PRC-024-3 - Frequency and Voltage Protection Settings For Generating Resources
PRC-024-3 - Frequency and Voltage Protection Settings For Generating Resources
A. Introduction
1. Title: Frequency and Voltage Protection Settings for Generating Resources
2. Number: PRC-024-3
3. Purpose: To set protection such that generating resource(s) remain connected
during defined frequency and voltage excursions in support of the Bulk Electric System
(BES).
4. Applicability:
4.1. Functional Entities:
4.1.1 Generator Owners that apply protection listed in Section 4.2.1.
4.1.2 Transmission Owners (in the Quebec Interconnection only) that own a BES
generator step-up (GSU) transformer or main power transformer (MPT)1
and apply protection listed in Section 4.2.1.
4.1.3 Planning Coordinators (in the Quebec Interconnection only)
4.2. Facilities2:
4.2.1 Frequency, voltage, and volts per hertz protection (whether provided by
relaying or functions within associated control systems) that respond to
electrical signals and: (i) directly trip the generating resource(s); or (ii)
provide signals to the generating resource(s) to either trip or cease injecting
current; and are applied to the following:
4.2.1.1 BES generating resource(s).
4.2.1.2 BES GSU transformer(s).
4.2.1.3 High side of the generator-connected unit auxiliary transformer3
(UAT) installed on BES generating resource(s).
4.2.1.4 Individual dispersed power producing resource(s) identified in the
BES Definition, Inclusion I4.
4.2.1.5 Elements that are designed primarily for the delivery of capacity
from the individual dispersed power producing resources
identified in the BES Definition, Inclusion I4, to the point where
those resources aggregate to greater than 75 MVA.
1
For the purpose of this standard, the MPT is the power transformer that steps up voltage from the collection system
voltage to the nominal transmission/interconnecting system voltage for dispersed power producing resources.
2
It is not required to install or activate the protections described in Facilities Section 4.2.
3
These transformers are variably referred to as station power UAT, or station service transformer(s) used to provide
overall auxiliary power to the generating resource(s). This UAT is the transformer connected on the generator bus
between the low side of the GSU and the generator terminal.
Page 1 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
4
For the purpose of this standard, the MPT is the power transformer that steps up voltage from the collection system
voltage to the nominal transmission/interconnecting system voltage for dispersed power producing resources
Page 2 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
5
Frequency, voltage, and volts per hertz protection (whether provided by relaying or functions within associated
control systems) that respond to electrical signals and: (i) directly trip the generating resource(s); or (ii) provide
signals to the generating resource(s) to either trip or cease injecting current.
Page 3 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
R3. Each Generator Owner shall document each known regulatory or equipment limitation6
that prevents an applicable generating resource(s) with frequency or voltage protection
from meeting the protection setting criteria in Requirements R1 or R2, including (but not
limited to) study results, experience from an actual event, or manufacturer’s advice.
[Violation Risk Factor: Lower] [Time Horizon: Long-term Planning]
3.1. The Generator Owner shall communicate the documented regulatory or equipment
limitation, or the removal of a previously documented regulatory or equipment
limitation, to its Planning Coordinator and Transmission Planner within 30 calendar
days of any of the following:
Identification of a regulatory or equipment limitation.
Repair of the equipment causing the limitation that removes the limitation.
Replacement of the equipment causing the limitation with equipment that
removes the limitation.
Creation or adjustment of an equipment limitation caused by consumption of
the cumulative turbine life-time frequency excursion allowance.
M3. Each Generator Owner shall have evidence that it has documented and communicated
any known regulatory or equipment limitations that resulted in an exception to
Requirements R1 or R2 in accordance with Requirement R3, such as a dated email or
letter that contains such documentation as study results, experience from an actual
event, or manufacturer’s advice.
R4. Each Generator Owner shall provide its applicable protection settings associated with
Requirements R1 and R2 to the Planning Coordinator or Transmission Planner that
models the associated generating resource(s) within 60 calendar days of receipt of a
written request for the data and within 60 calendar days of any change to those
previously requested settings unless directed by the requesting Planning Coordinator or
Transmission Planner that the reporting of protection setting changes is not required.
[Violation Risk Factor: Lower] [Time Horizon: Operations Planning]
M4. Each Generator Owner shall have evidence that it communicated applicable protection
settings in accordance with Requirement R4, such as dated e-mails, correspondence or
other evidence and copies of any requests it has received for that information.
6
Excludes limitations caused by the setting capability of the frequency, voltage, and volts per hertz protective relays
for the generating resource(s). This does not exclude limitations originating in the equipment protected by the relay.
This also does not exclude limitations of frequency, voltage, and volts per hertz protection embedded in control
systems.
Page 4 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
C. Compliance
1. Compliance Monitoring Process
1.1. Compliance Enforcement Authority: “Compliance Enforcement Authority” means
NERC or the Regional Entity, or any entity as otherwise designated by an Applicable
Governmental Authority, in their respective roles of monitoring and/or enforcing
compliance with mandatory and enforceable Reliability Standards in their
respective jurisdictions.
1.2. Evidence Retention: The following evidence retention period(s) identify the period
of time an entity is required to retain specific evidence to demonstrate compliance.
For instances where the evidence retention period specified below is shorter than
the time since the last audit, the Compliance Enforcement Authority may ask an
entity to provide other evidence to show that it was compliant for the full-time
period since the last audit.
The applicable entity shall keep data or evidence to show compliance as identified
below unless directed by its Compliance Enforcement Authority to retain specific
evidence for a longer period of time as part of an investigation.
The Generator Owner shall keep data or evidence Requirement R1 through
R4; for 3 years or until the next audit, whichever is longer.
If a Generator Owner is found non-compliant, the Generator Owner or
Transmission Owner shall keep information related to the non-compliance
until mitigation is complete and approved for the time period specified
above, whichever is longer.
1.3. Compliance Monitoring and Assessment Program: As defined in the NERC Rules of
Procedure, “Compliance Monitoring and Enforcement Program” refers to the
identification of the processes that will be used to evaluate data or information for
the purpose of assessing performance or outcomes with the associated Reliability
Standard.
Page 5 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
days of identifying the to 90 calendar days of days but less than or documented limitation to
limitation. identifying the limitation. equal to 120 calendar its Planning Coordinator
days of identifying the and Transmission Planner
limitation. within 120 calendar days of
identifying the limitation.
R4. The Generator Owner The Generator Owner The Generator Owner The Generator Owner failed
provided its protection provided its protection provided its protection to provide its protection
settings more than 60 settings more than 90 settings more than 120 settings within 150 calendar
calendar days but less than or calendar days but less than calendar days but less days of any change to those
equal to 90 calendar days of or equal to 120 calendar than or equal to 150 settings.
any change to those settings. days of any change to calendar days of any
those settings. change to those
OR settings. OR
OR
The Generator Owner OR
provided protection settings The Generator Owner The Generator Owner failed
more than 60 calendar days provided protection The Generator Owner to provide protection
but less than or equal to 90 settings more than 90 provided protection settings within 150 calendar
calendar days of a written calendar days but less than settings more than 120 days of a written request.
request. or equal to 120 calendar calendar days but less
days of a written request. than or equal to 150
calendar days of a
written request.
Page 7 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
D. Regional Variances
D.A. Variance for the Quebec Interconnection
This Variance extends the applicability of Requirements R1, R3, and R4 to
Transmission Owners in the Quebec Interconnection that own a BES GSU or MPT
and apply protection listed in Section 4.2.1, Facilities. This Variance also replaces
Requirement R2 of the continent-wide standard in its entirety and adds a new
requirement, Requirement D.A.5., applicable to Planning Coordinators in the
Quebec Interconnection.
In Requirements R1, R3, and R4, all references to “Generator Owner” are replaced
with “Generator Owner and Transmission Owner.”
Page 8 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
7
Facilities in the strategic power plants include facilities from the generator up to and including the MPT or GSU.
Page 9 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
OR
Page 10 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
Page 11 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
E. Associated Documents
Implementation Plan
Page 12 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
Version History
Version Date Action Change Tracking
Page 13 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
Attachment 1
(Frequency No Trip Boundaries by Interconnection8)
62
Frequency (Hz)
61
60 No Trip Zone*
59
58
57
0.1 1 10 100 1000 10000
Time (Sec)
Figure 1
* The area outside the "No Trip Zone" is not a "Must Trip Zone."
Frequency (Hz) Minimum Time (Sec) Frequency (Hz) Minimum Time (sec)
≥61.8 Instantaneous9 ≤57.8 Instantaneous9
≥60.5 10(90.935-1.45713*f) ≤59.5 10(1.7373*f-100.116)
<60.5 Continuous operation > 59.5 Continuous operation
Table 1
8
The figures do not visually represent the “no trip zone” boundaries before 0.1 seconds and after 10,000 seconds.
The Frequency Boundary Data Points Table defines the entirety of the “no trip zone” boundaries.
9
Frequency is calculated over a window of time. While the frequency boundaries include the option to trip
instantaneously for frequencies outside the specified range, this calculation should occur over a time window.
Typical window/filtering lengths are three to six cycles (50 – 100 milliseconds). Instantaneous trip settings based
on instantaneously calculated frequency measurement is not permissible.
Page 14 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
61
60
No Trip Zone*
59
58
57
56
0.1 1 10 100 1000 10000
Time (Sec)
Figure 2
* The area outside the "No Trip Zone" is not a "Must Trip Zone."
Frequency (Hz) Minimum Time (Sec) Frequency (Hz) Minimum Time (sec)
≥61.7 Instantaneous9 ≤57.0 Instantaneous9
≥61.6 30 ≤57.3 0.75
≥60.6 180 ≤57.8 7.5
<60.6 Continuous operation ≤58.4 30
≤59.4 180
>59.4 Continuous operation
Table 2
Page 15 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
64
63
62
61
60 No Trip Zone*
59
58
57
56
55
0.1 1 10 100 1000 10000
Time (Sec)
Figure 3
* The area outside the "No Trip Zone" is not a "Must Trip Zone."
Frequency (Hz) Minimum Time (Sec) Frequency (Hz) Minimum Time (Sec)
>66.0 Instantaneous9 <55.5 Instantaneous9
≥63.0 5 ≤56.5 0.35
≥61.5 90 ≤57.0 2
≥60.6 660 ≤57.5 10
<60.6 Continuous operation ≤58.5 90
≤59.4 660
Table 3
Page 16 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
62
Frequency (Hz)
61
60
No Trip Zone*
59
58
57
0.1 1 10 100 1000 10000
Time (Sec)
Figure 4
* The area outside the "No Trip Zone" is not a "Must Trip Zone."
Frequency (Hz) Minimum Time (Sec) Frequency (Hz) Minimum Time (sec)
Table 4
Page 17 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
PRC-024 — Attachment 2
(Voltage No-Trip Boundaries – Eastern, Western, and ERCOT Interconnections)
0.90
0.85 No Trip Zone*
0.80
0.75
0.70
0.65
0.60
0.55
0.50
0.45
0.40
0.35
0.30
0.25
0.20
0.15
0.10
0.05
0.00
0 0.5 1 1.5 2 2.5 3 3.5 4
Time (sec)
High Voltage Duration Low Voltage Duration
10
Figure 1
* The area outside the "No Trip Zone" is not a "Must Trip Zone."
Voltage (pu) Minimum Time (sec) Voltage (pu) Minimum Time (sec)
≥1.200 0.00 <0.45 0.15
≥1.175 0.20 <0.65 0.30
≥1.15 0.50 <0.75 2.00
≥1.10 1.00 <0.90 3.00
<1.10 4.00 ≥ 0.90 4.00
Table 1
10
Voltage at the high-side of the GSU or MPT.
Page 18 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
If using a steady state calculation or dynamic simulation, use the following conditions when
evaluating protection settings:
a. The most probable real and reactive loading conditions for the unit under study.
b. All installed generating plant reactive support (e.g., static VAR compensators,
synchronous condensers, capacitors) equipment is available and operating normally.
c. Account for the actual tap settings of transformers between the generator terminals
and the high side of the GSU/MPT.
d. For dynamic simulations, the automatic voltage regulator is in automatic voltage control
mode with associated limiters in service.
Page 19 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
PRC-024— Attachment 2a
(Voltage No-Trip Boundaries – Quebec Interconnection)
1.4
Positive-sequence Voltage (per unit)
1.25
1.20
1.15
1.10
1.0
"No Trip Zone" *
0.90
0.85
0.75
0.25
0
2.5
0 0.1 0.5 1 2 3 4 5 30 300
0.15
0.033 Time (sec)
Low Voltage/High Voltage Duration - All Power Plants
Low Voltage Duration – Inverter-Based Resources
High Voltage Duration - Strategic Power Plants
Figure 1
* The area outside the "No Trip Zone" is not a "Must Trip Zone."
Page 20 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
Voltage (pu) Minimum Time (sec) Voltage (pu) Minimum Time (sec)
--- --- >1.50 0.033
>1.40 0.033 >1.40 0.10
>1.25 0.10 >1.25 2.50
>1.20 2.00 >1.20 5.00
>1.15 30 >1.15 30
>1.10 300 >1.10 300
≤1.10 continuous ≤1.10 continuous
Table 1
Voltage (pu) Minimum Time (sec) Voltage (pu) Minimum Time (sec)
<0.25 0.15 <0.25 3.4*V(pu)+0.15
<0.75 1.00 <0.75 1.00
<0.85 2.00 <0.85 2.00
<0.90 30 <0.90 30
≥0.90 continuous ≥0.90 continuous
Table 2
Page 21 of 22
PRC-024-3 —Frequency and Voltage Protection Settings for Generating Resources
If using a steady state calculation or dynamic simulation, use the following conditions when
evaluating protection settings:
a. The most probable real and reactive loading conditions for the unit under study.
b. All installed generating plant reactive support (e.g., static VAR compensators, synchronous
condensers, capacitors) equipment is available and operating normally.
c. Account for the actual tap settings of transformers between the generator terminals and
the high side of the GSU/MPT.
d. For dynamic simulations, the automatic voltage regulator is in automatic voltage control
mode with associated limiters in service.
Page 22 of 22