Gantt Chart With Layout Table
Gantt Chart With Layout Table
GH-01 Guest House Project G+1 376 11-Feb-22 25-Apr-23 25-Apr-23, GH-01 Guest Hou
GH-01.1.2 Excavation & Earth Work 91 11-Feb-22 27-May-22 27-May-22, GH-01.1.2 Excavation & Earth Work
A1002 Clearing the site to remove top soil and other rubbish materials to an average depth of 200mm. 1 11-Feb-22 11-Feb-22 Clearing the site to remove top soil and other rubbish materials to an average depth of 200mm.
A1003 Bulk excavation of ordinary soil to a depth not exceeding 1500mm below existing ground surface. 1 12-Feb-22 12-Feb-22 Bulk excavation of ordinary soil to a depth not exceeding 1500mm below existing ground surface.
A1004 Pit excavation in ordinary soil to a depth not exceeding 1500mm from reduced ground level 2 14-Feb-22 15-Feb-22 Pit excavation in ordinary soil to a depth not exceeding 1500mm from reduced ground level
A1005 Ditto over 1500 mm but not exceeding 3000mm. 2 16-Feb-22 17-Feb-22 Ditto over 1500 mm but not exceeding 3000mm.
A1006 Trench excavation of ordinary soil to masonry wall starting from reduced bulk level to a depth not exceeding 1500mm. 2 18-Feb-22 19-Feb-22 Trench excavation of ordinary soil to masonry wall starting from reduced bulk level to a depth not exceeding 1500mm.
A1007 Backfill around footing and foundation columns with selected material from outside, well rammed in layers of 200mm thick 2 21-May-22 23-May-22 Backfill around footing and foundation columns with selected material from outside, well rammed in layers of 200
A1008 Backfill under hardcore with selected material from outside, well rammed in layers of 200mm thick and compacted at dry d 2 24-May-22 25-May-22 Backfill under hardcore with selected material from outside, well rammed in layers of 200mm thick and compact
A1009 Cart away excavated material up to 10Km from the site 2 21-Feb-22 22-Feb-22 Cart away excavated material up to 10Km from the site
A1010 250mm thick basaltic or equivalent Stone hard core well rolled, consolidated and blinded with crushed stone. 2 26-May-22 27-May-22 250mm thick basaltic or equivalent Stone hard core well rolled, consolidated and blinded with crushed stone.
GH-01.1.3 Concrete Work 111 11-Feb-22 20-Jun-22 20-Jun-22, GH-01.1.3 Concrete Work
GH-01.1.3.1 Lean Concrete [50mm thick] 75 11-Feb-22 09-May-22 09-May-22, GH-01.1.3.1 Lean Concrete [50mm thick]
A1014 a. Under Stone masonry 5 04-May-22 09-May-22 a. Under Stone masonry
A1015 b. Under footing pad 5 01-Mar-22 05-Mar-22 b. Under footing pad
A1016 c. Under basement beams 5 11-Feb-22 16-Feb-22 c. Under basement beams
GH-01.1.3.2 Reinforced Concrete 86 12-Mar-22 20-Jun-22 20-Jun-22, GH-01.1.3.2 Reinforced Concrete
A1019 a. For Isolated footing pads 5 12-Mar-22 17-Mar-22 a. For Isolated footing pads
A1021 c. For basement beams 5 05-Apr-22 09-Apr-22 c. For basement beams
A1022 d. For 100mm thick basement Floor slabs 5 11-Apr-22 15-Apr-22 d. For 100mm thick basement Floor slabs
A1023 e. For basement columns 5 28-Apr-22 03-May-22 e. For basement columns
A1024 f. For 150mm thick ground Floor slabs 5 09-Jun-22 14-Jun-22 f. For 150mm thick ground Floor slabs
A1026 h. In basement level retaining wall 5 28-Apr-22 03-May-22 h. In basement level retaining wall
A1020 b. For foundation columns 5 30-Mar-22 04-Apr-22 b. For foundation columns
A1025 g. In Concrete stair 5 15-Jun-22 20-Jun-22 g. In Concrete stair
GH-01.1.3.3 Formwork 86 23-Feb-22 02-Jun-22 02-Jun-22, GH-01.1.3.3 Formwork
