Project: 1x950 TDS/Day Soda Recovery Boiler Customer: ITC LTD., - PSPD Enmas Engenius Projects Limited

1) The document outlines the erection progress and plan for a soda recovery boiler project in December 2006. 2) It provides details on the structural components, pressure parts, non-pressure parts, and balance of construction (BOC) that were planned to be erected in December as well as totals erected to date. 3) The total weight planned for erection in December was 292.36 tonnes while the total actually achieved was 252.23 tonnes, slightly below the target for the month.

Uploaded by

V U P Rao
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
38 views

Project: 1x950 TDS/Day Soda Recovery Boiler Customer: ITC LTD., - PSPD Enmas Engenius Projects Limited

1) The document outlines the erection progress and plan for a soda recovery boiler project in December 2006. 2) It provides details on the structural components, pressure parts, non-pressure parts, and balance of construction (BOC) that were planned to be erected in December as well as totals erected to date. 3) The total weight planned for erection in December was 292.36 tonnes while the total actually achieved was 252.23 tonnes, slightly below the target for the month.

Uploaded by

V U P Rao
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 2

Project: 1x950 TDS/Day Soda Recovery Boiler

ENMAS ENGENIUS PROJECTS LIMITED Date:31.12.06


Customer: ITC Ltd., - PSPD

Erection Progress / Plan for the month of DEC- 06


Drg Mat at Total weights DEC Month
PG-MA Description Balance Current Month Plan
Wt. Site Erected Wts.
NOV CUM Plan A W1 W2 W3 W4
STRUCTURAL P A P A P A P A
05-01 Foundation Materials 6.00 6.00 5.75 5.75 0.00 0.00 0.25
05-02 Columns 311.08 311.08 311.08 311.08 0.00 0.00 0.00
05-02 Tie Beams 174.83 174.83 161.66 161.66 0.00 0.00 13.17
05-03 Ceiling Structure 113.98 113.98 113.09 113.09 0.89 0.00 0.89 0.89
05-04 Floor Beams 115.60 115.60 51.89 83.85 33.00 31.96 31.75 6.00 8.92 7.00 0.29 10.00 9.58 10.00 13.18
05-05 Staircase and Gratings 192.62 192.62 49.29 85.89 22.00 36.60 106.73 5.00 13.72 6.00 5.77 5.00 8.94 6.00 8.17
05-07 Roof Truss 21.66 21.66 0.00 0.00 21.26 0.00 21.66 10.00 11.26
05-09 Vertical and Horizontal Bracings 48.35 48.35 8.66 9.98 4.00 1.32 38.37 1.32 2.00 2.00
PRESSURE PARTS
10-01 Steam Drum 30.91 30.91 0.00 30.91 30.91 30.91 0.00 30.91 30.91
11-01 Economiser 229.29 229.29 227.26 227.26 2.03 0.00 2.03 2.03
12-01 Water Wall Panels 196.17 117.65 0.00 84.73 84.81 84.73 111.44 22.86 13.36 18.48 29.62 42.03 32.33 10.86
13-01 Boiler Bank 131.56 131.56 84.09 119.32 47.47 35.23 12.24 30.00 29.47 17.47 5.76
xx-01 Super Heaters 127.4 67.23 0.00 0.00 0.00 0.00 127.40
20-01 Downcomer & Supply Piping 45.79 0.00 0.00 0.00 0.00 0.00 45.79
20-02 Riser, Sat & Eco to Drum Piping 24.28 9.86 0.00 0.00 0.00 0.00 24.28
20-03 Desuperheater & Link Piping 10.82 0.00 0.00 0.00 0.00 0.00 10.82
20-06 Feed Water & Eco Interstage Pipin 2.37 2.37 0.00 0.00 0.00 0.00 2.37
20-10 Boiler Integral Piping 1 0.00 0.00 0.00 0.00 0.00 1.00
NON PRESSURE PARTS
10-03 Supports for Steam Drum 2.75 2.75 0.00 2.75 2.75 2.75 0.00 2.75 2.75
11-04 Supports for Economiser 21.47 21.47 21.47 21.47 0.00 0.00 0.00
11-05 Economiser Casing & Hopper 49.25 36.60 0.00 0.00 24.00 10.38 49.25 12.00 8.55 12.00 1.83
11-07 Supports fo Economiser Casing 4.31 4.31 2.00 4.31 2.31 2.31 0.00 2.31 2.31
11-08 Economiser Seals 14.42 14.42 0.00 4.04 4.00 4.04 10.38 2.00 2.00 4.04
12-04 Water Wall Supports 19.45 7.34 6.52 15.80 12.93 9.28 3.65 3.23 3.23 0.52 3.23 8.76 3.24
13-04 Supports for Boiler Bank 12.41 12.41 6.57 6.57 0.00 0.00 0.00
13-06 Boiler Bank Seals 0.74 0.64 0.00 0.00 0.74 0.00 0.74 0.74
xx-04 Superheater Supports 15.11 10.86 0.00 2.71 0.00 2.71 12.40 2.71
BOC 450.00 49.63 5.04 5.04 0.00 0.00 444.96
Total 1733.42 1054.37 1306.60 292.36 252.23 69.84 65.47 49.88 60.04 91.63 83.62 81.75 43.10
1119.84 1179.88 1263.50 1306.60
TOTAL WT PLANNED FOR THE MONTH DEC' 06 = 292.36 TONNES
Project: 1x950 TDS/Day Soda Recovery Boiler
ENMAS ENGENIUS PROJECTS LIMITED Date:31.12.06
Customer: ITC Ltd., - PSPD

TOTAL WT ACHIEVED FOR THE MONTH DEC' 06 = 252.23 TONNES