Sample Work Schedule

This document outlines the schedule for a building construction project with 41 activities from start to finish. It lists each activity along with the start and finish days, activity duration in days, and project duration in days. The project is scheduled to be completed in 216 days, with activities related to slab work, brick work, plastering, plumbing, electrical work, flooring, painting and other finishing works planned over that time period.

Uploaded by

Kamal Rao
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
915 views

Sample Work Schedule

This document outlines the schedule for a building construction project with 41 activities from start to finish. It lists each activity along with the start and finish days, activity duration in days, and project duration in days. The project is scheduled to be completed in 216 days, with activities related to slab work, brick work, plastering, plumbing, electrical work, flooring, painting and other finishing works planned over that time period.

Uploaded by

Kamal Rao
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Date: 05/12/2021

To,
Mr. ________
Site: ________, Aurangabad.
Sub: building construction work schedule.

SR.N START FINISH ACTIVITY PROJECT


DESCRIPTION OF ITEM
O. DAY DAY DAYS DAYS
1 Site mobilization 1 4 4 4
2 Footing concreting 5 14 10 14
3 Plinth level PCC 14 43 30 43
4 Mezzanine slab 44 58 15 58
5 Ground floor slab 59 88 30 88
6 Ground floor brick work 72 81 10
7 Internal plaster toilets-Ground floor 82 85 4
8 Granite door frames & window frames-Ground floor 85 95 11 95
9 1st floor slab 89 118 30 118
10 Ground floor electrical piping work 91 95 5
11 Internal plaster-Ground floor 96 105 10
12 Toilets concealed plumbing piping-Ground floor 96 102 7
13 Mezzanine floor brick work 102 116 15 116
14 Waterproofing with testing -toilets-Ground floor 103 117 15 117
15 Wall tiles-Ground floor toilets 118 127 10 127
16 Staircase Headroom slab 119 125 7
17 Granite door frames & window frames-Mezz floor 120 126 7
18 Mezzanine floor electrical piping work 126 130 5 130
19 Internal plaster-Mezz floor 131 137 7 137
20 1st floor brick work 132 152 21 152
21 External plaster-complete 140 169 45 169
22 Internal plaster toilets-1st floor 153 156 4
23 Granite door frames & window frames-1st floor 160 170 11 170
24 1st floor electrical piping work 162 166 5
25 Internal plaster-1st floor 167 181 15 181
26 Toilets concealed plumbing piping-1st floor 167 173 7
27 Side margin development work 170 214 45 214
28 Floor tiles & skirting work-mezz floor 170 179 10
29 Waterproofing with testing -toilets-1st floor 174 188 15
30 External plumbing work-complete 180 194 15
31 Electrical wiring work 182 196 15
32 External painting work-complete 184 203 20
33 Internal painting work-Ground floor 185 204 20
34 Wall tiles-1st floor toilets 189 198 10
35 Floor tiles & skirting work-1st floor 191 205 15
36 Floor tiles & skirting work-Ground floor 191 205 15
37 Internal painting work-1st floor 197 216 20 216
38 Aluminium windows-Complete 200 214 15
39 Doors shutters-Complete 200 214 15
40 Internal painting work-mezzanine floor 205 211 7
41 CP & sanitary work-complete 205 215 11
42 Electrical switches & boards 205 215 11