0% found this document useful (0 votes)
13 views

Project Planner Dec-26: 1 Plan Duration Actual Start % Complete Actual (Beyond Plan % Complete (Beyond Plan)

The document outlines two projects with multiple activities and timelines. It shows the planned and actual start and duration dates for different activities across two projects over many periods. The percentage complete is also shown for each activity.
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views

Project Planner Dec-26: 1 Plan Duration Actual Start % Complete Actual (Beyond Plan % Complete (Beyond Plan)

The document outlines two projects with multiple activities and timelines. It shows the planned and actual start and duration dates for different activities across two projects over many periods. The percentage complete is also shown for each activity.
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Project Planner Dec-26 n ###

Select a period to highlight at right. A legend describing the charting follows. Period Highlight: 1 Plan Duration Actual Start % Complete Actual (beyond plan) % Complete (beyond plan)

assigned person PLAN ACTUAL PERCENT


ACTIVITY PLAN START DURATION ACTUAL START DURATION COMPLETE PERIODS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60

1
y 1 23 5 20

schematic 1 9

prelimanary 10 7

final 17 7

Model 10 14

2
h 10 42

schemaatic 10 10

premailer 20 20

final 40 12
model 30 22

3
g

schematic

prelimanary

final

Model

4
h

schematic

prelimanary

final

Model

You might also like