1.0 APPROVAL
Prepared by
Reviewed by
Reviewed by
Reviewed by
Reviewed by
Approved by
4.0 ABBREVIATIONS
Ann Annexure
Bar (g) Gauge pressure in bar
CE Common European Standards
cGMP Current Good Manufacturing Practices
Doc. Document
DQ Design Qualification
Equip. Equipment
FAT Factory Acceptance Test
FDA Food and Drug administration
HEPA High Efficiency Particulate Air
HZ Hertz
IQ Installation Qualification
MOC Material of Construction
NA Not Applicable
OQ Operational Qualification
Ph Phase
QA Quality Assurance.
USER REQUIREMENT
SPECIFICATIONS
Source of
Sr. No. Parameters Requirement / Specifications
Requirement
2. RLAF shall have negative pressure
recirculation air flow design.
3. The design should allow easy cleaning of
the RLAF unit.
4. The RLAF unit shall be provided with in
built light system for operator visibility
and comfort, separate on-off switch shall
be provided for lights
5. The RLAF body should be fully welded
and shall be leakproof for Aerosol to pass
from body to room.
6. The blower speed control nobs shall be
located on the operating panel.
7. Aerosol injection and testing ports shall
be as accessible positions and shall have
minimum distance to filter upstream to
avoid the concentration loss.
8. RLAF shall be supplied with antistatic PVC
strips.PVC strip shall be 6mm thick, 12”
wide with 2” overlap.
9. Two single phase sockets shall be
provided on rear wall for weighing scale
5.1.1 Operating parameters
Parameters to be displayed
1. Differential pressure across the filters
URS-11 on Control Panel & Process
2. Others (vendor to specify)
Monitored
URS-12 Measured Parameters 1. Differential pressure across filters Process
5.1.2 Environment
Process
URS-13 Equipment location & Layout Sampling room & Dispensing room
Process/
URS-14 Electrical classification Safe/Non-Flameproof
Safety
Intended Operating
URS-15 Class A (Background area Grade D) Process
Environment
5.1.3 MOC
Documentation
Manufacturer should provide (at minimum)
the following documents.
1. MOC certificates
2. Surface finish certificates
3. Confirmatory Certificates for bought out
components.
4. GA drawing along with layout dimensions
5. Design Specifications
6. Fan Curve ,fan selection and certificate
7. IQ & OQ protocols.
URS-35 List of Documents required 8. Operation and Maintenance and service Process/QA
manuals for all components
9. List of bought out items with makes
10. As built drawings
a. Control Schematics
b. Control Panel Assembly drawing
c. Wiring diagrams
11. Spare part list
12. Calibration certificates for all instruments
13. CE confirmatory certificate for all
relevant parts of the machine.
Maintenance
Source of
Sr. No. Parameters Requirement / Specifications
Requirement
Inspection and Testing
FAT & SAT Protocols shall be shared by
URS-37 FAT & SAT Process
supplier for approval before execution
URS-38 Stage wise Inspection Preferred /not mandatory Process
Support
Operator training to be included after
URS-42 Start-up support Process
commissioning of the system
1. Area Layout 1