A1029 a. For Isolated footing pads 5 23-Feb-22 28-Feb-22 a. For Isolated footing pads
A1031 c. For basement beams 5 24-Mar-22 29-Mar-22 c. For basement beams
A1032 d. For basement columns 5 22-Apr-22 27-Apr-22 d. For basement columns
A1033 e. For 150mm thick ground Floor slabs 5 28-May-22 02-Jun-22 e. For 150mm thick ground Floor slabs
A1035 g. In basement level retaining wall 5 22-Apr-22 27-Apr-22 g. In basement level retaining wall
A1030 b. For foundation columns 5 18-Mar-22 23-Mar-22 b. For foundation columns
A1034 f. In Concrete stair 5 23-May-22 28-May-22 f. In Concrete stair
GH-01.1.3.4 Reinforcement Bar 83 07-Mar-22 10-Jun-22 10-Jun-22, GH-01.1.3.4 Reinforcement Bar
A1037 a) Footing pad rebar 2 07-Mar-22 08-Mar-22 a) Footing pad rebar
A1038 b) For basement columns 2 16-Apr-22 18-Apr-22 b) For basement columns
A1039 c) For 150mm thick ground floor slab 2 03-Jun-22 04-Jun-22 c) For 150mm thick ground floor slab
A1040 d) For basement beam 2 18-Mar-22 19-Mar-22 d) For basement beam
A1041 e) In basement level retaining wall 2 16-Apr-22 18-Apr-22 e) In basement level retaining wall
A1044 h) For 100mm thick basement floor 2 30-Mar-22 31-Mar-22 h) For 100mm thick basement floor
A1042 f) For foundation columns 2 24-Mar-22 25-Mar-22 f) For foundation columns
A1043 g) In Concrete stair 2 09-Jun-22 10-Jun-22 g) In Concrete stair
GH-01.1.4 Masonary Work 7 10-May-22 17-May-22 17-May-22, GH-01.1.4 Masonary Work
A1045 Basaltic or Equivalent stone masonry wall bedded in cement sand mortar (1:3) below ground level to a depth not exceedin 1 10-May-22 10-May-22 Basaltic or Equivalent stone masonry wall bedded in cement sand mortar (1:3) below ground level to a depth not ex
A1047 Basaltic or Equivalent stone masonry wall bedded in cement sand mortar (1:3) belowAbove ground level to a depth not ex 2 16-May-22 17-May-22 Basaltic or Equivalent stone masonry wall bedded in cement sand mortar (1:3) belowAbove ground level to a dep
GH-01.5 SUPER-STRUCTURE 306 04-May-22 25-Apr-23 25-Apr-23, GH-01.5 SUPER
Actual Level of Effort Remaining Work Milestone Page 1 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
Guest House Project G+1 Classic Schedule Layout 14-Feb-22 03:21
Activity ID Activity Name Original Duration Start Finish F M A M J J A S O N D J F M A M
2 01 20 2 01 20 1 20 12 11 3 12 01 20 1 30 22 11 0 12 01 2 11 00 23
A1053 a. In Elevation Columns 2 27-Jun-22 28-Jun-22 a. In Elevation Columns
A1055 c. In 150mm concrete Slab 5 26-Jul-22 30-Jul-22 c. In 150mm concrete Slab
A1056 d. Stair Case 2 18-Aug-22 19-Aug-22 d. Stair Case
A1054 b. In Intermediate Floor beams 2 26-Jul-22 27-Jul-22 b. In Intermediate Floor beams
GH-01.5.6.2 Formwork 32 21-Jun-22 27-Jul-22 27-Jul-22, GH-01.5.6.2 Formwork
A1058 a. In Elevation Columns 5 21-Jun-22 25-Jun-22 a. In Elevation Columns
A1059 b. In Intermediate Floor beams 1 02-Jul-22 02-Jul-22 b. In Intermediate Floor beams
A1060 c. In 150mm concrete Slab 5 14-Jul-22 19-Jul-22 c. In 150mm concrete Slab
A1061 d. Stair Case 2 26-Jul-22 27-Jul-22 d. Stair Case
GH-01.5.6.3 Reinforcement Bar 45 15-Jun-22 05-Aug-22 05-Aug-22, GH-01.5.6.3 Reinforcement Bar
A1063 a) Ø 8mm deformed bars 5 20-Jul-22 25-Jul-22 a) Ø 8mm deformed bars
A1064 b) Ø 10mm deformed bars 2 15-Jun-22 16-Jun-22 b) Ø 10mm deformed bars
A1065 c) Ø 12mm deformed bars 5 15-Jun-22 20-Jun-22 c) Ø 12mm deformed bars
A1068 f) Ø 20mm deformed bars 1 08-Jul-22 08-Jul-22 f) Ø 20mm deformed bars
A1066 d) Ø 14mm deformed bars 1 01-Aug-22 01-Aug-22 d) Ø 14mm deformed bars
