Saudi Aramco Typical Inspection Plan

This document is a typical inspection plan from Saudi Aramco for earthwork during construction projects. It outlines 4 phases of work: document review, material receiving, installation, and pre-commissioning. For each work item, it specifies the quality procedures and records, assigns inspection responsibilities to Saudi Aramco and contractors, and provides remarks about required oversight levels. The plan requires close involvement from Saudi Aramco inspectors for the initial occurrences of each work item to oversee contractors' performance before potentially adjusting participation levels.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
66 views2 pages

Saudi Aramco Typical Inspection Plan

This document is a typical inspection plan from Saudi Aramco for earthwork during construction projects. It outlines 4 phases of work: document review, material receiving, installation, and pre-commissioning. For each work item, it specifies the quality procedures and records, assigns inspection responsibilities to Saudi Aramco and contractors, and provides remarks about required oversight levels. The plan requires close involvement from Saudi Aramco inspectors for the initial occurrences of each work item to oversee contractors' performance before potentially adjusting participation levels.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

SAUDI ARAMCO ID/PID FORM (Standards Cutoff -March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Earthwork - Site Preparation, Excavation and Backfill During Construction. SATIP-A-114-01 30-Apr-13 CIVIL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Contractor - "RH" of Documents and "H" for Material


Sampling and Testing.
Soil Sampling, Testing and Review of Test SAIC-A- S.ARAMCO - "RH" of Documents and "H" for Material
1.1
Reports
SAIC-A-1001
1001 RH/ H RH/ H Sampling and Testing for first 2 occurences and once
every 5 occurences thereafter on Mega Projects. "W" for
other occurences and for other Projects.

2.0 MATERIAL RECEIVING

S. ARAMCO - Witness delivery of fill, select fill and marl


Fill, Select Fill and Marl Cap Materials SAIC-A-
2.1
Receiving Inspection
SAIC-A-1002
1002 I S cap materials for the first 2 delivery days, and once every
5 delivery days thereafter.

3.0 INSTALLATION

Soil Protection and Control, Drainage and SAIC-A- S. ARAMCO - Witness 2 occurences, and once every 5
3.1
De-watering Inspection
SAIC-A-1003
1003 I S occurrences thereafter.

SAIC-A- S. ARAMCO - Witness 2 occurences, and once every 5


3.2 Fill Placement and Compaction Inspection SAIC-A-1004
1004 I S occurrences thereafter.

SAIC-A-
3.3 Compaction Testing SAIC-A-1005
1005 I W

SAIC-A-
3.4 Final Fill Inspection SAIC-A-1006
1006 I W

4.0 PRE-COMMISSIONING

4.1 Not Applicable

Page 1 of 2
SAUDI ARAMCO ID/PID FORM (Standards Cutoff -March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Earthwork - Site Preparation, Excavation and Backfill During Construction. SATIP-A-114-01 30-Apr-13 CIVIL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1 levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative
3 is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
4
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

Page 2 of 2