Module 1 Week 4-6, TVE SMAW 10
Module 1 Week 4-6, TVE SMAW 10
CONTENT STANDARDS
The learner demonstrates understanding of basic concepts and underlying theories in
preparing weld materials.
PERFORMANCE STANDARDS
The learner independently demonstrates competency in preparing weld materials
needed for the job.
TECHNICAL TERMS
1. Oxy-acetylene is an equipment for cutting and welding outfit requires compressed oxygen
and acetylene gases.
2. Regulator a valve with controls flow of gases for processes such as welding by oxyacetylene
3. Gauges a device use to indicate the magnitude of pressure in the cylinder.
4. Working pressure gauge is the gauge attached to the regulator which determines the gas
working pressure during cutting.
5. Welding torch is a device used in oxy-fuel gas welding, cutting, brazing, and soldering
directing the heating flame produced by the controlled combustion of fuel gas.
6. Cutting outfit is a unit of cutting equipment used for cutting metals.
7. Plasma cutting is a process using plasma to transfer an electric arc to metal. The metal is
heated to its melting point by the heat of the arc and blown away by air.
8. Coupling distance is the gap between the end of the pre-heat cones and the surface of the
material being cut.
9. Gas flow is the amount of gas released from the regulator which passes through the hose
towards the direction of the torch tip.
10. Gas storage an area free from fire hazard. A storage for tanks filled with proper air
ventilation.
11. Gas volume is the amount of pressure gas.
12. Drying oven is an oven where electrodes are baked with a temperature from 200 deg. C –
300 deg.C.
13. LP Liquified Petroleum
Pre-Test
Directions: Choose the correct answer from the options given for every item. Write the
letter only. Use a separate answer sheet.
Introduction:
Pre-heat flame is properly adjusted all the safety measures must be taken before
you do the actual cutting. You may see how fast cutting goes, but drills and practices
will build confidence.
The distance between the end of the pre-heat cones and the surface of the mate-
rial being cut is known as the coupling distance. When cutting plates up to 76 mm (3
inches) thick and with Mapp ® gas, the coupling distance must be about 3.25mm (1/8”).
For cutting, coupling distance should be increased to get more heat from the secondary
flame cones. Materials (plates) over 305mm thick (12 inches) should be cut using 19.9-
31.8mm coupling distance.
Straight Cutting
Once the pre-heated spot is cherry red in color, the cutting oxygen lever should
be slowly depressed. This allows the pure cutting oxygen to attack the metal thus re-
moving the metal by flame pressure and oxidation when allowing the cutting oxygen to
flow out slowly, the spot will not be cooled by the fresh oxygen stream. Cooling could
happen if a large gush of oxygen is blown on to the heated spot all at once. The visible
oxygen cutting stream coming from the center hole of the tip when the cutting oxygen
valve is opened is called the stinger.
Manual hand cutting of sheet cut starts with the torch drawn over the gloved
hand. The welder must be comfortable and be free to move the torch along the line to
be cut. It is a good idea for the welder to get into the position and practice the cutting
movements a few times before lighting the torch.
The physics of a cut, as the cut progresses along a plate, records of what is hap -
pening during the cut which is preserved along both sides of the key. This record indi-
cates to the welder what is correct or incorrect with the pre-heat flame cutting speed
and oxygen pressure.
When bevel cutting is required, the torch head must be inclined in the position to
the preheated metal along the top edge of the parts. This allows the metal to form the
required bevel angle. The tip should be kept high enough so that the outlet holes are
away from any splashing molten metals. Bevel cuts in the production are usually done
by a radiograph. This produces a more accurate cut with less gas.
After performing task on oxy-acetylene and fuel gas cutting, there are other de-
signed cutting equipment/machines that produce mass cutting of materials at the largest
welding production segment in the workplace. The illustration/drawing shown on the
next page, are the cutting machines with work descriptions for the students to compre-
hend more.
A cutting machine can make several complex cuts at one time. Automatic torches
are set the same for pre-heating as the manual torches. However, the motor drives the
automatic torch along the line of cut at a speed it could easily be regulated using a vari -
able control mechanism.
When the starting point on the joint is cherry red, the cutting oxygen is engaged
for a continuous flow of oxygen. Then, the torch travel running mechanism is moved at
a speed necessary for a smooth key edge. The torch head on most automatic cutting
torches can be tilted to several angles for marking different bevel cuts. Using these ma-
chines, many different and complex cuts are made evenly.
Radius rods are also available for automatic cutting torches and for circle cutting.
Multiple cutting heads are commonly used for automatic cutting machines, especially
where many pieces of the same shape are required.
Plasma is a gas that has been heated to a high temperature and converted (ion-
ized) so that the gas becomes electrically conductive. The plasma cutting process uses
plasma to transfer an electric arc to the metal. The metal is heated to its melting point
by the heat of the arc and is blown away by air.
Directions:
Use the checklist below as basis for judging whether you meet the required compe-
tency? Write YES or NO as your answer in a separate sheet.
2. Can heat the spot and recognize the cherry red color.
4. Can start hand-cut with the torch drawn over the gloved hand.
Note: Have learners assess their performance. For criteria needing assistance, provide
the appropriate intervention/s.
