MSRA-T&C Electrical System
MSRA-T&C Electrical System
Section A. Details
Project Name: Project Number: Location: MSRA Reference: Rev:
13TH FLOOR-SOUTH KPS-IWIN-MSRA-T&C-01 00
DSP - TECOM K22-006 TOWER, DUBAI Date of Submittal:
SCIENCE PARK
06-06-2022
Consultant: Main Contractor: Sub-Contractor:
M/S TUV M/S KPS IWIN ELECTROMECHANICAL LLC
Attachments: Catalogues Drawings Samples Compliance Statement Other: ITP, CHECK LIST
Description:
MSRA for testing
and commissioning REV 00
of electrical system
Consultant
No Objection w/
comments
Objection
The above review / comments do not in any way imply acceptance of material / equipment installation / performance and
do not in any way absolve the contractor’s responsibility of fulfilling the contractual obligation and consultant’s
responsibility of fulfilling the design & supervision liability requirements.
TAMDEEN and DTS Project Manager
No Objection w/
comments
Objection
Materials rejected must be resubmitted for approval with all requested documents & data. Contractor remains fully
responsible for approved materials under terms and conditions of the contract.
Note: For submittals requiring TAMDEEN and DTS review, consultant approval status shall reflect TAMDEEN and DTS approval status.
Note: If there are additional comments, please use continuation sheet.
DATE 06-06-2022
1. 0. Revision Status
Rev. 00
No.
Date 05-06-2022
Prepared Subcontractor
By QA/QC
Main Contractor
Reviewed MEP Engineer
By
Approved Consultant
By
Revision 00
Description First Issue
B.6 Earth Fault Loop Impedance Test
Earth fault loop impedance is to be checked for each final circuits with an impedance tester
and reading is to be verified with permissible limit.
All MCB are to be checked by means of RCD Tester with minimum 3 different set currents
(one setting above, one below and one rated sensitivity currents of an ELCB) and the trip times are
to be recorded. The values to be verified with the permissible test.
After all above tests are conducted and observed that they are satisfactory, an operational
test to be verify the desired performance of the circuits need to be carried out they are as follows
Switch on the MCB in the DB.
In case of lighting circuits, operate all the switches connected in the circuit to ensure their
functioning to the desired light fixtures in the desired manner.
In case of any other fixed equipment, operates the relevant switch and observed the functioning of
the equipment.
Measure and record the current in all phases of the incoming cables in lighting DB’S Keeping
all the Lights ON.
B.10 Process
1. All the instruments used for the commissioning shall have a valid calibration test certificates
and must be made available.
2. All Commissioning results shall be prepared, obtained and maintained by the commissioning
team as given in this procedure.
2. Make Sure all installation is complete with approved WIR and all comments are
incorporated.
3. Megger Voltage of 500v shall be applied between following configuration of circuit and the
resistance values were recorded in site test certificate. Test Procedure shall be followed as detailed
below
PROJECT CODE NO: PROJECT NAME:
CONSULTANT NAME:
CONTRACTOR NAME:
MEP SUB-CONTRACTOR NAME:
INSTRUMENT TYPE/SL.NO
INSTRUMENT TYPE/SL.NO