Crackamite Usage Manual
Crackamite Usage Manual
Revolution
1
What is Crackamite?
Crackamite is a soundless, non-
explosive and safe demolition agent
which is quite different from ordinary
demolition agents such as explosives and
dangerous materials. It does not cause
any explosion, noise, ground vibration,
gas, dust or any other environmental
pollution when used properly.
Marble Quarrying
Granite Cutting
Rock Breaking
Limestone Mining
Stone Cutting
Concrete Demolition
1
Removing boulders
Breaking rock into pieces
Excavating foundations
Leveling stones for road works
Excavating trenches for pipe-laying
Underground excavations
Demolition of concrete or reinforced concrete objects
Demolition of foundations
Demolition of breakwaters or jetties
Demolition of tiled and refractory structures, and more
In the field as a new method of demolition, Crackamite
can effectively be use in the construction and civil
engineering fields as follows:
Bridges
Ledge
Machinery Bases
Slabs 6 " thick and more
Dams
Boulders
Concrete Piers
Marble and Granite
Crackamite can be used on any type of rock formation, concrete,
reinforced concrete or tiled structure in:
excavating foundations;
leveling rocks for road works;
excavating trenches for pipe-laying;
underground excavations;
1
marine and submarine excavations;
removing boulders;
demolition of concrete or reinforced concrete poles,
towers, walls, etc.;
demolition of foundations;
demolition of breakwaters/jetties;
demolition of tiled and refractory structures.
Crackamite provides the most technically suitable and cost-
effective solution in:
2
benefits of Crackamite can be listed against
explosives and other methods of breaking,
cutting or demolishing.
3
conditions. The expansive stress along the hole depth is almost
constant except for that near the entrance of the hole. Generally
the expansive stress loss from the hole entrance has little effect on
the demolition work when hole depth is long.
4
CRACKAMITE PROVIDES THE MOST TECHNICALLY SUITABLE
AND COST-EFFECTIVE SOLUTION IN:
• Restricted demolition of stone and concrete structures where
nearby structures must be protected from vibration generated
by explosions
• Pre-splitting of stone
formations, to create isolated
blocks that can then be more
easily demolished
• Cutting blocks of marble and
granite more economically
than that of the traditional
wire saw method
• Excavations and demolition
of stone or concrete structures where the use of explosives
would be expensive due to long operating times, special
transport, storage, handling precautions and the need to
comply with public safety regulations.
5
• Crackamite is ideal for the mining of emeralds and other
precious and semi-precious stones, as the brittle material is not
destroyed or broken up, just cracked.
• Crackamite has a shelf-life
of 2 years, thus obviating
problems associated with
out-of-date material as may
be the case with explosives
and detonator fuse.
• Hoisting operations can be
minimized when using
Crackamite, significantly
reducing electricity and
maintenance costs.
• Mines employing only Crackamite do not need to evacuate
personnel from the shaft before blasting. Labour can therefore
be more productively and cost-effectively employed, thus
safeguarding jobs and time.
• Because of the all-round saving, particularly in the areas of
labour, winching, electricity maintenance and cleaning, many
marginal mines could avoid closure with the use of Crackamite.
• Mine safety is promoted
because there is no danger
of underground fire caused
by explosives or igniter
cord. There is no post-blast
caused by misfires. Mine
safety is further enhanced
since the disturbance of the
surrounding rock is minimal
as there is no concussion or
vibration and there are no
blasting accidents.
• Heavily faulted areas are mineable utilizing Crackamite due to
its inherent capabilities.
6
CRACKAMITE PROVIDES THE MOST TECHNICALLY SUITABLE
AND COST-EFFECTIVE SOLUTION IN:
• Restricted demolition of stone and concrete structures where
nearby structures must be protected from vibration generated
by explosions
• Pre-splitting of stone formations, to create isolated blocks that
can then be more easily demolished
• Cutting blocks of marble and granite more economically than
that of the traditional wire saw method
• Excavations and demolition of stone or concrete structures
where the use of explosives would be expensive due to long
operating times, special transport, storage, handling
precautions and the need to comply with public safety
regulations.
Explosives
Very
(Concrete High High High High Low Very High High
High
Cracker)
7
How Does Crackamite® Work?
