Session 14-Capital Budgeting and Risk
Session 14-Capital Budgeting and Risk
Introduction
• Capital budgeting decisions require that managers analyze the
following factors for each project they consider:
• Future cash flows,
• The degree of uncertainty of these future cash flows, and
• The value of these future cash flows considering their uncertainty.
• Managers incorporate risk into their calculations in one of two
ways: (1) by discounting future cash flows using a higher discount
rate, the greater the cash flow’s risk, or (2) by estimating risk-
adjusted cash flows.
Measuring project’s stand-alone risk
• Statistical Measure of Cash Flow Risk:
• Range
• Standard Deviation
• Coefficient of Variation
• Once we know how to calculate and apply these statistical
measures, all we need are the probability distributions of
the project’s future cash flows
• Three approaches to incorporate risks in cash flows:
• Sensitivity analysis
• Scenario analysis
• (Monte Carlo) Simulation
Sensitivity & Scenario Analyses
• Estimates of cash flows are based on assumptions about
the economy, competitors, consumer tastes and
preferences, construction costs, and taxes, among a host
of other possible assumptions.
• One can analyze the sensitivity of cash flows to change in
the assumptions by reestimating the cash flows for
different scenarios.
• Sensitivity analysis is a method of looking at the possible
outcomes, given a change in one of the factors in the
analysis.
• Scenario analysis is a method of looking at the possible
outcomes under different probabilistic scenario of state of
the economy or industry.
Simulation Analysis
• Sensitivity analysis becomes unmanageable if we change
several factors at the same time.
• Simulation analysis allows the financial manager to
develop a probability distribution of possible outcomes,
given a probability distribution for each variable that may
change.
• However, simulation analysis looks at a project in
isolation, and ignores the effects of diversification for the
owners’ personal portfolio.
Monte Carlo Simulation
• Set the precise model of the project laying down the
variables that affect your cash flows.
• Specify probabilities (or range of outcome) for each
variable.
• Simulate the cash flows many times (e.g. 10000 runs)
• You get the distributions of project cash flows. Compute
the expected cash flows.
• Finally, using the applicable discount factor, discount the
expected cash flows to get NPV.
Scenario Analysis: A case study
•Financial Appraisal of Koyali-
Ratlam Pipeline
Justification
• Better evacuation of MS, SKO and HSD ex-Koyali.
• Reduce logistic cost and help in positioning IOC’s
products in Central India at competitive cost .
• The pipeline would act as an entry barrier to private
oil companies from laying Central India pipeline.
Financial Appraisal
• Laying down of pipeline would involve:
• Upfront investment- Rs. 322.92 crore (for 2MMTPA
capacity in phase I)
• Annual opex-Rs. 9.97 crore
• Augmentation of refining capacity at Koyali in line with
demand requirements
• Better throughput and savings therefrom.
Three different scenario
• Scenario-I
• Demand numbers at the levels as originally furnished by
Planning Department. Gives and takes escalated by the growth
rates adopted for demand.
• Scenario- II
• Demand numbers for IOCL and associates lowered. Gives and
takes as per scenario-I.
• Scenario-III
• Demand numbers same as scenario-II. Gives separately
determined.
IRR under various scenarios
IRR(%)
Project IRR(%)
Increase in capital 13.63 13.19 9.76
cost by 10%
Increase in opex 14.80 14.40 10.88
by 10%
Equity IRR(%)
Expected
= (0.50×$575) + (0.50×$0) = $287.50
Payoff
$287.50
NPV = –$300 + = –$38.64
1.10
The Option to Abandon: Example
Traditional NPV analysis overlooks the option to abandon.
Success: PV = $575
Expected
= (0.50×$575) + (0.50×$250) = $412.50
Payoff
$412.50
NPV = –$300 + = $75.00
1.10
Valuing the Option to Abandon
• Recall that we can calculate the market value of a
project as the sum of the NPV of the project
without options and the value of the managerial
options implicit in the project.
M = NPV + Opt
$75.00 = –$38.64 + Opt
$75.00 + $38.64 = Opt
Opt = $113.64
The Option to Delay: Example
Cost Cost PV PVNPV tNPVNPV
Year Year t 0
0 $0 20,000
$ 20,000 $ 25,000
$ 25,000 $ 5,000
$ 5,000 $ 5,000
1 $1 18,000
$ 18,000 $ 25,000
$ 25,000 $ 7,000
$ 7,000 $ 6,364
2 $2 17,100
$ 17,100 $ 25,000
$ 25,000 $ 7,900
$ 7,900 $ 6,529 $7,900
$6,529
3 $3 16,929
$ 16,929 $ 25,000
$ 25,000 $ 8,071
$ 8,071 $ 6,064 (1.10) 2
4 $4 16,760
$ 16,760 $ 25,000
$ 25,000 $ 8,240
$ 8,240 $ 5,628
• Consider the above project, which can be undertaken in any of the
next 4 years. The discount rate is 10 percent. The present value of
the benefits at the time the project is launched remains constant at
$25,000, but since costs are declining, the NPV at the time of launch
steadily rises.
• The best time to launch the project is in year 2—this schedule yields
the highest NPV when judged today.