Quality Management - Question
Quality Management - Question
Quality Management
A. Quality is achieved.
B. The cost of quality is high.
C. The cost of quality is low.
D. The customer pays the minimum price.
3. A project has faced major difficulties in the quality of its deliverables. Management now
states that quality is the most important project constraint. If another problem with
quality were to occur, what would be the BEST thing for the project manager to do?
5. Quality is:
A. Inspection.
B. Cost of quality.
A. Rework.
B. Quality training.
C. Scrap.
D. Warranty costs.
12. Control chart shows seven data points in a row on one side of the mean. What should be
done?
14. You are the program level manager with several project activities underway. In the
executing process group, you begin to become concerned about the accuracy of progress
reports from the projects. What would BEST support your opinion that there is a
problem?
A. Quality audits.
B. Risk quantification reports.
C. Regression analysis.
D. Monte Carlo analysis.
15. A project manager and team from a firm that designs rail road equipment are tasked to
design a machine to load stone onto railroad cars. The design allows for two percent
spillage, amounting to over two tons of spilled rock per day. In which of the following
does the project manager document quality control, quality assurance, and quality
improvements for this project?
16. During a team meeting, the team adds a specific area of extra work to the project because
they have determined it would benefit the customer. What is wrong in this situation?
17. The project team has created a plan for how they will implement the quality policy. It
addresses the organizational structure, responsibilities, procedures, and other information
about plans for quality. If this changes during the project. Which of the following plans
will also change?
A. Quality assurance.
B. Quality management.
C. Project management.
D. Quality control.
18. You are asked to select tools and techniques to implement a quality assurance program to
supplement existing quality control activities. Which of the following would NOT be
appropriate for this purpose?
A. Quality audits.
19. Management wants to look at how a project is doing as compared to past projects. To
make a valid judgment, management should compare this project to?
A. Benchmarks.
B. Flowcharts.
C. Bar charts.
D. Trend Charts.
20. A project is facing a major change to its project deliverables. If the project manager is
involved in determining which quality standards are relevant to the change, the project
manager must be involved in:
A. Quality management.
B. Perform Quality Assurance.
C. Plan Quality.
D. Perform Quality Control.