When Crackamite is mixed with an appropriate quantity of water
and poured into cylindrical holes drilled in rock or concrete, it
hardens and creates an amazing expansive pressure of 11
MT/m2. Crackamite cracks the matter to be demolished which
then can be easily removed with a pick breaker, pneumatic
breaker, excavator, etc.
8
more than 11,000 T/m2 at room temperature after 24 hours. As
Crackamite generates its expansive stress, the material to be
cracked undergoes a process of (1) crack initiation, (2) crack
propagation, (3) the increase of crack width. Therefore, this
fracture mechanism is distinguished from a breakage by blasting .
9
also arises from the bottom of the hole running toward the free
surface.
10
ESTABLISHMENT OF FREE SURFACE:
In the case of trenching, shafting or tunneling, if all holes are
drilled vertically and filled with Crackamite, the crack width can
not increase but horizontal cracks initiate. Therefore, in order to
obtain two free surfaces, inclined holes or pre-splitting must be
required.
Fig. 1 - Time required that expansive stress reaches 11,200 T/m2 and
Temperature
11
Fig. 2 - The relation between the expansive stress and hole diameter.
12
Factors affecting the expansive pressure of
Crackamite®
a. The
expansive stress
developed by
Crackamite
reach a
maximum value
at about 24
hours of
reaction.
However it still
keeps increasing
slightly even
afterwards.
b. The
expansive
pressure of
Crackamite
decreases as the
water to
Crackamite
powder ratio
increases. The
optimum ratio is
0.30.
13
c. The
expansive
capabilities of
Crackamite
increase s with
increase in
ambient
operating
temperature
upto the
maximum
operating
temperature.
d. The
expansive power
of
Crackamite
decreases with
increase in the
diameter of pre-
drilled hole
above the
optimal value.
14
TYPE OF CRACKAMITE USABLE TEMPERATURE
CM - H 35 °C TO 45°C
CM - A 25 °C TO 35 °C
CM - B 15°C TO 25 °C
CM - C 5 °C TO 15°C
CM - D -5 °C TO 5 °C
15
How to use Crackamite®
Hole Design Design the hole pattern according to the job site
16
Crackamite Grade Selection
Always start by matching the temperature of the material to be
cracked with the temperature range of the grade of Crackamite.
Also, match the temperature of the water with the grade of
Crackamite you are mixing. (Ref - Table 1)
CRACKAMITE CM - A 25 °C TO 35 °C BELOW 35 °C
CRACKAMITE CM - D -5 °C TO 5 °C BELOW 5 °C
Temperature Estimation
As shown in the figure on the right, place
a thermometer in the bottom of the hole
and leave it in place for 2-3 minutes.
Then quickly pull out the thermometer
and take a reading. Avoid taking
temperature right after drilling since the
temperature of the hole is higher
because of friction heat.
17
breaking should be done according to
the properties of rocks, joint, volume
to be removed, secondary breaking,
and work period, etc.
A=KxD
where, A - hole spacing (in mm), D - hole diameter (in mm) and K -
cra cking coefficient.
PLAIN CONCRETE 10 - 16 0 - 30
8 - 10 30 - 60
REINFORCED CONCRETE
6-8 60 - 100
18
K VALUE CHANGES WITH THE GEOMETRY AND SHAPE OF
ROCK OR CONCRETE
Lesser the free surface, smaller the K value Grea ter the free surface, larger the K
value
19
Note: Before experimenting with a test break, re ference should be
made to 'Hole Design for Rock' or 'Hole Design for Concrete' links (on
the left) to assist in y our special needs for successfully planning a
break design.
20
Estimating Quantity Required
Once the hole design is fixed, it is simple to figure out how much
Crackamite you need. The formula is:
Table 2 - Kg/m3 values for different hole sizes and depth of 1 meter
30 32 34 36 38 40 42 44 46 48 50
Hole Diameter
mm mm mm mm mm mm mm mm mm mm mm
Crackamite (Kg/m3) 1.2 1.3 1.5 1.7 1.9 2.1 2.3 2.5 2.8 3.0 3.2
Hole Depth One Meter
Note: You may get 3% to 6% less yield due to field conditions.
