Automatic Adjustment of Transformer in The Newton Power Flow
Automatic Adjustment of Transformer in The Newton Power Flow
the desired operating conditions: zero when no branch (k,m) exists for the network, but 2) C6km
and Dkm are also zero when branch (k,m) does not represent
t,new = told + c(Ereg - 3= 4,5 the LTC transformer that is regulating node m. Each LTC-
.2,new = o23°ld + d23 (P23reg - P23). (3) regulated-node column in (4a) thus usually has only one nonzero
off-diagonal C6km and/or Dkm term.
Acceleration factors C4, c5, and d23 are empirically determined, The nonzero block pattern of the Jacobian matrix in (4a) is
often resulting in slow and/or unpredictable overall convergence like that of (2a), so elimination may proceed in the usual order
for the problem. (based on network topology) [3], [4]. Appendix II details
formulas for the C6km and Dkm elements, and it is seen that only
AUTOMATIC ADJUSTMENTS minor changes from the elements in (2a) exist. As a result,
Continuing with the sample system, t4, ts, and 023 can be programming modifications are minor, and the changing of
"automatically" adjusted if included as variables, rather than LTCs between fixed and variable types when LTC limits are
as constants, in the constraint equations. The two variable types encountered during the course of the solution is easily done.
require two procedures: automatic LTC tap changing and Automatic Phase-Shifter Adjustments
automatic phase-shifter adjustments.
Phase shifter b23 in Fig. 1 is typically operated to constrain
Automatic LTC P23 at a value p23reg. But since P23 is not a regular problem vari-
An LTC such as T4 is operated so that t4 is adjusted (within able, a variable switch as was done for LTCs is not possible.
limits) to constrain E4 at value E4reg For this mode of operation 423 enters as an extra problem variable, and the linearized
E4 is a constant and t4 should replace it in (2a) as a variable. relation AP23 = P23reg - P23 is an additional constraint equation.
Hence, any LTC-regulated node i has its voltage E? replaced The resulting linearized Newton equations appear in (5a).
as a variable by ti. Incorporating these changes, (2a) is modified Note that both LTCs and the phase shifter will now be auto-
to become (4a): matically adjusted.
i- * 1
AP1 T
Hill
;r
H140 Aa1
AP2 H22N22 H23'N23' H24C24 E2,23 A32
AE2
AQ2 J22L22 J23'L23' J24D24 F2,23 aE2
AP3 H32'N32' H3aN33 H35C35 Es,23
AEs
AQ3 J32'LS2' J33Ls3 Fs3,23 E3
AP4 H41 H42AN42 H450 (5a)
A34
At4
AQ4 J41 J42L42 J450 t4
AP5 H53N53 H540 H5C655 6A5
At5
AQ5 Js3Ls3 J540 J55Ds5 t5
_ AP23 - H23,2'N23,2' H23,31N23,3I _LA\423 -
old method (curve 3), where taps are continually changed after TERMS ASSOCIATED WITH LTC TRANSFORMERS
each Newton iteration until all changes in (3) are less than 10-3
pu; then taps are permanently fixed (iteration 12 of Fig. 2), and a If node m is regulated by LTC transformer Tm (with tap tin),
final solution is obtained after an additional iteration (iteration the conventions shown in Fig. 3 can be assumed. Tm affects the
13). Although of course taps on the actual transformers are dis- self- and mutual admittances of nodes k and m by
crete, at least one is now able to "exactly" solve the problem
being formulated.
Ykm' = (Gkm0 + j1Bkm') = -Y
As of June 1969, the testing of automatic phase-shifter ad- Ykm = Ymk = tmYkm0
justments by the new method has been confined to small test
systems only. By inserting four phase shifters into the 20-node Ymm =
YmmI + t?m2y
NSP test system and finding solutions for different values of Ykk = YkkI+ yO. (10)
106 IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS, JANUARY/FEBRUARY 1971
.Okm
k 1- -->
m
km km
Fig. 3. Representation of ETC transformers. Fig. 4. Variable phase-shiftinig transformer representation.