A1067 e) Ø 16mm deformed bars 5 01-Aug-22 05-Aug-22 e) Ø 16mm deformed bars
GH-01.5.4 Water Proof work 78 04-May-22 02-Aug-22 02-Aug-22, GH-01.5.4 Water Proof work
A1072 Supply and apply APP modified 4mm thick bituminous membrane system with granular / slated finish to the roof concrete co 2 01-Aug-22 02-Aug-22 Supply and apply APP modified 4mm thick bituminous membrane system with granular / slated
A1071 Prepare the basement external RC wall for water proofing membrane application by rectifying the rugged face of the wall 5 04-May-22 09-May-22 Prepare the basement external RC wall for water proofing membrane application by rectifying the rugged face of the
A1073 Construct a shield wall for the applied basement shear wall membrane out of 10cm thick HCB block at the back of the memb 1 10-May-22 10-May-22 Construct a shield wall for the applied basement shear wall membrane out of 10cm thick HCB block at the back of th
GH-01.5.7 Block Work 15 06-Aug-22 23-Aug-22 23-Aug-22, GH-01.5.7 Block Work
A1082 200 mm thick class B HCB wall bedded in cement sand mortar mix(1:3) 8 06-Aug-22 15-Aug-22 200 mm thick class B HCB wall bedded in cement sand mortar mix(1:3)
A1083 150 mm thick class B HCB wall bedded in cement sand mortar mix(1:3) 10 12-Aug-22 23-Aug-22 150 mm thick class B HCB wall bedded in cement sand mortar mix(1:3)
GH-01.5.8 Carpentery & Joinery 21 22-Mar-23 14-Apr-23 14-Apr-23, GH-01.5.8 Carpente
GH-01.5.8.1 Wooden doors of 40mm thick both sides covered with 4mm thick kerero plyeood 11 22-Mar-23 03-Apr-23 03-Apr-23, GH-01.5.8.1 Wooden d
A1087 a) D1 size [900x2100] mm 1 22-Mar-23 22-Mar-23 a) D1 size [900x2100] mm
A1088 b) D2 size [950x2100] mm 1 28-Mar-23 28-Mar-23 b) D2 size [950x2100] mm
A1089 c) D3 size [1200x2100] mm 1 03-Apr-23 03-Apr-23 c) D3 size [1200x2100] mm
GH-01.5.8.2 Ditto as [NG-01.5.8.1] 6 08-Apr-23 14-Apr-23 14-Apr-23, GH-01.5.8.2 Ditto as
A1091 a) D4 size [900x2100] mm 1 08-Apr-23 08-Apr-23 a) D4 size [900x2100] mm
A1092 b) D5 size [950x2100] mm 1 14-Apr-23 14-Apr-23 b) D5 size [950x2100] mm
GH-01.5.9 Aluminum Work 46 19-Nov-22 11-Jan-23 11-Jan-23, GH-01.5.9 Aluminum Work
A1097 1) W1 Size [2500x1800] 1 19-Nov-22 19-Nov-22 1) W1 Size [2500x1800]
A1098 2) W2 Size [3600x3200] 1 25-Nov-22 25-Nov-22 2) W2 Size [3600x3200]
A1099 3) W3 Size [2600x4500] 1 01-Dec-22 01-Dec-22 3) W3 Size [2600x4500]
A1100 4) W4 Size [700x100] 1 07-Dec-22 07-Dec-22 4) W4 Size [700x100]
A1101 5) DW1 Size [900x2100] 1 13-Dec-22 13-Dec-22 5) DW1 Size [900x2100]
A1102 6) DW2 Size [1200x2100] 1 19-Dec-22 19-Dec-22 6) DW2 Size [1200x2100]
A1103 Supply and fix Stair case hand rail made of aluminum profiles consisting of baluster and hand rail as per shown in detai 1 11-Jan-23 11-Jan-23 Supply and fix Stair case hand rail made of aluminum
GH-01.5.10 Finishing 122 18-Aug-22 06-Jan-23 06-Jan-23, GH-01.5.10 Finishing
A1113 PVC flooring 4 28-Sep-22 01-Oct-22 PVC flooring
A1114 15x15x6mm thick ceramic floor tile for toilet area 5 04-Oct-22 08-Oct-22 15x15x6mm thick ceramic floor tile for toilet area
A1115 400x400x8mm non slippery colored ceramic floor tile 5 10-Oct-22 14-Oct-22 400x400x8mm non slippery colored ceramic floor tile
A1116 400x400x8mm thick perque tile 5 15-Oct-22 20-Oct-22 400x400x8mm thick perque tile
A1121 100x8mm perque skirting 2 21-Oct-22 22-Oct-22 100x8mm perque skirting
A1122 100x20mm thick marble skirting 5 27-Oct-22 01-Nov-22 100x20mm thick marble skirting
A1123 100x20mm thick ceramic skirting 2 02-Nov-22 03-Nov-22 100x20mm thick ceramic skirting