Pre-drilling Holes
Crackamite's effectiveness
depends on the placement,
diameter and depth of the
holes drilled in the material. To
determine the right
combination of hole size and
spacing, first make a reference
hole design using the
parameters from the hole
design sections, then drill
several holes of different
diameter at different burden
21
and spacing. Now check the break conditions of each of them and
then decide hole diameter, depth, burden and spacing.
Drilling
I. Drilling machine: Use electrical drill, rock
drill or crawler drill.
III. Hole diameter and hole spacing: The breaking plan of the
hole design sections should serve as a guideline in making this
decision. In general, the preferable hole diameter is from 40 to 50
mm.
Hole Depth
1. Maximum Hole Depth is 10 feet. (3.05 meter)
2. Minimum Hole Depth is 4 times hole diameter; for example 5"
with 1¼" hole, 6" with 1½". Holes shallower than 4 times
diameter are likely to blow out.
3. In reinforced concrete, drill 90% to 95% of its depth. In a
ledge, drill as deep as you want to remove. In boulders, drill
2/3rd to 3/4th of the rock's thickness.
4. In soft hardness rock, like Marble, hole depth is 100%. In
middle or high hardness rock, like granite, hole depth is 105%.
22
Hole Pattern
1. Holes must be drilled so as to
allow a free face for the
Crackamite to push towards. For
example, drilling at a 45° angle
in the flat surface of a ledge will
push it upwards, but drilling
straight down might not allow
the pressure to go anywhere.
2. To demolish a slab without
pushing out the walls, which surround it, drill a cone shaped
pattern at the center and fill these holes first. The cone will
pop upwards and create a free face.
3. Hole pattern depends on tensile strength of what you're
breaking, amount of rebar, if any, and the size of the pieces
you want when you're done. This can often be determined by
experiment; a good starting point is to space holes one foot
apart, in rows, one and a half feet apart. In non-reinforced
concrete, holes may be spaced as far apart as 30 cm.
4. Hole pattern also depends on how fast you need results. More
holes spaced closer together will give faster cracking time and
smaller pieces, but will cost more in terms of labor and
Crackamite.
5. Boulders are much easier to break than reinforced concrete or
ledge, and drill holes can be spaced further apart, especially if
breaking speed is not critical.
6. Empty holes can also be used to direct cracks - they cost less
than filled holes. This will save money compared to filling all
the holes, but will slow down the breaking time.
23
Mixing of Crackamite®
CRACKAMITE is a powder
that must be thoroughly mixed
with clean water before use, in
a ratio of 30 % of the overall
weight (1.5 liters for each 5 kg
package). Gradually add the
powder to water, stirring all the
time to obtain a smooth, lump-
free mortar.
I. Mixing Equipment:
Mix Crackamite with water, one bag at a time, by hand or,
preferably, with a mechanical mixer. Prepare the following
equipment.
24
II. Mixing Method:
Pour approximately 1.5 liter (0.4 U.S. gallon) of water into
container. Add one bag of Crackamite gradually and mix well
until it has a good fluidity.
25
IV. Standard Quantity:
The quantity of Crackamite to be used for cracking differs with
the hole spaces and diameters. In Table 2, the relation between
the quantity of Crackamite used and the hole diameters is
indicated for the hole of 1 m depth, where Crackamite is mixed
at a water ratio of 30%.
26
i. Crackamite should be
poured into holes
within 10 minutes after
mixing with water.
Crackamite may loose
fluidity within 10
minutes of mixing and
become difficult to
pour. Once its fluidity is
gone, it should not be
diluted by re-mixing
with water, as its
strength is reduced. Longer mixing time will cause blow
outs.
ii. Crackamite is best filled using a bucket with spout or
funnel. For a horizontal hole use a grout pump. Drill
horizontal holes with some slope to help in filling.
iii. Crackamite must be poured into every hole upto the brim.
iv. For a horizontal hole, the hole can be easily plugged with
Crackamite as it reaches a clay like consistency as it
starts setting.
27
water. However, in
cold temperature,
avoid pouring water
as it may freeze in the
hole.
iv. When the material to
be cracked is
immersed in water,
use the sack method
indicated in Fig. 1.
Use a bucket or pump
when filling the sack
and then seal the
sack from the top to
avoid Crackamite
dilution. If there is no
flow of water around
Figure 1 : Use of Polyethylene Sack in hole
the mouth of the
holes, Crackamite may be directly poured into the holes
using the pump. This should gently displace the water in
the hole.
After-treatment:
i. Tamping with mortar or
sand is not required
after filling Crackamite.
It is also not necessary
to put any restrictive
cap. Just leave it as it is
and wait until cracks
initiate. Covering the
filled hole with tarpaulin
is desirable to avoid
dilution of Crackamite
from external water source until cracking starts.
ii. Spraying the surface with water, after the cracks initiate,
tends to increase the width of cracks and speeds up the
cracking process.
28
Crack Formation
Upon filling of the pre-drilled
holes with the mixed
Crackamite slurry, reaction
immediately starts to occur in
the Crackamite. Upon reacting,
the Crackamite mortar starts
hardening and expanding
causing the material to develop
cracks. The cracks generally
appear within 3 to 20 hours
after filling, depending on the
temperature. These cracks
spread further and become wider with time.
29
surface available. It is best to wait until Crackamite has worked
to full depth before removing the rock, as premature removal at
the first sign of a crack can hamper the leverage effect of
Crackamite.
Some points to remember after filling, while waiting for the cracks
to appear:
30
Table 1. Quantity of Inhibitor Required
5 °C None
15 °C 1 per 3 bag
25 °C 2 per 3 bag
35 °C 1 per bag
TYPE OF BREAKING BY
SECONDARY BREAKING REQUIRED
CRACKAMITE®
NOTE:
a. Be sure to wear PROTECTIVE GLASSES when secondary
breaking is carried out.
b. The crack width for rock or concrete continues to increase
with time and can become 10-30 mm (3/8"-1 1/8") after
several days, depending on free surfaces available.
31
Container and Storage
Crackamite is packed in 4 anti-moisture bags of 5 kg each and
then placed in a water-proof carton with a total weight of
approximately 20 kg.
32
Choose the correct grade according to the working
conditions.
Usage Tips:
1. Mix well and pour, while agitating the slurry, to make sure
that no air gaps are left in the hole.
2. Fill the hole almost to the top, leaving at least ½ inch
before reaching the top.
3. In summer, the best time to use CRACKAMITE is early
morning or evening when temperature of the material is
low. High material temperature might cause blowouts.
4. In summer, cover the holes to avoid direct sunlight, by
using a tarpaulin or wet hay.
5. When the ambient temperature is high, put some ice into
the water, and then mix with CRACKAMITE.
6. Depending on the material to be cracked, CRACKAMITE
may be mixed with more water to lower the costs.
7. For better results, it is important to note both air and
material temperature. Material temperature is the
temperature inside the rock or concrete which can be
different from the air temperature. DO NOT GUESS! Tie a
string on the thermometer and lower it into the drill hole.
8. In winter, mix 1% calcium chloride with CRACKAMITE.
9. If CRACKAMITE has completely dried into powder and
there are no cracks, then pour additional water onto
CRACKAMITE filled holes.
10. Never fill glass or metal containers with CRACKAMITE or
any container which widens towards the bottom.
11. Never pump CRACKAMITE with pressure.
12. Mixing by hand lengthens mixing time, and is more likely
to result in a blowout.
13. When rock or concrete temperature is above 23°C, add
approximately 150 ml of extra water per 5 Kg bag.
33
Safety Precautions
1. Do not use Crackamite for purposes than cracking rocks
or concrete.
2. Crackamite is a highly alkaline product. The Ph reaches
13 after contact with water and can cause severe irritation
to mucous membranes, especially eyes. Rinse with large
amounts of water any portion of the skin that comes in
contact with Crackamite. Consult a doctor immediately.
3. Wear safety glasses, rubber gloves and a helmet during
CRACKAMITE handling, mixing and filling. Wear a dust
mask when using CRACKAMITE in poorly ventilated areas
such as tunnels or mines.
4. Do not pour and leave Crackamite in bottles or cans to
avoid shattering of the bottle or can.