Introduction
Proper cleaning of metal surfaces and edges must be in mind before any fit-up
and tacking takes place. There must be an acceptable cleaning procedure applied in the
surface of the plates and pipes before welding joints. The cleaning of surfaces and
edges is considered one step for achieving quality in the preparation of materials.
Below are acceptable practices in the preparation of surfaces and edges of the
materials.
Illustration: Figure 1
Edge A needs to grind smoothly and squarely so that no gaps appear on the fit-
up and the surface of the other plate to form Tee-joint. These two sides of the plate are
placed together to see to it that no gaps are found, then are tightly assembled. The con -
taminants that are found in the fit-up must be cleaned and removed for welding safety.
Safety measures:
Before tacking, air tight fit-up must be checked so as to avoid air pockets in the
fitted edge or surface.
After root face is made and smoothened on the beveled surface, the two plates
are placed together facing each other with an approximate gap before tacking may be
done. This kind of preparation is applicable for plates and pipes of different types of ma-
terials. The root face must not exceed the maximum of 3mm thick from wall thickness of
6mm to 20 mm.
Introduction:
Baking/Drying Oven
Drying Oven
Courtesy of https://www.indiamart.com/proddetail/
welding-electrode-drying-oven-20879757848.html
Welding production and fabricators that usually accepts welding jobs are under
the welding code provisions. First and foremost, there must be a standard plan for elec-
trode control and maintenance. Electrodes are kept in the stockroom for sometime be-
cause of the influence of atmospheric conditions. These electrodes have to pass the
Holding oven
After drying, remove the electrodes from the oven and store them in the storing
oven with a maintained temperature of 150 deg. C plus/minus 20 deg. C. The electrode
must remain in the oven without reducing the temperature as per 27 requirements. The
electrodes are maintained and controlled under the supervision of a storekeeper, as he
is responsible for the issuance of these electrodes to the welders and fitters.
Portable oven
Portable oven
https://weldingreto.en.made-in-
china.com/product/xKvQSHDJXBhq/
China-5kg-Portable-Welding-Electrode-
Normally, welders perform welding activities in the shop. In cases where welding
is done in a worksite, the welder should provide himself with a portable oven sometimes
called welder’s oven. The welder’s oven should be plugged to a power source. The tem -
perature that should be maintained is 70 deg. C plus/minus 10 deg. C. The unused
electrodes shall be returned to the storing oven at the end of the day’s work.
Different types of electrodes, size, current, and power source are the recom-
mendable data for electrodes that can be the basis for selection. Only four (4) types of
electrodes are reflected in this information, but this will help you understand their proper
use and their existing specification. Further studies about electrodes will help you dis-
cover many things about welding consumables.
The industrial gases must be stored in a separate storage room and must have
proper air ventilation. The place should be equipped with fire hazard signs and also a
unit of fire extinguisher to be installed in a location near the series of filled full tanks for
accessibility. Cylinders must be provided with protection caps to prevent the valves from
being broken. Defective tanks, fitters, and others must be separated and marked defec-
tive.
Welding Electrodes
E- stands for electrode and is used for electric arc welding process
The first two or first three-digit numbers designate the tensile strength of a metal in
thousands of pounds.
The last digit indicates the type of coating and the polarity of the electrode.
A. TRUE OR FALSE
Direction: Read each statement below carefully. White TRUE if the statement is correct
and FALSE if the statement is not correct. Use separate sheet of paper (tablet paper/
long bond paper)
____________1. Welding torch is a gas mixing and burning tool for the welding of metal
____________2. Welding rod is a filler metal in the form of a rod or heavy wire
____________3. Welding is joining two metals by applying heat to melt and fuse them,
with or without filler metal
____________4. Weldment is an assembly or structure whose component parts are
joined by welding
____________5. The metal that is to be worked or welded is called base metal.
B. MULTIPLE CHOICE
Direction: Choose the correct answer and write the letter that corresponds to your
choice on the answer sheet provided.
1. Why is cleaning of surface and edges of metal so important?
a. It provides good appearance of the cut material
b. It is given in the instruction.
c. Dirt and other substances are detrimental to weld quality.
d. It makes it easy to fit-up joint.
2. What tool is used to easily metal scales, old paints and rust?
a. Grinder c. Chipping hammer
b. Scraper d. Metal sand paper
3. Why is an air tight fit-up necessary for Tee-joint preparation?
a. Dirt or contaminant will not stick
b. Gas pockets associated with unfit fit-up are avoided.
Explain the following: Use separate sheet of paper (tablet paper/ long bond paper)
1. What are the specified dimensions or specifications in cutting and preparing edge
materials?
2. Why should cutting and preparing edge of materials be in conformity with a given
standard?
4. What are the specified dimensions per specifications in cutting and preparing edge
materials?
5. Why is there a need to measure the area, volume and perimeter of the weld materi-
als?
Essential Ideas:
Reflection:
I realized that___________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
_____________________________________.
Pre-Test 4. T
1. c 5. T
2. c
3. c Part B.
4. c 1.
5. c 2. c
6. c 3. c
7. c 4. c
8. c 5. c
9. c 6. c
10. c 7. c
8. c
9. c
10. c
11. c
Activity sheet
12. c
Part A.
13. c
1. T
14. c
2. T
15. c
3. T
References:
Technology & Livelihood Education – Grade 9 Industrial Arts: Shielded Metal Arc Welding -
(Prepare Weld Materials) Learner’s Material First Edition, 2014