Performance of Rapid Impact Compaction As A Middle-Deep Ground Improvement Technique
Performance of Rapid Impact Compaction As A Middle-Deep Ground Improvement Technique
net/publication/326264312
CITATIONS READS
2 1,972
2 authors:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Bashar Tarawneh on 09 July 2018.
Yasser Hakam
Technical and Business Development Manager, Menard Vibro Middle East, Dubai, UAE
ABSTRACT: Rapid Impact Compaction ( RIC) is a modern dynamic compaction technique mostly used to compact sandy
soils, where silt and clay contents are little. The device uses the piling hammer technology to increase the bearing
capacity and reduce the potential settlement of soils. The RIC device uses "controlled impact compaction" of the ground
using a 9-ton hammer dropped from height between 0.3 m to 1.2 m onto a 1.5 m diameter steel patent foot. To evaluate
the performance of this technique, the results of ground improvement work for a project site using RIC is presented in this
paper. In the project site, a loose to very loose fine to medium sand was encountered at a depth ranging from 1.0m to
4.0m below the ground level. Cone Penetration Tests (CPT) were carried out before and after ground improvement. It
was shown that soil was improved to a depth of about 5.0m below the ground level. CPT tip resistance was significantly
increased post ground improvement work. This study demonstrates the successful application of the RIC for middle-deep
improvement and compaction of the ground. Foundation design criteria were achieved in all site post RIC work.
1 INTRODUCTION
- 2623 -
Proceedings of the 19th International Conference on Soil Mechanics and Geotechnical Engineering, Seoul 2017
The project site is a development to construct Villas. Each Villa which is about (35,000 m2). One Cone Penetration Test (CPT)
is built on about 500 m2. In some areas of the project site, a was carried out at each villa location before the commencement
loose to very loose fine to medium sand layer is encountered at of the compaction to evaluate the soil conditions and to
a depth ranging from 1.0m to 4.0m below the ground level. determine the needed degree of compaction to meet the design
Cohesive soil was not encountered in the project area. Water criteria.
table was encountered at a depth of 0.5m to 2.0m below the
ground level. Preliminary compaction trials are crucial to any extensive
RIC works to provide the designer with the necessary
The designer proposed the bottom of footings (B.O.F) to be information to allow refinement of the compaction procedure.
constructed at 1.0m below the ground level. The design criteria, Two Villa locations were used as a trial area to establish a
for the foundation, are to use square footing (2.5m by 2.5 m), compaction design criteria. Moreover, as the main RIC works
200 kPa bearing pressure, and settlement shall not to exceed are proceeding, ongoing monitoring and testing is necessary to
25mm in order to minimize differential settlement. ensure that the appropriate amount of energy is being
It’s proposed to use Schmertmann (1978) method to carry transferred to the soil and that performance requirements are
out the settlement calculations. The bearing capacity and being met. The compaction trial is important for the evaluation
settlement criteria could not be met based on the existing soil of ground response. The optimal number of blows per pass is
conditions. Therefore, a ground improvement is needed to meet typically taken as the value beyond which continued blows
the foundation design criteria. produce negligible further penetration of the compaction foot.
Considering the soil profile of loose to very loose fine to The process of compaction started by using a 6m grid then
medium sand, three soil improvement techniques were compacting a 3m grid in order to allow for deep improvement.
considered namely: Vibrocompaction, Dynamic Compaction, Figure 2 shows the sequence of the compaction.
and Rapid Impact Compaction. Those methods were considered
because they are suitable for granular soil and available in the
local market.
- 2624 -
Technical Committee 211 / Comité technique 211
evaluated by comparing the pre and post CPTs and calculating less than 25mm for all project area when the size of the footing
the expected settlements. is (2.5m by 2.5m) and the bearing pressure is 200 kPa.
Following the RIC work, one CPT per villa was carried out 5 CONCLUSIONS
to provide post-treatment evaluation. The post-treatment CPTs
were advanced, near to pre-treatment CPTs, to depths of about The results of ground improvement work project presented
5.5 meters approximately two days after the RIC treatment to in this paper benefited from RIC, essentially by meeting the
allow for dissipation of pore water pressure. The corresponding foundation design criteria, reducing foundation system costs
post-treatment CPTs indicate an increase in the tip resistance and construction time. Results of the field pre and post
within these same depths. Figure 3 shows the tip resistance for improvement testing indicate improvement of soil to depths of
the pre-improvement, post 1st, 2nd, and 3rd Pass. It can be noted about to 5.0 meters below the ground level. Settlements
that the first pass energy was consumed to break the existing calculations showed that the RIC method reduced the expected
hard layer (crust) at the top while the 2nd and 3rd passes settlement. RIC is considered to have less cost and more
improved the soil. productivity when compared to other ground improvement
techniques such as Dynamic Compaction and Vibrocompaction.
It also, has less vibration effect when compared to dynamic
Tip Resistance (MPa) compaction. No known damage to nearby utilities has occurred
0.0 at the time RIC was performed.
0.5
6 ACKNOWLEDGEMENTS
9 REFERENCES
2.0 Braithwaite E.J. and Du Preez R.W. 1997. Rapid impact compaction in
southern Africa. Proceedings of the Conference on Geology for
Engineering, Urban Planning and the Environment. South African
2.5 Institute of Engineering Geologists, 13-14 November 1997.
5.5
0 10 20 30
1st Pass 2nd
3rd Pass Pre-Improvement
- 2625 -
- 2626 -