Checklist Testing and Inspection Without Interconnection: Shams Dubai
Checklist Testing and Inspection Without Interconnection: Shams Dubai
GOVERNMENT OF DUBAI
l;---/.::1 oW,.og .c.l.../~ ~
Dubai Electricity & Water Authority
SHAMS DUBAI
CHECKLIST
TESTING AND INSPECTION WITHOUT
INTERCONNECTION
1 SCOPE................................................................................................................................................................................................................. 5
1.1 PV PLANT AND INSPECTION DATA.........................................................................................................................................................6
3 DOCUMENTS ................................................................................................................................................................................................. 8
3.1 Reference documents and standards..........................................................................................................................................................8
3.2 PV plant design documents (Technical dossier) ...................................................................................................................................8
SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0 3
Dubai Electricity and Water Authority
4 SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0
Dubai Electricity and Water Authority
1 SCOPE
This document reports the results of the Mechanical Completion inspection.
The inspection consists of visual checks and of the measurement of selected electrical characteristics. Most checks are
required with reference to 100% of the installation, some checks and measures with reference to a minimum percentage of
15% of the installation.
Participants shall take note of inspection checks and measures for their own record. The test engineer of the Applicant /
Contractor shall prepare the draft Test Report that will be distributed to the participants for comments and approval.
The present Mechanical Completion inspection is related to testing without interconnection, a further on-site testing phase
shall be carried out in the frame of the Final Inspection: the Mechanical Completion test report will be thus become part of
the Final Inspection Report.
The checks to be performed in the Mechanical Completion inspection are described in the following paragraphs.
The testing instruments shall be provided by the Applicant / Contractor and have valid calibration certifcates in order that
valid on-site testing measures can be performed.
SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0 5
Dubai Electricity and Water Authority
1.1 PV PLANT AND INSPECTION DATA
Consultant
PASSED
TESTING AND INSPECTION WITHOUT
INTERCONNECTION RESULT
REJECTED
Consultant Designer
Contractor Installer
DEWA Inspector
6 SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0
Dubai Electricity and Water Authority
2 TESTING EQUIPMENT
Test equipment
Wattmeter
DC clamp meter
Reference cell
4 Cell temperature
Thermocouple / PT100
5 Checks on PV strings
Inclinometer
Digital multimeter
(*) It is recommended the use of equipment that can perform measurements in accordance to IEC 62446 (e.g. Seward
PV150, HT-Instruments PVCHECK, Gossen Metrawatt PROFITEST).
SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0 7
Dubai Electricity and Water Authority
3 DOCUMENTS
3.1 Reference documents and standards
[1] DEWA Standards for Distributed Renewable Resources Generators Connected to the Distribution Network
[2] DEWA Connection Guidelines for Distributed Renewable Resources Generators Connected to the Distribution
Network
[3] DEWA Inspection and Testing Guideline for Distributed Renewable Resources Generators Connected to the
Distribution Network
[1]
[2]
[3]
....
Technical Reports
[1]
[2]
[3]
....
Drawings
[1]
[2]
[3]
....
8 SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0
Dubai Electricity and Water Authority
4 TESTS AND INSPECTIONS WITHOUT INTERCONNEC-
TION TO THE NETWORK
4.1 Mechanical inspections and Tests
4.1.1 PV plant General Assessment
With reference to 100% of the installation, verify the correspondence to the drawings and design documents regarding
the quantity, type, sizing, installation and integrity of components and materials. The following checks shall be performed.
Note: 2.…..
3.…..
SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0 9
Dubai Electricity and Water Authority
4.1.2 Civil Works
The Inspections listed below will involve the competent Authority/Entity (i.e. Dubai Municipality, Trakhees, Etihad,
Esco etc.). A provisional description of the Inspection is given only to make the Applicant aware of the kind of checks that
may be performed.
With reference to 100% of the installation, verify the compliance with the drawings and design documents regarding
the quantity, type, sizing, installation and integrity of components and materials. The following checks shall
be performed.
Civil works
Note: 2.…..
3.…..
10 SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0
Dubai Electricity and Water Authority
4.1.3 Support Structures
The Inspections listed below will involve the competent Authority/Entity (i.e. Dubai Municipality, Trakhees, Etihad,
Esco etc.). A provisional description of the Inspection is given only to make the Applicant aware of the kind of checks that
may be performed.
With reference to 100% of the installation, verify the compliance with the drawings and design documents regarding
the quantity, type, sizing, installation and integrity of components and materials. The following checks shall
be performed.
Support Structures
1. …..
Note: 2.…..
3.…..
SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0 11
Dubai Electricity and Water Authority
4.1.4 Photovoltaic Modules
With reference to 100% of the installation, verify the compliance with the drawings and design documents regarding the
quantity, type, sizing, installation and integrity of components and materials. The following checks shall be performed.
Photovoltaic modules
Note: 2.…..
3.…..
12 SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0
Dubai Electricity and Water Authority
4.2 Inspections without interconnection
4.2.1 Electrical equipment
With reference to 100% of the installation, verify the compliance with the drawings and design documents regarding the
quantity, type, sizing, installation and integrity of components and materials. The following checks shall be performed.
Electrical equipment
1. …..
Note: 2.…..
3.…..
SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0 13
Dubai Electricity and Water Authority
4.2.2 Protection of Assembled Components (IP degree)
With reference to 100% of the installation, check the fulflment of the design prescriptions.