5. Do not look directly into any holes for at least 6 hours
after pouring. Crackamite may splatter or blow out of the
hole due to heat generation when temperature of material
to be broken is over the temperatures found in the
temperature chart. Do not get your face close to or stand
near filled holes for at least 3 hours after completion of
filling.
6. Shelter the holes from rain or sunlight only with a
tarpaulin sheet.
7. Do not use hot water.
8. Do not mix over one bag (5 kg, 11 b.) of Crackamite with
water at a time.
9. Use the proper grade of Crackamite.
10. Keep out of reach of children
34
Equipment for Mixing Protectors while mixing
35
wait a while before assuming failure. CRACKAMITE
continues to increase pressure for 24 - 28 hours
7. When mixed, if CRACKAMITE begins to steam in the
bucket, add ½ gallon or more of water, stir, and throw it
away. You’ve allowed too much time to pass from
beginning to mix.
8. If filled holes start to smoke or steam, that is a sign they
may be about to blow-out shot. Immediately clear the
area of people. The vapors are only steam, and are not
hazardous or toxic in any way.
36
10. A "know-it-all" attitude that causes some people to ignore
this manual instead of reading it thoroughly, cover to
cover.
11. Holes drilled closer than 10 " apart in soft rock or
concrete, in hot weather
12. Drill hole diameter 1½” is the best to work with
13. Blowouts will usually not occur more than 3 hours after
filling holes.
37
14. Do not plug holes with hard or setting materials after
filling.
15. Do not pour CRACKAMITE mortar into glass bottles or
similar containers; the pressure will shatter the glass.
Dispose off unused mortar only after substantial dilution
with water on an open surface.
38 - 44 mm
d
1 1 / 2 "- 1 3 / 4 "
D 70 % of Height
38
Underground Excavation
d L D
d L D
39
Splitting of Large Boulders
d L D
Slabbing
d L D
40
Leakage of Virgin Rock
The toe should be drilled at closer hole spacing and successively
broken from the front row. No drilling will cause poor breakage.
44 - 51 mm
The front holes (up to the sixth row)
d may be simultaneously filled in. It is
1¾ " - 2 " more effective for removal to fill in
30 - 40 cm one hole and then each two rows
L1 (2, 3) after a delay of 6 - 20 hours.
1 '- 1'4"
60 - 90 cm
L2
2 '- 3 '
Add 5 % of Height
D
80 °- 90 °
41
Trenching And Tunneling
Reliever holes are necessary when trench is deep
d L D
42
38 - 51 mm 30 - 40 cm
d L2
1½ "- 2 ' 1 '- 1'4"
40 - 60 cm 1 - 1.8 m
L1 D
1'4 "- 2 ' 3 '- 6 '
38 - 44 mm
d
1½ "- 1¾ "
30 - 60 cm
L
1 '- 2 '
43
Hole Design For Concrete
Crackamite's effectiveness depends SYMBOL KEY
on the placement, diameter and depth d Hole Diameter
of the holes drilled in the material. L Hole Space
D Hole Depth
Angle
Hole Direction
General Concrete
When vertical drilling is difficult, drill horizontal holes with some
slope.
32 - 35 mm
d
1½ " - 1¾ "
40 - 60 cm
L
1´ 4" - 2´
D 70% of Height
Reinforced Concrete
d and L depend on both quantity and shape of the reinforced
steel.
44
35 mm 38 - 44 mm
d
1 3/8" 1 ½" - 1 ¾"
20 - 25 cm 30 - 40 cm
L
8" - 10" 1’-1’4"
D 90% of Height
Thin Concrete
45
(2) AVOID DIAGONAL CRACK
32 - 38 mm 25 mm 32 - 38 mm
d
1 ¼"-1 ½" 1" 1 ¼" - 1 ½"
25 - 30 cm 10 cm 10 - 15 cm
L
10" - 1’ 4" 4"-6"
46
(3) SPLITTING OF WALL
38 - 44 mm
d
1 ¼" - 1 ½"
25 - 30 cm
L
10" - 1’
47
(4) SPLITTING OF SLAB
38 - 44 mm
d
1 ½" - 1 ¾"
25 - 30 cm
L
10" - 1’
48
38 - 44 mm
d
1 ½" - 1 ¾"
25 - 30 cm
L
10" - 1’
Mass Concrete
REINFORCED
CONCRETE
CONCRETE
38 - 51 mm 38 - 44 mm
d
1 ½" - 2" 1 ½" - 1 ¾"
50 - 90 cm 40 - 60 cm
L
1’8" - 3’ 1’4" - 2’
49
Pile Foundation
38 - 44 mm
d
1 ½"-1 ¾"
20 cm
L1
8"
20 - 25 cm
L2
8" - 10"
50
Thick Wall
38 - 44 mm
d
1 ½" - 1 ¾"
30 - 60 cm
L
1’ - 2’
51
Pier / Bridge / Foundation
Drilling depends on a shape of structure and a circumstance.
