0% found this document useful (0 votes)
170 views

MSRA-T&C Electrical System

1. The document provides a method statement and risk assessment form for testing and commissioning the electrical system of a project located in Dubai Science Park. 2. It outlines the various tests to be conducted, including insulation resistance testing, earth fault loop impedance testing, MCB testing, and circuit performance testing. 3. The document also describes the commissioning procedure, including surveying equipment, instrument calibration, and the testing process.

Uploaded by

Sharvin Nageeb
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
170 views

MSRA-T&C Electrical System

1. The document provides a method statement and risk assessment form for testing and commissioning the electrical system of a project located in Dubai Science Park. 2. It outlines the various tests to be conducted, including insulation resistance testing, earth fault loop impedance testing, MCB testing, and circuit performance testing. 3. The document also describes the commissioning procedure, including surveying equipment, instrument calibration, and the testing process.

Uploaded by

Sharvin Nageeb
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 18

METHOD STATEMENT RISK ASSESSMENT FORM

Section A. Details
Project Name: Project Number: Location: MSRA Reference: Rev:
13TH FLOOR-SOUTH KPS-IWIN-MSRA-T&C-01 00
DSP - TECOM K22-006 TOWER, DUBAI Date of Submittal:
SCIENCE PARK
06-06-2022
Consultant: Main Contractor: Sub-Contractor:
M/S TUV M/S KPS IWIN ELECTROMECHANICAL LLC

Trades/Services: Architectural Civil/Structural M.E.P. Other: Spec. Reference:

Attachments: Catalogues Drawings Samples Compliance Statement Other: ITP, CHECK LIST

Description:
MSRA for testing
and commissioning REV 00
of electrical system

Section B. Material Submittal Attachment Details (tick as applicable)

Section C. Approval Details

Part A Cover Sheet


Part B Project Specification Spec. Compliance Statement Original Catalogue
Part C Product Data Sheet / Schedules Calculations & Test Results Supplementary Drawings
Part D Supplementary Design Data Supporting Documentation (for deviations)
Part E References Cardinals & Certifications

Consultant

Status Comments Authorized Signature


Lead Consultant:
Approved (A)

Approved as Noted (B)


Sub-Consultant:
Rejected – resubmit (C)

TAMDEEN and DTS Technical Reviewer

Status Comments Authorized Signature


Technical Reviewer:
No Objection

No Objection w/
comments

Objection

The above review / comments do not in any way imply acceptance of material / equipment installation / performance and
do not in any way absolve the contractor’s responsibility of fulfilling the contractual obligation and consultant’s
responsibility of fulfilling the design & supervision liability requirements.
TAMDEEN and DTS Project Manager

Status Comments Authorized Signature


Project Manager:
No Objection

No Objection w/
comments

Objection

Materials rejected must be resubmitted for approval with all requested documents & data. Contractor remains fully
responsible for approved materials under terms and conditions of the contract.
Note: For submittals requiring TAMDEEN and DTS review, consultant approval status shall reflect TAMDEEN and DTS approval status.
Note: If there are additional comments, please use continuation sheet.

DTS-AD-F-17 REV 1 Issued 10/11/19 page 1 of 1


TESTING AND COMMISSIONING
OF ELECTRICAL SYSTEM

Project: DSP - Tecom,Level-13 South


Tower, Dubai Science Park
Main Contractor: KPS
MEP Consultant: TUV
DOC. REF. NO. KPS-MEP-T/C-01
Method Statement
REVISION / ISSUE 00/01

DATE 06-06-2022

1. 0. Revision Status

Rev. 00
No.

Date 05-06-2022

Prepared Subcontractor
By QA/QC

Main Contractor
Reviewed MEP Engineer
By

Approved Consultant
By

Revision 00
Description First Issue
B.6 Earth Fault Loop Impedance Test

Earth fault loop impedance is to be checked for each final circuits with an impedance tester
and reading is to be verified with permissible limit.

B.7 MCB Test

All MCB are to be checked by means of RCD Tester with minimum 3 different set currents
(one setting above, one below and one rated sensitivity currents of an ELCB) and the trip times are
to be recorded. The values to be verified with the permissible test.

B.8 Circuit Performance

After all above tests are conducted and observed that they are satisfactory, an operational
test to be verify the desired performance of the circuits need to be carried out they are as follows
Switch on the MCB in the DB.

In case of lighting circuits, operate all the switches connected in the circuit to ensure their
functioning to the desired light fixtures in the desired manner.

In case of any other fixed equipment, operates the relevant switch and observed the functioning of
the equipment.

B.9 Full Load Current

Measure and record the current in all phases of the incoming cables in lighting DB’S Keeping
all the Lights ON.

B.10 Process

B.10.1 Surveying Equipment and instrument checking & calibration

1. All the instruments used for the commissioning shall have a valid calibration test certificates
and must be made available.

2. All Commissioning results shall be prepared, obtained and maintained by the commissioning
team as given in this procedure.

B.10.2 Commissioning Procedure

B.10.2.1 Testing Procedure

1. Start physical test according to the specifications.

2. Make Sure all installation is complete with approved WIR and all comments are
incorporated.

3. Megger Voltage of 500v shall be applied between following configuration of circuit and the
resistance values were recorded in site test certificate. Test Procedure shall be followed as detailed
below
PROJECT CODE NO: PROJECT NAME:
CONSULTANT NAME:
CONTRACTOR NAME:
MEP SUB-CONTRACTOR NAME:

EARTH FAULT LOOP IMPEDANCE TEST REPORT

INSTRUMENT TYPE/SL.NO

SI NO MCB Rating Equipment Earth Fault Impedance


Connected

Witnessed by: Tested by:


PROJECT CODE NO: PROJECT NAME:
CONSULTANT NAME:
CONTRACTOR NAME:
MEP SUB-CONTRACTOR NAME:

MCB TEST REPORT

INSTRUMENT TYPE/SL.NO

SI NO MCB RATING Equipment Connected Trip Time Required in m


seconds

Witnessed by: Tested by: