Boq - Drilling of Borehole

This document provides an estimate for drilling a water borehole, including 10 items of work needed to complete the project. The main work includes drilling an appropriate diameter borehole, supplying and installing PVC casing pipe and a sand screen, developing the water yield, and installing a submersible pump. The total estimated cost for drilling the water borehole is 1,906,000 Naira.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
643 views1 page

Boq - Drilling of Borehole

This document provides an estimate for drilling a water borehole, including 10 items of work needed to complete the project. The main work includes drilling an appropriate diameter borehole, supplying and installing PVC casing pipe and a sand screen, developing the water yield, and installing a submersible pump. The total estimated cost for drilling the water borehole is 1,906,000 Naira.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Page 1

JobTitle: ESTIMATE FOR DRILLING OF BOREHOLE Date: June, 2022


ITEM DESCRIPTION OF WORK QTY UNIT RATE (N) AMOUNT (N)
1.00 DRILLING OF WATER BOREHOLE
Provide motorised rig to site, set up rig / development
1.01 equipment and personnel, accessories and dismantle
on completion. 1 L/S 150,000 150,000
Drill an appropriate diameter borehole complete with
1.02
drilling rig. 1 L/S 200,000 200,000

1.03 Supply and install 8" diameter, 10 bar,PVC casing pipe.


25 M 3,000 75,000
Provide and install 6" Johnson Telescopic stainless
1.04 steel continuous slot sand screen complete with
bottom bunk. 10 M 7,000 70,000
1.05 Provide and fix heavy adaptor screen joinings. 1 NR 1,000 1,000
Clean out well and develop water yield by surging air
1.06
lift pumping and determine probable optimum output. 1 L/S 200,000 200,000
Provide and fix to casing stick-out temporary cap and
1.07
sealing plug. 1 L/S 100,000 100,000
Provide and install 2HP approved premium quality
submersible pump complete with electrical supply
1.08
line, control gears, low level water cut- off device.
(Back-up Standby Submersible pump) 1 L/S 180,000 180,000
Provide and fix 18mm marine rope of adequate
1.09 length to the pump and anchor on surface riser for
removal purpose. 1 L/S 50,000 50,000
Allow a provisional sum for the supply and fix of tank
1.10
stand 1 L/S 800,000 800,000
Supply and fix 100Ltr GeePee Tank 1 L/S 80,000 80,000
Sub-Total: (2) DRILLING OF WATER BOREHOLE 1,906,000

SUMMARY
2.00 DRILLING OF WATER BOREHOLE 1,906,000
AMOUNT CARRIED TO FORM TENDER (N) 1,906,000
TOTAL AMOUNT IN WORDS: One Million, One Nine Hundred and Six Thousand Naira Only