Chapter11 Capacity Management
Chapter11 Capacity Management
Chapter 11
Capacity Management
Photodisc. Photolink
Operations
strategy
Design Improvement
Introduction
•Providing sufficient capability to satisfy
current and future demand is a fundamental
responsibility of operations management.
•Get the balance right between the capacity
of an operation and the demand it is subjected
to and it can satisfy its customers cost-
effectively.
•Get it wrong and it could both fail to satisfy
demand and have excessive costs.
•Capacity planning and control is also
sometimes referred to as aggregate planning
and control.
Capacity constraints
•Any measure of capacity should reflect the ability of an
operation or process to supply demand.
Capacity constraints
•Revenues
•Capacity levels equal to or higher than demand at any
point in time will ensure that all demand is satisfied and no
revenue lost.
•Working capital
•Working capital will be affected if an operation decides to
build up finished goods inventory prior to demand.
•This might allow demand to be satisfied, but the
organisation will have to fund the inventory until it can be
sold.
Slack, Chambers and Johnston, Operations Management, 6th Edition,
11.13
© Nigel Slack, Stuart Chambers, and Robert Johnston 2010
11.14
•Speed
•Speed of response to customer demand could be
enhanced, either by the build-up of inventories or by the
deliberate provision of surplus capacity to avoid queuing.
•Flexibility
•Especially volume flexibility, will be enhanced by surplus
capacity.
•If demand and capacity are in balance, the operation will
not be able to respond to any unexpected increase in
demand.
Time
•Seasonality of demand
•Most markets are influenced by some kind of
seasonality – that means that they vary depending
on the time of year.
Causes of seasonality
•Seasonality of demand
Measuring Capacity
•The main problem with measuring capacity is the
complexity of most operations.
•Only when the operation is highly standardized and
repetitive is capacity easy to define unambiguously.
•Input capacity measures are frequently used to define
capacity.
Worked example
•Suppose an air-conditioner factory produces three different
models of air-conditioner unit, the deluxe, the standard and
the economy.
•The deluxe model can be assembled in 1.5 hours, the
standard in 1 hour and the economy in 0.75 hours.
•The assembly area in the factory has 800 staff hours of
assembly time available each week.
•If demand for deluxe, standard and economy units is in the
ratio 2:3:2, the time needed to assemble 2 + 3 + 2 = 7 units
is:
•(2 x 1.5) + (3 x 1) + (2 x 0.75) = 7.5 hours
•The number of units produced per week is:
•800 x 7 = 746.7 units
•7.5
Worked example
•Not all of these losses are the operations manager’s fault. They
have occurred because of the market and technical demands on
the operation.
•The actual capacity which remains, after such losses are
accounted for, is called the effective capacity of operation.
Actual output
Efficiency =
Effective capacity
Planned loss
Design of 59 hours
capacity
Avoidable loss –
Effective
58 hours per week
capacity
Actual output
Utilization=
Design capacity
Demand
Level capacity Chase demand
management
Absorb
demand
Have
excess
capacity Keep output
level
Make
Make to
customer
stock
wait
Part finished Queues
Finished goods, or Backlogs.
Customer inventory
Slack, Chambers and Johnston, Operations Management, 6th Edition,
11.45
© Nigel Slack, Stuart Chambers, and Robert Johnston 2010
11.46
11.47
© Nigel Slack, Stuart Chambers, and Robert Johnston 2010
Adjust output to match demand
11.48
Adjust output to
match demand
Hire Fire
11.49 products. © Nigel Slack, Stuart Chambers, and Robert Johnston 2010
11.50
Change demand
Change
demand
7000
Forecast in aggregated units
6000
of output per month
5000
4000
3000
2000
1000
0
J F M A M J J A S O N D
Months
For any capacity plan to meet demand as it occurs, its cumulative production
line must always lie above its cumulative demand line.
60
Forecast cumulative aggregated
40
Producing at
10
average demand
0
0 40 80 120 160 200 240
Cumulative operating days
Slack, Chambers and Johnston, Operations Management, 6th Edition,
11.67
© Nigel Slack, Stuart Chambers, and Robert Johnston 2010
Cumulative representations
11.68
Cumulative demand
Cumulative capacity
Unable to
Building meet orders
stock
Time
Low variability –
narrow distribution
of process times
Time
High variability –
wide distribution of
process times
Time
11.70
© Nigel Slack, Stuart Chambers, and Robert Johnston 2010
Simple queuing system (Continued)
11.71
Distribution of Distribution of
arrival times Server 1
processing times
Source of
customers
Queue or Served
‘waiting line’ customers
Server m
Boundary
of system