Exercises Session 5
Exercises Session 5
ORINOCO S.L. manufactures and sells two products: CIF and FOB to which the
following standards apply:
The indirect manufacturing costs are standardized as 175% of total Direct Labour.
At the end of the period the closing stock comprised the items below:
The total cost of Direct Labour was 2,738,125 € and was priced the same for all
operations,(Standard cost =€ 35 per hour).
Bearing in mind that everything manufactured was sold and that the sale prices
were:
1. Produce separate information sheets on the standard cost of the CIF and
FOB products.
The Eastern division is managed by Richard Hill. The division only makes one
product, the Beta. Budgeted Beta production for May was 8000 units, although
actual production was 9500 units.
In order to prepare the standard cost report for May, you have asked a member
of your staff to obtain standard and actual cost details for the month of May.
This information is reproduced below:
Task 1
(a) Calculate the following:
(i) ) the material price variance;
(ii) the material usage variance;
(iii) ur rate variance;
(iv) our efficiency variance (sometimes called the utilization
variance); (b)
After Richard Hill has received your standard costing statement, you visit him to
discuss the variances and their implications. Richard, however, raises a number
of queries with you. He makes the following points:
• An index measuring material prices stood at 247.2 for May but at 240.0
when the standard for the material price was set.
• The Eastern division is budgeted to run at its normal capacity of 8000
units of production per month, but during May it had to manufacture an
additional 1500 Betas to meet a special order agreed at short notice by
Melton’s sales director.
• Because of the short notice, the normal supplier of the raw material was
unable to meet the extra demand and so additional materials had to be
acquired from another supplier at a price per litre of £22.
• This extra material was not up to the normal specification, resulting in
20% of the special purchase being scrapped prior to being issued to
production.
• The work force could only produce the special order on time by working
overtime on the 1500 Betas at a 50% premium.
Task 2
(a) Calculate the amounts within the material price variance, the material
usage variance and the labour rate variance which arise from producing
the special order.
(b) (i) Estimate the revised standard price for materials based on the change
in the material price index.
(ii)For the 8000 units of normal production, use your answer in (b) (i) to
estimate how much of the price variance calculated in Task 1 is caused
by the general change in prices.
(c) Using your answers to parts (a) and (b) of this task, prepare a revised
standard costing statement. The revised statement should subdivide the
variances prepared in Task 1 into those elements controllable by Richard
Hill and those elements caused by factors outside his divisional control.
(d) Write a brief note to Richard Hill justifying your treatment of the elements
you believe are outside his control and suggesting what action should be
taken by the company.
5.3 Reconciliation of actual and budgeted profit (including overhead
variances)
A local restaurant has been examining the profitability of its set menu. At the
beginning of the year the selling price was based on the following predicted
costs:
(£)
Starter Soup of the day
100 grams of mushrooms 0.30
@ £3.00 per kg
Cream and other ingredients 0.20
Main course Roast beef
Beef 0.10 kg 1.50
@ £15.00 per kg
Potatoes 0.2 kg 0.05
@ £0.25 per kg
Vegetables 0.3 kg 0.27
@ £0.90 per kg
Other ingredients and
accompaniments 0.23
Dessert Fresh tropical fruit salad
Fresh fruit 0.15 kg 0.45
@ £3.00 per kg
The selling price was set at £7.50, which produced an overall gross profit of
60%.
During October the number of set menus sold was 860 instead of the 750
budgeted: this increase was achieved by reducing the selling price to £7.00.
During the same period an analysis of the direct costs incurred showed:
(£)
90 kg of mushrooms 300
Cream and other ingredients 160
70 kg of beef 1148
180 kg of potatoes 40
270 kg of vegetables 250
Other ingredients and accompaniments 200
140 kg of fresh fruit 450