) Dutch bond
(a) rest bend
(b) gulley trap
56. The underside of a segmental arch is called the:
(c) rain-water shoe
(a) skewback
(d) back-inlet gulley
(b) intrados
49. A saddle fitting is used to: (c) haunch
(a) reduce the rate of flow (d) soffit
(b) connect drains to sewers
57. The best way to reduce heat losses through the
(c) form outlets from manholes
external walls of a domestic building is to:
(d) inspect long lengths of pipes
(a) build the inner leaf 1 brick thick in engineer-
50. Guard rails are provided when operatives are ings
liable to fall more than: (b) have an unventilated cavity between the two
(a) 1.5 m leaves
(b) 2.0 m (c) use 100 mm aerated concrete blocks for the
(c) 1.8 m inner leaf
(d) 2.0 m (d) fill the cavity with fibre glass
126 Brickwork 3 and Associated Studies
58. Drainpipes are no longer made or used in the UK 63. The figure shows a sectional elevation through a
in the following material: concrete strip foundation. In order to comply
(a) uPVC with Building Regulations, the dimension marked
(b) concrete x should be:
(c) clay
(d) pitch fibre
59. Flue liners for solid fuel appliances should be
bedded in:
(a) the same mortar used for the brickwork of
the stack
(b) high alumina cement mortar
(c) sulphate resisting cement mortar
(d) lime sand mortar
(not to scale)
60. Flexible jointed pipes should be bedded on:
(a) pea gravel (a) 100mm
(b) clinker ash (b) 150 mm
(c) river sand (c) 200 mm
(d) crushed bricks (d) 300 mm
61. The figure shows a: 64. The figure shows the first three bricks needed for
the commencement of a decorative panel in:
(c) 300 mm 74. A dentil course should not project more than:
(d) 220 mm (a) 75 mm
(b) 28 mm
69. The minimum height for a handrail to a stair-
(c) 56 mm
case, above the pitch line, is:
(d) 12 mm
(a) 780 mm
(b) 840 mm 75. A string course is built:
(c) 740 mm (a) around the face of a building
(d) 880 mm (b) over window openings
(c) under certain types of arches
70. Drawings (0) and (b) in the figure show the foot
(d) below window sills
of a raking strut, resting on a concrete base. The
strut is being tightened up by means of a lever. 76. Square diagonal basketweave panels are set out:
The order of levers shown in (0) and (b) respec- (a) below the centre line
tively is the: (b) from the sides of the panel
(c) at the base of the panel
(d) from the centre
77. Plinth courses are normally used to:
(a) form a decorative effect
(b) increase the wall thickness
(c) provide an alternative bond
(d) reduce the wall thickness
78. The equipment required to carry out tumbling-in
work is:
(a) bevel, square, lines, templet
(a) (b)
(b) square, templet, gun, bevel
(a) first and second (c) lines, square, templet, gun
(b) second and third (d) gun, lines, bevel, square
(c) first and third 79. Corbel courses are used to:
(d) second and first (a) form string courses
71. One reason why diagonal herringbone is the (b) increase wall thickness
easiest herringbone panel to set out and build is (c) increase stability
because: (d) terminate piers
(a) all the work is at 45° 80. The height, base diameter and top diameter of
(b) no diagonal cutting is necessary the slump cone are respectively:
(c) all the cut bricks are the same size (a) 300, 200, 100 mm
(d) all bricks to be cut can be marked from the (b) 300,150,100 mm
same bevel (c) 200, 150, 100 mm
72. Given that the mechanical advantage of a certain (d) 300, 200, 150 mm
pulley is 3, an effort of 150 N will raise a load 81. The Factory Inspector must be notified:
creating a force of: (a) if materials delivered to site do not comply
(a) 50 N with a BS
(b) 150 N (b) if a hoarding is to be erected in a public
(c) 300 N thoroughfare
(d) 450 N (c) where an injury involves absence from work
for 3 days or more
73. When carrying out the slump test on a sample of
concrete, the number of layers in which the cone (d) before pouring concrete in an excavation for
a foundation
is filled and the number of times each layer is
rodded is: 82. A header is placed adjacent to the quoin three-
(a) 3 and 25 quarter on every other course of stretchers. This
(b) 4 and 25 bond is:
(c) 3 and 35 (a) English garden wall
(d) 4 and 35 (b) English cross
728 Brickwork 3 and Associated Studies
j LS
L (d) continuous foundation
93. When a trench is excavated the spoil increases in
volume. This is known as:
(a) expansion
4m 2m
1- -I· (b) bulking
(c) swelling
(d) surplus spoil
(a) 2 kN
94. Wire cut bricks may be recognised because they
(b) 3 kN
have:
(c) 4 kN
(a) scratches on the face
(d) 6 kN
(b) shiny surfaces
86. The use of a boat level is desirable when: (c) no frogs
(a) using a long straightedge (d) deep frogs
(b) levelling individual bricks
95. A suitable foundation for domestic buildings built
(c) tamping oversite concrete
on shrinkable clay subsoils is a:
(d) checking small quoins for plumb
(a) raft
87. To remove a brick from an existing wall, it is (b) wide strip
necessary to use a lump hammer and a: (c) stepped
(a) plugging chisel (d) short bored piled
(b) raking out pick
96. Extra wall ties are necessary in cavity walls of
(c) brick bolster
domestic buildings when the:
(d) tiling chisel
(a) house is to be built on reclaimed land
88. A long, timber straightedge used to compact (b) building is to be over three storeys in height
concrete is called a: (c) cavity is in excess of 75 mm wide
(a) punner (d) building is to be heavily loaded
Multiple Choice Questions 129
97. To prevent displacement of struts in trench 99. The number of bricks required to carry out the
timbering, the following are used: efflorescence test according to BS 3921 is:
(a) lipping pieces (a) 10
(b) waling boards (b) 20
(c) puncheons (c) 24
(d) page wedges (d) 36
100. The term 'batching' of concrete materials refers
98. Curing concrete refers to: to:
(a) Correcting faults on the surface (a) mixing
(b) adding extra water to the mixer (b) measuring
(c) keeping it damp while hardening (c) pouring
(d) regularly checking the water content (d) transporting
ANSWERS TO
MULTIPLE CHOICE QUESTIONS
730
INDEX