2 ESTIMATION NOTES-unlocked
2 ESTIMATION NOTES-unlocked
Estimation
The word Estimation here refers to Material Take off (or) Quantity take off, of the
Entire project, for the concern service.
Departments:
Tender Department:
In this department, project will be done which are in tender stage and will be
closed in specified time and date provided by the main contractor, with project
final cost. The main aim for tender stage is to get an overview cost of the project
(Complete Building) and changes if any with any services.
After getting awarded the project in tender stage, the project will be forwarded
from the tender department to the project department. So now the project
becomes job in hand to the company.
Job in hand exactly refers to the Execution or installation of the project.
OWNER
ARCHITECH
(Main Contractor)
(Sub-Contractors)
Conversions or Equivalents: The units have fixed numerical relationship to each other
called equivalents or conversion factor.
Length or Distance: -
1 1 meter 3.28’ (feet)
2 1 meter 100cm = 1000mm
3 1 meter 39”
4 1 feet 12” (inches)
5 1 inch 25 mm or 25.4mm (exactly)
6 1 feet 300 mm (304.8mm exactly)
7 1 yard 3’
Area:
1 1mt2 10.76 ft2 (sft)
2 1 ft2 0.093 m2
3 1 ft2 144 in2
4 1 sq. yard 9ft2
Equipment Schedule:
An equipment schedule is a list of the Equipment’s present in the project.
Sample Project
Steps:
Copy the Documents in your local Drive.
Consultant: HBI International.
Client: Real Estate Huda.
Closing Date: 05 Jan 2018.
Open Equipment Schedule.
Sprinklers:
Upright – 406 no’s
Pendent – 502 no’s
Side Wall – 285 no’s
Quick response – 1 no
After taking all quantity of Entire Project Piping, accessories & Equipment’s.
Then do B.O.Q Comparison.
B.O.Q Comparison: Matching the quantity what is given and what you have got.
Lastly entire all the quantities (Piping, accessories, valves) in Excel program (Negotiation
matrix).