Note: 2.…..
3.…..
14 SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0
Dubai Electricity and Water Authority
4.2.3 String Combiner Boxes (DC string connections and AC auxiliary services)
With reference to a percentage of the installed plant, ranging between the 15% and the 20%, check compliance of labels
(cables, terminal blocks, and connectors) with drawings and design documents. Check the cables are tightened in their
respective terminals.
Note: 2.…..
3.…..
SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0 15
Dubai Electricity and Water Authority
4.2.4 Electrical Power Connections in Substations and Electrical Rooms
With reference to 100% of the installation, check compliance of labels (cables, terminal blocks, and connectors) with
drawings and design documents. Check the cables are tightened in their respective terminals.
Note: 2.…..
3.…..
16 SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0
Dubai Electricity and Water Authority
4.2.5 Bonding and Earthing System
1. …..
Note: 2.…..
3.…..
SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0 17
Dubai Electricity and Water Authority
4.2.6 Connections to earthing system of metal structures / equipment
With reference to 100% of the installation, check the connections to the terminals and the earthing grid.
corrosion.
Test of the electrical continuity of the
PV modules frames (if any) with the
3 supporting structure or installation and
test of bonding and earthing conductors
OK
□ NO N/A
on PV modules frames
In case of bonding and earthing
conductors on PV modules frames
4 the removal of any PV module(s) does
not compromise the continuity of the
OK
□ NO N/A
grounding system
Installation and test of the electrical
5 continuity of the grounding connections
of surge arresters
OK
□ NO N/A
cabins
Installation of the grounding connection
7 OK
of MV cable shields □ NO N/A
1. …..
Note: 2.…..
3.…..
18 SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0
Dubai Electricity and Water Authority
4.3 Tests without interconnection
4.3.1 Insulation of LV connections DC and AC
1. …..
Note: 2.…..
3.…..
SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0 19
Dubai Electricity and Water Authority
4.3.2 Measurements on PV strings
1. …..
Note: 2.…..
3.…..
20 SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0
Dubai Electricity and Water Authority
4.3.3 Calibration of protections (Interface Protection)
The Interface Protection(s) usually comes with predefned settings from factory. However it is required that settings are
checked on-site, if necessary the said settings shall be adjusted.
OK
□ NO
□ N/A
□
OK
□ NO
□ N/A
□
OK
□ NO
□ N/A
□
OK
□ NO
□ N/A
□
OK
□ NO
□ N/A
□
OK
□ NO
□ N/A
□
OK
□ NO
□ N/A
□
1. …..
Note: 2.…..
3.…..
SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0 21
Dubai Electricity and Water Authority
ANNEX 1 – INSULATION TESTS
Operational note
1. Test performed between each cable positive or negative and earth, test voltage maximum 1000Vdc for
1 minute.
2. Insulation resistance for acceptance of test result 1 MΩ.
Insulation tests
Insulation
Test time
Cable ID Connection (from / to) resistance Test result Ref. Note
[hh:mm]
[Mohm]
OK
□ NO
□
OK
□ NO
□
OK
□ NO
□
OK
□ NO
□
OK
□ NO
□
OK
□ NO
□
OK
□ NO
□
OK
□ NO
□
OK
□ NO
□
OK
□ NO
□
OK
□ NO
□
OK
□ NO
□
OK
□ NO
□
OK
□ NO
□
Note:
22 SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0
Dubai Electricity and Water Authority
ANNEX 2 – TESTS ON PV STRINGS
PV string open circuit voltage measurements
Operational notes
Measure short-circuited strings, downstream e.g. the DC disconnect of combiner box, inverter
1.
switched off.
Test each single short-circuited string, other strings in open. Apply the test voltage maximum 1000Vdc for 1 minute
2. between earth and short-circuited string. Before each new test open the DC disconnect, disconnect the last tested
string and connect the following string to be tested. Finally close the DC disconnect, and test.
4. Insulation resistance for acceptance of test result 5 MΩ in dry conditions (2 MΩ in wet conditions).
SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0 23
Dubai Electricity and Water Authority
Report of detailed test results
Combiner Box Start Time Stop Time Start Time Stop Time Start Time Stop Time
1 OK
□
2 OK
□
3 OK
□
4 OK
□
5 OK
□
6 OK
□
7 OK
□
8 OK
□
9 OK
□
10 OK
□
11 OK
□
12 OK
□
13 OK
□
14 OK
□
15
16
Itot_strings
VOC_ave [V]
ISC_ave [A]
Note:
24 SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0
Dubai Electricity and Water Authority
~
V
a)
~Jzlj
: =
I
/, ........_,
I
I
LI
b)
~EJ
:
I
/4 .
=
----~ _/
I
I
L1
fl --
~trq curnnl mtuJJiem t
c) I1
Figure 2 – Procedure for the measurements of the current of strings and array:
SHAMS DUBAI - Checklist testing and inspection without interconnection Version 2.0 25
Dubai Electricity and Water Authority
'" EXPO Our Vision
CJ I) [ml[] ml a DEWAOFFICIAL
2020
DUBAI
A globally leading sustainable innovative corporation
P.O. Box 564, Dubai, United Arab Emirates
•· I
[email protected] www.dewa.gov.ae UAE T: +971 4 601 9999
OFFICIAL SUSTAINABLE ENERGY PARTNER