The power flow equations for no(les k an-d m are 2) The off-diagonal terms in the row of the Pk1reg constraint
N equation are
(Pk + iQk) = Ek2Ykk* + EkEm*tmYkkm * + Es Ei*yki* Hkmm = - Hkm,k = Hkm
i/k
Nkm,m = Nkm.
(Pm + iQm) = Em2(tm2yO * + ymm' *) N1m, k = Nkm + 2Ek2Y COS (15)
07am
N 3) The terms in the column of the Pk1reg constraint equation
+ EmEk*tmYkmO * + Em E Ei*Ymi*. (11) are calculated using (5b). The off-diagonal terms are
t=1
am + jbm = (em + jfm)(Gkm + jBkm)
Differentiating (11) as in (4b), the off-diagonal terms where Ek,km -amfk + bmek= Hkm
= -
ki # m are
Fk,km = +amek + bmfik = Jkm
am0 + jbmO = (em + ifm) (Gk1f + jBkm') ak + jbk = (ek + jfk)(Gmk + jBmk)
Ckm = (amIek + bm0fk)tm = Nkm Em,km = +alkfm - bkem = Hmk
Dkm =
(am0fk -
bm0ek)tm =
Lkm (12) Fm,km = -akem - bkfm =Jmk (16)
and the diagonal terms are and the diagonal term is
Cmm = -2Gkm'Em2tm2 + (ak0em + bkofm)tm Ekm,1km= Ek,km. (17)
Dmm = 2B1m0Em2tm2 + (aOfm - bklem)tm. (13) REFERENCES
[1] J. P. Britton, "Improved area-interchange control for Newton's
method load flows," IEEE Trans. Power App. Syst., vol. PAS-
88, pp. 1577-1581, October 1969.
APPENDIX III [2] J. E. Van Ness and J. H. Griffin, "Elimination methods for
load flow studies," AIEE Trans. (Power App. Syst.), vol. 80,
TERMS ASSOCIATED WITH VARIABLE PHASE-SHIFTING pp. 299-304, June 1961.
[3] N. Sato and W. F. Tinney, "Techniques of exploiting the
TRANSFORMER sparsity of the network admittance matrix," IEEE Trans.
Power App. Syst., vol. 82, pp. 944-950, December 1963.
If nodes k and m are the terminal of the km phase-shifting [4] W. F. Tinney and C. E. Hart, "Power flow solution by Newton's
method," IEEE Trans. Power App. Syst., vol. PAS-86, pp. 1449-
transformer and if the phase shifter is on the k side of the Y 1460, November 1967.
admittance, the phase-shifting transformer can be represented
as shown in Fig. 4.
The admittance relationships are
y = Y(Cos 0klm + j sin Okm)
Ykm = Gkm + jB&-m
Discussion
-Y [COS (0k.m - 'k.) + ij ll (0km -
Okm)]
Ymk = Gmk + jBmk
(Itndian Institute of Science, Bangalore, India):
D. K. Subramanian
- -Y[cos (0m1k + Pkim) + i in (Omk + 'km)] iinproved Newton's method of incorporating
The authors have
additional autom.atic facilities that had been hampering the conver-
gence. This will aid in the -ise of these modified methods for on-line
Ykk = Ykk + " load flows. The authors' opinions are sought on the following poin-ts.
Whein the and powers corrected by tap changers
Ymm = Ymm +- Y (14) and1) phase shiftersvoltages
are not fixed at particular values but are kept
within specified limits, can this method be suitably modified to
The calcutlationi of tlhe termls of the Jacobian matrix (5a) incorporate the changes? Also, can miniinization methods minimizing
that are affected by the presenice of a plhase-shifting transformer losses be used in conjunction with these methods?
can be divided into three categories. 2) From Fig. 2 it is fouind that both old and new methods con-
1) The terms in the anid m rows of the Jacobian
k matrix verge with nearly the saimie speed up to an accuracy of 0.1. So for
shown as primes in (5a) are calculated by (8) using the admit-
tances given in (14). Manuscript received February 9, 1970.
PETERSON AND MEYER: AUTOMATIC ADJUSTMENT OF TRANSFORMER AND PHASE-SHIFTER TAPS 107
if the old method is used up to an accuracy of 0.1 and then the new
method is resorted to, will the computations be reduced? > >
3) In cases where phase shifters are employed on a line with the
voltages of the buses connected to that line kept at fixed values, 0 0:
uL U.a LL
00
JLt:
can phase shifters then be eliminated completely from the system
sr
equations? 0 0 0 0
Manuscript received February 12, 1970. Manuscript received February 13, 1970.
108 IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS, JANUARY/FEBRUARY 1971
adjustment of LTC transformers presents significant improvement In the NSP program we have chosen to limit the magnitude of all
for the solution of power flow problems. variable changes during the back-substitution step, with present
Incorporation of the new technique into the Newton algorithm
requires only minor modifications, yet gives significant saving
bounds being |AVI and |Atl < 0.1 pu, and IA5I < 30°. For certain
systems these restrictions might retard convergence during the
in solution time. I compliment the authors for incorporating the early stages of the solution; but they seem to increase the probability
new technique into existing Newton power flow programs. of solving other cases that would otherwise diverge or oscillate due to
the imposition of excessive variable corrections. Naturally the en-
countering of (or backing off from) tap limits requires the use of
transformer-type switching analogous to the case for generators,
where reactive power limits are involved.
We have chosen to handle the regulation priority question (where
Norris M. Peterson and W. Scott Meyer: The authors wish to thank both a generator and an LTC transformer regulate the same node
the discussers for their constructive comments and interest. voltage magnitude) a little differently from the way suggested by the
Mr. Subramanian's suggestion of using the proposed procedure discussers. Although we assume that a generator will be given first
to maintain node voltage or power flows within certain predeter- priority to regulate the node voltage magnitude, we have chosen to
mined limits would require a reversal of the type switching and hold the associated LTC transformer tap constant so long as gen-
priority schedules usually employed. The LTC transformer and erator reactive limits are not reached (rather than constrain the
phase-shifter taps would then remain fixed until voltage or power reactive power flow). The LTC transformer tap would only become a
flow inequality constraints were violated, at which point the proper variable if and when the generator reaches its reactive limit.
control equations would be substituted or added to adjust the taps Mr. Tinney and Mr. Powell are absolutely correct concerning the
to maintain the appropriate limits. It must be noted that such a ordering of the phase-shifter equations; this recognition, included in
scheme permits a wide range of solutions for a given power flow [6], is important for maximum elimination efficiency. The suggested
problem and appears to be unnecessary due to the rapid convergence order is clearly preferable to that shown in (5a), where fill-in during
of the proposed new method. the elimination generally will occur.
The proposed method can be used in conjunction with minimiza- It has been found necessary to develop logic for the NSP program
tion or optimization techniques, provided that the voltage and/or to handle special system configurations such as series and parallel
power flow regulation thereby provided is indeed a constraint to the LTC transformer connections. The series condition occurs when two
problem. For such cases, the proposed Newton power flow solutions or more LTC transformers are connected in series and one LTC
fit naturally into gradient optimization procedures [5]. But if such transformer regulates the nonregulated terminal of another LTC
regulation is not desired, the proposed adjustment procedure is of transformer. The parallel condition occurs when a node is regulated
course inapplicable. The LTC regulation of node voltage magnitude by two or more LTC transformers that are connected to different
will not, in general, produce the minimum possible system loss, nodes. The inclusion of such features makes it possible to handle
for example. The same would generally be true of constraining the general topology.
real power flow through phase shifters, which is generally not A matter which we feel requires investigation is the area of remote
compatible with general economic dispatch. control by the proposed method (i.e., the control of a line flow or a
A question was also raised by Mr. Subramanian about the com- sum of line flows by a remote phase shifter, or the control of a node
parative rates of convergence during early stages of the solution. voltage magnitude by a remote transformer). Although there is no
The old method is similar to that described in [4], where the problem theoretical reason why remote regulation by the proposed method
is treated as a fixed system (LTC taps fixed) until after the third should not be possible, we have not investigated its practicality and
iteration. It is thus only from the fourth iteration on that the old feel that three areas may cause difficulty.
method is actually solving the problem that was posed, and com- 1) The inclusion of remote regulation requires that the renumbering
parisons must be made for this portion of the solution process. It strategy be modified to insure that a nonzero diagonal exists (follow-
should be remembered that the computational effort per iteration ing elimination to the left of the diagonal). For the case of remote
for the new and old methods is nearly identical. voltage regulation by a transformer, nodes forming a path between
Mr. Subramanian's final point concerns the removal of phase the remotely controlled node and the controlling transformer, plus
shifters. If voltage magnitude is maintained constant at one terminal the transformer terminal that terminates this path, must all be
this could indeed be accomplished by opening the element across the eliminated before the remotely controlled node. Analogous con-
ideal phase shifter and inserting two generators having opposite siderations apply to the phase-shifter case. The development of
injected power outputs. The reactive generation requirement could efficient program logic for the general case is simply stated in words,
be calculated to maintain the voltage magnitude at the voltage- but it appears to be quite involved.
controlled node. But such elimination is not completely general in 2) The altered node numbering (as above) will degrade the
that it requires that a phase shifter control both the real power flow solution efficiency. Inclusion of remote control by phase shifters
and either the reactive flow or the voltage magnitude at the terminal does not allow the elimination order as outlined by Mr. Tinney and
node. Further, such an approach would not significantly affect Mr. Powell, which is most efficient; the general case is similar to
problem storage requirements (see comments by Mr. Tinney and that associated with area-interchange equations [1]. The use of
Mr. Powell), and would not in general converge any faster than the transformers to remotely regulate voltage magnitude adds two
proposed scheme. Remote regulation also would not be possible additional nonzero blocks to the original Jacobian matrix for each
using the suggested approach. such transformer; remote regulation in both cases thus results in an
The authors are especially grateful to Mr. Tinney and Mr. Powell asymmetrical nonzero block pattern for the Jacobian matrix. The
for their very relevant comments. We are gratified to find that inclusion of many remote controls might significantly degrade the
the Bonneville Power Administration has experienced solution time problem sparsity and the efficiency of the overall algorithm.
reductions similar to those stated in the paper and confirmed by our 3) Remote regulation should in general require changes in the
experimental and production runs. The authors concur that tap control variable larger than would be required for local regulation.
limits and the other points mentioned must be efficiently handled in This might increase convergence difficulties normally associated
order to make the method practical for production programs; these with constraint limits.
points are considered in the following paragraphs.
Certainly the first and most important consideration is that
of constraint limits. As the discussers state, Newton's method cannot REFERENCES
directly take limits into account; if large tap changes At occur during
the back substitution, it is possible for the resulting transformer [5] H. W. Dommel and W. F. Tinney, "Optimal power flow solu-
taps to greatly exceed their predefined limits, thereby resulting in tions," IEEE Trans. Power App. Syst., vol. PAS-87, pp. 1866-
large AP and AQ residuals when the tap limits are actually imposed. 1876, October 1968.
[6] H. W. Dommel, W. F. Tinney, and W. L. Powell, "Further
developments in Newton's method for power system applica-
tions," Paper 70 CP 161-PWR, presented at the IEEE Winter
Manuscript received March 30, 1970. Power Meeting, New York, N. Y., January 25-30, 1970.