Bill of Materials San Enrique FS
Bill of Materials San Enrique FS
BILL OF MATERIALS
DESCRIPTION QTY UNIT UNIT COST AMOUNT
A1. MOBILIZATION/DEMOBILIZATION 1.00 lot
A2. BUILDING PERMIT & OCCCUPANCY FEE, MISC. FEE AND
1.00 lot
PROFESSIONAL FEE (Signed & Sealed)
A3. Occupational Safety & Health Program 1.00 mos
A4. Clearing 1.00 lot
A5. DILG & BFP Official Logo and Stainless Metal Cut Out
Letters Signage, Project Signboard and Commemorative 1.00 l.s
Marker
A6. Electrical Main line connection 1.00 l.s
A7. Hauling 1.00 lot
A8. EXCAVATION ( Vol. = 211.63 cu.m. ) 1.00 lot
A9. BACKFILLING (Filling materials) (V= 99.0cu.m) 1.00 lot
Sub-Total A
B. SITE DEVELOPMENT
1. Flagpole Construction 1.00 l.s
2. Concreting of driveway V=12.0 cu.m 1.00 l.s
Material Cost
Labor Cost
Direct Cost
Indirect Cost
Sub - Total B
G. CEILING WORKS
GROUND FLOOR (92.4 SQ.M)
1. Gypsum Board 36.00 pcs
2. Wall Angle 50.00 pcs
3. Double furrings 50.00 pcs
4. Carrying Channel 36.00 pcs
5. 1 1/2" Concrete Nails 4.00 kgs
6. Self tapping Screw 2,000.00 pcs
7. Blind Rivet 9.00 box
8. #16 Tie wire 10.00 kgs
9.Miscellaneous/Furring Accessories 1.00 lot
Mezzanine Floor (63.65 Sq.M)
1. Gypsum board 24.00 pcs
2. Wall Angle 39.00 pcs
3. Double furrings 34.00 pcs
4. Carrying Channel 24.00 pcs
5. 1 1/2" Concrete Nails 4.00 kgs
6. Self tapping screw 1,300.00 pcs
7. Blind Rivet 7.00 box
8.#16 Tie wire 6.00 kgs
9.Miscellaneous/Furring Accessories 1.00 lot
Material Cost
Labor Cost
Direct Cost
Indirect Cost
Sub - Total G
H. STAIRS
Portland Cement 55.00 bags
Sand 3.00 cuM
Gravel 6.00 cuM
16 mm ø x 6.0M Steel Bars Grade 60 20.00 pcs
12 mm ø x 6.0M Steel Bars (Slab) Grade 40 55.00 pcs
10 mm ø x 6.0M Steel Bars Grade 40 55.00 pcs
Tie Wire # 16 8.00 kilos
Material Cost
Labor Cost
Direct Cost
Indirect Cost
Sub - Total H
J. HARDWARE
1. Door Lockset 17.00 sets
2. Butt Hinges 26.00 pairs
3. Cabinet Handle 22.00 pcs
4. Cabinet Lockset 22.00 sets
5. Cabinet Hinges 33.00 pairs
Material Cost
Labor Cost
Direct Cost
Indirect Cost
Sub - Total J
K. TILE WORKS
Ground Floor,Mezzanine Floor and Stair
1. .60 m x .60 Granite Tiles( Offices & Quarters) 347.00 pcs
2. Unglazed Tiles 300mm x 300mm toilet floor tiles(toilet, stairs) 428.00 pcs
3. Glazed Tiles 300mm x 300mm toilet wall tiles(kitchen & toilet
778.00 pcs
wall)
4. Tile Adhesive 78.00 bags
5. Tile Grout(2.5kg) 33.00 bags
6. Cement 78.00 bags
7. Sand 7.00 cu.m
8. Bronze Brass stair nosing 10.00 pcs
Material Cost
Labor Cost
Direct Cost
Indirect Cost
Sub - Total K
L. PLUMBING WORKS
Ground Floor
1. PVC Pipe 6" dia. Series 1000 25.00 pcs
2. PVC Pipe 4" dia. Series 1000 10.00 pcs
3. PVC Pipe 3" dia. Series 1000 15.00 pcs
4. PVC Pipe 2" dia. Series 1000 10.00 pcs
5. PVC Fittings 1.00 lot
6. Water Closet with Fittings and Accessories 4.00 sets
7. Lavatory with Fittings and Accessories 4.00 sets
8. Vanity Mirror 3.00 sets
9. Telephone shower head and valve 1.00 sets
10. Strainer 4" x 4" Stainless floor drain 4.00 pcs
11. Faucet 5.00 pcs
12. Soap Holder 3.00 sets
13. Tissue Holder 3.00 sets
14. Bidet 4.00 sets
15. Hose Bibb 3.00 pcs
16. Teflon Tape 20.00 rolls
17. PVC Solvent Cement 10.00 cans
18. Water Pipe Line with fittings ( PPR No. 20) 1.00 l.s
19. Stainless Kitchen sink with accessories and fittings 1.00 set
20. Water heater 1.00 set
Mezzanine Floor