A1124 5mm cement screed 5 08-Nov-22 12-Nov-22 5mm cement screed
A1125 333x30mm window sill 2 14-Nov-22 15-Nov-22 333x30mm window sill
GH-01.5.10.2 Plastering 35 18-Aug-22 27-Sep-22 27-Sep-22, GH-01.5.10.2 Plastering
A1106 two coats of External HCB wall surface 5 18-Aug-22 23-Aug-22 two coats of External HCB wall surface
Actual Level of Effort Remaining Work Milestone Page 2 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
Guest House Project G+1 Classic Schedule Layout 14-Feb-22 03:21
Activity ID Activity Name Original Duration Start Finish F M A M J J A S O N D J F M A M
2 01 20 2 01 20 1 20 12 11 3 12 01 20 1 30 22 11 0 12 01 2 11 00 23
A1107 Ditto as item 5.1 but for external column and beams 6 24-Aug-22 30-Aug-22 Ditto as item 5.1 but for external column and beams
A1108 Three coats of cement plaster to internal wall suraface 5 30-Aug-22 03-Sep-22 Three coats of cement plaster to internal wall suraface
A1109 two coats of plaster to internal column and beams 5 05-Sep-22 09-Sep-22 two coats of plaster to internal column and beams
A1110 Ditto as item 5.4 but for bottom side of slab 5 10-Sep-22 15-Sep-22 Ditto as item 5.4 but for bottom side of slab
A1111 Ditto as item 5.4 but for concrete stair case 4 16-Sep-22 20-Sep-22 Ditto as item 5.4 but for concrete stair case
A1112 Ditto as item 5.4 but for retaining wall 5 22-Sep-22 27-Sep-22 Ditto as item 5.4 but for retaining wall
GH-01.5.10.1 Wolega Marble Tile 12 24-Dec-22 06-Jan-23 06-Jan-23, GH-01.5.10.1 Wolega Marble Tile
A1118 a) 300x300 for landing 2 24-Dec-22 26-Dec-22 a) 300x300 for landing
A1119 b) 300x30mm thick tread 2 30-Dec-22 31-Dec-22 b) 300x30mm thick tread
A1120 c) 160x20mm thick riser 2 05-Jan-23 06-Jan-23 c) 160x20mm thick riser
GH-01.5.3 Glazing 5 20-Apr-23 25-Apr-23 25-Apr-23, GH-01.5.3 Glazin
A1076 Supply and fix approved type 4mm thick clear glass as per the architectural drawing for the ground floor. Price shall in 5 20-Apr-23 25-Apr-23 Supply and fix approved type
GH-01.5.11 Painting 85 17-Jan-23 25-Apr-23 25-Apr-23, GH-01.5.11 Paint
A1128 Apply three coats of Quartz paint to external plastered wall surfaces. 4 17-Jan-23 20-Jan-23 Apply three coats of Quartz paint to external plastere
A1129 Apply three coats of plastic emulsion paint to internal plastered wall surfaces. 5 23-Jan-23 27-Jan-23 Apply three coats of plastic emulsion paint to intern
A1130 Ditto but column and beam surface 2 28-Jan-23 30-Jan-23 Ditto but column and beam surface
A1131 Ditto but bottom slab 4 03-Feb-23 07-Feb-23 Ditto but bottom slab
A1132 Ditto but concrete stair 2 09-Feb-23 10-Feb-23 Ditto but concrete stair
A1133 Ditto but concrete retaining wall 5 15-Feb-23 20-Feb-23 Ditto but concrete retaining wall
GH-01.5.11.1 Gypsum 17 21-Feb-23 11-Mar-23 11-Mar-23, GH-01.5.11.1 Gypsum
A1135 gypsum to all internal wall surface 4 21-Feb-23 24-Feb-23 gypsum to all internal wall surface
A1136 gypsum to all internal wall surface, column, beam suface 3 27-Feb-23 01-Mar-23 gypsum to all internal wall surface, column
A1137 Ditto but to bottom slab 5 04-Mar-23 09-Mar-23 Ditto but to bottom slab
A1138 Ditto but stair case 2 10-Mar-23 11-Mar-23 Ditto but stair case
GH-01.5.11.2 Gypsum Decoration 35 16-Mar-23 25-Apr-23 25-Apr-23, GH-01.5.11.2 Gyp
A1140 Living and dining room 5 16-Mar-23 21-Mar-23 Living and dining room
A1150 End Of Project 0 25-Apr-23 End Of Project,
Actual Level of Effort Remaining Work Milestone Page 3 of 3 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation