Risk Management: UNIT-5
Risk Management: UNIT-5
Risk Management
- Introduction
- Risk identification
- Risk projection (estimation)
- Risk mitigation, monitoring, and
management
Project Risks
What can go wrong?
What is the likelihood?
What will the damage be?
What can we do about it?
2
Introduction
What Is Software Risk?
• Risk is an expectation of loss, a potential problem
that may or may not occur in the future.
• It is generally caused due to lack of information,
control or time.
• A possibility of suffering from loss in software
development process is called a software risk.
• Loss can be anything, increase in production cost,
development of poor quality software, not being
able to complete the project on time.
4
Types of software risks
• Software risk exists because the future is
uncertain and there are many known and
unknown things that cannot be incorporated
in the project plan.
• A software risk can be of two types
– (1) internal risks that are within the control of
the project manager and
– (2) external risks that are beyond the control of
project manager. 5
Definition of Risk
• A risk is a potential problem – it might happen and it might
not
• Conceptual definition of risk
– Risk concerns future happenings
– Risk involves change in mind, opinion, actions, places,
etc.
– Risk involves choice and the uncertainty that choice
entails
• Two characteristics of risk
– Uncertainty – the risk may or may not happen, that is,
there are no 100% risks (those, instead, are called
constraints)
– Loss – the risk becomes a reality and unwanted
consequences or losses occur 6
Risk Categorization – Approach #1
• Project risks
– They threaten the project plan
– If they become real, it is likely that the project schedule
will slip and that costs will increase
• Technical risks
– They threaten the quality and timeliness of the software
to be produced
– If they become real, implementation may become
difficult or impossible
• Business risks
– They threaten the viability of the software to be built
– If they become real, they jeopardize the project or the
(More on next slide)
product 7
Risk Categorization – Approach #1
(continued)
• Sub-categories of Business risks
– Market risk – building an excellent product or system
that no one really wants
– Strategic risk – building a product that no longer fits
into the overall business strategy for the company
– Sales risk – building a product that the sales force
doesn't understand how to sell
– Management risk – losing the support of senior
management due to a change in focus or a change in
people
– Budge t risk– losing budgetary or personnel
commitment 8
Risk Categorization – Approach #2
• Known risks
– Those risks that can be uncovered after careful evaluation
of the project plan, the business and technical environment
in which the project is being developed, and other reliable
information sources (e.g., unrealistic delivery date)
• Predictable risks
– Those risks that are extrapolated from past project
experience (e.g., past turnover)
• Unpredictable risks
– Those risks that can and do occur, but are extremely
difficult to identify in advance
9
Risk Management
• Risk management is carried out to:
– Identify the risk
– Reduce the impact of risk
– Reduce the probability or likelihood of risk
– Risk monitoring
10
Reactive vs. Proactive Risk
Strategies
12
Steps for Risk Management
13
Risk Identification
Background
• Risk identification is a systematic attempt to specify threats to the
project plan
• By identifying known and predictable risks, the project manager takes
a first step toward avoiding them when possible and controlling them
when necessary
• Generic risks
– Risks that are a potential threat to every software project
• Product-specific risks
– Risks that can be identified only by those a with a clear understanding of
the technology, the people, and the environment that is specific to the
software that is to be built
– This requires examination of the project plan and the statement of scope
– "What special characteristics of this product may threaten our project
plan?"
15
Risk Item Checklist
17
Recording Risk Information
18
Questionnaire on Project Risk
(Questions are ordered by their relative importance to project success)
19
(More on next slide)
Questionnaire on Project Risk
(continued)
7) Does the software engineering team have the right mix of skills?
8) Are project requirements stable?
9) Does the project team have experience with the technology to be
implemented?
10) Is the number of people on the project team adequate to do the job?
11) Do all customer/user constituencies agree on the importance of the
project and on the requirements for the system/product to be built?
20
Risk Components and Drivers
• The project manager identifies the risk drivers that affect the following risk
components
– Performance risk - the degree of uncertainty that the product will meet its
requirements and be fit for its intended use
– Cost risk - the degree of uncertainty that the project budget will be maintained
– Support risk - the degree of uncertainty that the resultant software will be easy
to correct, adapt, and enhance
– Schedule risk - the degree of uncertainty that the project schedule will be
maintained and that the product will be delivered on time
• The impact of each risk driver on the risk component is divided into one of
four impact levels
– Negligible, marginal, critical, and catastrophic
• Risk drivers can be assessed as impossible, improbable, probable, and
frequent
21
Risk Components and Drivers:
22
Risk Projection (Estimation)
Background
• Risk projection (or estimation) attempts to rate each risk in two ways
– The probability that the risk is real
– The consequence of the problems associated with the risk, should it occur
• The project planner, managers, and technical staff perform four risk
projection steps (see next slide)
• The intent of these steps is to consider risks in a manner that leads to
prioritization
• By prioritizing risks, the software team can allocate limited resources
where they will have the most impact
24
Risk Projection/Estimation Steps
1) Establish a scale that reflects the perceived
likelihood of a risk (e.g., 1-low, 10-high)
2) Delineate(describe/portray) the consequences of
the risk
3) Estimate the impact of the risk on the project
and product
4) Note the overall accuracy of the risk projection
so that there will be no misunderstandings
25
Contents of a Risk Table
• A risk table provides a project manager with a simple technique for
risk projection
• It consists of five columns
– Risk Summary – short description of the risk
– Risk Category – one of seven risk categories (slide 12)
– Probability – estimation of risk occurrence based on group input
– Impact – (1) catastrophic (2) critical (3) marginal (4) negligible
– RMMM – Pointer to a paragraph in the Risk Mitigation, Monitoring, and
Management Plan
26
(More on next slide)
Developing a Risk Table
• List all risks in the first column (by way of the help of the risk item
checklists)
• Mark the category of each risk
• Estimate the probability of each risk occurring
• Assess the impact of each risk based on an averaging of the four risk
components to determine an overall impact value (See next slide)
• Sort the rows by probability and impact in descending order
• Draw a horizontal cutoff line in the table that indicates the risks that
will be given further attention
27
• Risk Table:
28
Assessing Risk Impact
• Three factors affect the consequences that are likely if a risk
does occur
– Its nature – This indicates the problems that are likely if the risk occurs
– Its scope – This combines the severity of the risk (how serious was it)
with its overall distribution (how much was affected)
– Its timing – This considers when and for how long the impact will be felt
• The overall risk exposure formula is RE = P x C
– P = the probability of occurrence for a risk
– C = the cost to the project should the risk actually occur
• Example
– P = 80% probability that 18 of 60 software components will have to be
developed
– C = Total cost of developing 18 components is $25,000
– RE = .80 x $25,000 = $20,000
29
•Risk Impact & Probability have a distinct
influence on management concern
30
Risk Mitigation, Monitoring, and
Management
Background
• An effective strategy for dealing with risk must consider three issues
(Note: these are not mutually exclusive)
– Risk mitigation (i.e., avoidance)
– Risk monitoring
– Risk management and contingency planning
• Risk mitigation (avoidance) is the primary strategy and is achieved
through a plan
– Example: Risk of high staff turnover (see next slide)
33
Background (continued)
• During risk monitoring, the project manager monitors
factors that may provide an indication of whether a risk is
becoming more or less likely
• Risk management and contingency planning assume that
mitigation efforts have failed and that the risk has become
a reality
• RMMM steps incur additional project cost
– Large projects may have identified 30 – 40 risks
• Risk is not limited to the software project itself
– Risks can occur after the software has been delivered to
the user
(More on next slide)
34
Background (continued)