52
(1) Making of large block; Secondary (2) Making of small pieces;
breaking with large rock breaker Drilling is only from one side.
53
Zone Demolition
d L D
54
d L D
D L D
Delayed Filling
Fill in (1) holes then (2) holes after delaying (Refer to Figures 1, 2,
and 3)) This can be applied for controlling of a crack direction (See
Bellow).
55
FIGURE 1: SPLITTING OF LARGE BOULDER
d L D
56
FIGURE 2: TRENCHING AND TUNNELING OF ROCK
Reliever holes are necessary when trench is deep
d L D
38 - 51 mm 30 - 60 cm 1 - 1.8 m
45°-60°
1 ½" - 2" 1’ - 2’ 3’ - 6’
57
FIGURE 3: MASS CONCRETE
38 - 51 mm 38 - 44 mm
d
1 ½" - 2" 1 ½" - 1 ¾"
50 - 90 cm 40 - 60 cm
L
1’8" - 3’ 1’4" - 2’
58
Customer Testimonials
This motor base was 3' x 3' x 3'.
We needed to remove it for new
fitments. With a few holes and
Crackamite, it came apart in short
order.
- KOWIN CONDUCTORS
- AHUJA INDUSTRIES
- MEIKEN INDUSTRIES
- KVG CONSTRUCTIONS
- NATHANI BUILDERS
- NATHANI BUILDERS
60
Land Clearing and Rock Breaking
solution. These rocks needed to be
removed and the land cleared for
construction and landscaping work
- NATHANI BUILDERS
Non-Explosive Controlled
Limestone Quarrying in Rajasthan.
Crackamite is designed for
controlled mining and quarrying to
avoid waste of valuable stone and
to work safer.
- BK STONE MINES
- BK STONE MINES
61
Non-Explosive Controlled Marble
Quarrying in Rajasthan.
Crackamite is designed for this
type controlled mining to avoid
waste of this valuable stone. It
gives clean slabs without any
wastage
62
About Us - Hydraulics & Pneumatics
HYDRAULICS & PNEUMATICS (H&P) was established in 1993,
when one could not find even a simple O-Ring for the hydraulics
and pneumatics industry in the state of Rajasthan. Since then we
have introduced automation in 100's of small and medium scale
industries in Rajasthan. We are now an “A-Z Under One Roof”
store for all kinds of automation related spares and provide
complete solutions for every kind of industry. Being the biggest
such industrial store in Rajasthan spread over 14000 sq. ft. of
built up space, we carry an inventory
of more than 20,000 types of Best
Quality Components.
CUSTOMER DELIGHT
IS OUR MOTO We have a dedicated team of
professionals including Engineers,
MBA's, ITI's and other highly
committed and trained staff, with more
than 10 years experience in this field, who provide excellent Sales
& After Sales Services to our customers. In depth knowledge of
the product and its applications and a never ending zeal to delight
the customer is what keeps us going. We constantly strive to
supply customers with products of superior quality using latest
technology and best of raw material. We provide the most
technically suitable & cost-effective solution for the customers.
Hydraulics & Pneumatics dedicates itself to setting high
standards for safety and service in the
industry.
64
Our Esteemed Clients
65
Free Sample Order Form
Last Name
Designation
Company
Address
Phone ( ) Fax ( )
Mobile ( ) E-Mail
Use of product
Comments
Signature
66
We give you three easy ways to order:
• Visit us on the Web
• Fill out the order form and mail it to us
• Call us