21. Water Closet with Fittings and Accessories 3.00 sets
22. Lavatory with Fittings 2.00 sets
23. Vanity Mirror 1.00 sets
24. Telephone Shower Head and Valve 3.00 sets
25. 4" x 4" Stainless Floor Drain with Strainer 5.00 pcs
26. Faucet 5.00 pcs
27. Soap Holder 3.00 pcs
28. Tissue Holder 2.00 pcs
29. Bidet 3.00 sets
30. PVCFittings 1.00 l.s
31. Gate valve kitz 6.00 sets
32. Water Pipe Line with fittings ( PPR No. 20) 1.00 l.s
33. Teflon Tape 8.00 rolls
34. PVC Solvent Cement 10.00 quarts
35. Vulca seal 1.00 liter
Kitchen / T&B Accessories
36. Kitchen/ Dining Utensil organizer 1.00 set
37. Stainless Towel Bar 4.00 sets
38. Stainless Grab Bar 4.00 sets
Material Cost
Labor Cost
Direct Cost
Indirect Cost
Sub - Total L
M. SEPTIC TANK
1. Cement 55.00 bags
2. Sand 3.00 cu.m
3. Gravel 4.00 cu.m
4. CHB 4" 320.00 pcs
5. 10mm dia x 6.0 m RSB 35.00 pcs
6. G.I Wire # 16 2.00 kgs
7. PVC Fittings 1.00 lot
8. Water Proofing Application 1.00 lot
Material Cost
Labor Cost
Direct Cost
Indirect Cost
Sub - Total M
N. ELECTRICAL WORKS
1. Installation of Double Pole Double Throw ( DPDT for Power Generator)
1.00 set
2. Entrance Cap 1" dia. 1.00 pc
3. Junction Box 4"x4" ( Deep Type) 50.00 pcs
4. Utility Box ( Deep type) 27.00 pcs
5. Co-Axial Cable 1.00 box
6. Telephone Wire 1.00 box
7. Convenience Outlet 20.00 pcs
8. Aircon Outlet 6.00 pcs
9. Range Outlet 1.00 set
10.Bell ( Big Ben) 1.00 set
11. 100W LED Lamp 6.00 sets
12. 2x40W Tubular Fluorescent Fixture 13.00 sets
13. 25W Compact Fluorescent Lamp 14.00 sets
14. 25W Pinlight 10.00 sets
15. 1-way, 1-gang switch with utility box 14.00 sets
16. 1-way, 2-gang switch witch utility box 6.00 sets
17. 1-way, 3-gang switch with utility box 1.00 set
18. 2.0 mmsq THHN Wire 4.00 boxes
19. 3.5 mmsq THHN Wire 5.00 boxes
20. 5.5 mmsq THHN Wire 2.00 boxes
21. 8.0 mmsq THHN Wire 100.00 mts
22. 22 mmsq THHN Wire 200.00 mts
23. 20mmdia uPVC Conduit 200.00 pcs
24. 40mm dia uPVC Conduit 15.00 pcs
25. 25mm dia RSC Conduit 3.00 mts
26. C Clamp for 20mmdia uPVC Conduit 200.00 pcs
27. C Clamp for 40mmdia uPVC Conduit 30.00 pcs
28. C Clamp for 25mmdia RSC Conduit 5.00 pcs
29. Elbow for 20mm dia uPVC Conduit 30.00 pcs
30. Elbow for 40mm dia uPVC Conduit 10.00 pcs
31. Electrical Tape 20.00 pcs
32. Tie Wire 10.00 kgs
33. Cable Tie 10.00 packs
34. Panel Board 1.00 set
35. 20AT, 50AF, 230V MCCB 2.00 sets
36. 30AT, 50AF, 230V MCCB 10.00 sets
37. 100AT, 50AF, 230V MCCB 1.00 set
38. 1HP Split Type Air-Conditioning Unit 3.00 sets
39. 3/4HP Split Type Air-Conditioning Unit 3.00 sets
Material Cost
Labor Cost
Direct Cost
Indirect Cost
Sub - Total N
Y. ROOFING WORKS
1. Rib Type Roofing 0.4mm 235.00 l.m
2. Fascia Flashing 27.00 pcs
3. End wall Flashing 21.00 pcs
4. Gutter 7.00 pcs
5. 4" G.I. Pipe 1.00 pcs
6. 12mm Steel Plate (300x300mm) 2.00 pc
7. 12mm bolt 4.00 pcs
8. Nut & Washer 4.00 pcs
9. C purlins 1.5mmx2"x4" 67.00 pcs
10. Angle bar 2"x2"x 6mm 45.00 pcs
11. Angle bar 1.5"x1.5"x 6mm 30.00 pcs
12. Angle bar 1"x1"x 3/16 41.00 pcs
13. 10 mm ø x 6.0M Steel Bars 68.00 kgs
14. Welding rod 30.00 pcs
15. Tecksrew 1,200.00 box
16. Blind rivets 5.00 gal
17. Paint (Epoxy reducer) 5.00 pcs
18. Paint brush 10.00 pcs
19. Sealant 5.00 tube
Material Cost
Labor Cost
Direct Cost
Indirect Cost
Sub - Total Y
TOTAL COST
Business Name/Address