Development of Road Header Roof Bolting Module
Development of Road Header Roof Bolting Module
182
33rd International Conference on Ground Control in Mining
unacceptable because the bolts could only be installed to within
39.37 inches (1 m) of the mine face.
THE DESIGN
What resulted was an improved design that was built: a two The final challenge in the design phase was being able to
stage box section boom, with 146 inches (3.7 m) of extension for complete the functions required to drill and install bolts with the
each section (See Figure 2 and Figure 3). Through experience with module (See Figure 4) from a remote location nearly 40 feet (12.2
Fletcher metal/non-metal bolters, Fletcher identified that the area m) away. The following list details the steps required to drill
the boom rollers contacted on the box sections could potentially be the hole:
a weak spot. In lieu of a single boom roller, large dual diameter
rollers were mounted onto a central pivot, keeping the surface 1. Use Manipulator hands to retrieve drill steel from storage rack.
stresses to acceptable levels. The dual rollers were used on the 2. Position drill steel over drillhead and couple into drill chuck.
front and back of the cradle, on the bottom of the outer boom and 3. Slightly open Manipulator hands to act as drill guide.
the top of the inner boom.
183
33rd International Conference on Ground Control in Mining
was no way to return the midpoint to its home position without
actuating an upper cam valve. In an aborted drillings cycle, this
may not be possible. The updated package allowed the manual
return of the midpoint centralizer. This also allowed Fletcher the
opportunity to upgrade the size of all the sequence and shuttle
valves internal to the block, reducing the pressure losses in
the system.
CONCLUSIONS
Because the machines have not yet been deployed to the mine, a
review of the project objectives is in order to determine the success
of the project:
• The bolt modules and booms successfully meet all the roof
control requirements.
• A change out of parts allows conversion between multiple
bolt types.
Figure 4. ISO view of bolt module. • The need for an operator to work in unsupported ground is
virtually eliminated.
4. Actuate feed and rotation to begin drilling hole. • No electrical allowed for quick adherence to MDG rules.
5. Move midpoint centralizer to drill centerline. • Complex steps are aided by semi-autonomous hydraulic
6. Close midpoint lock to guide drill steel. drilling operations.
7. When drill depth allows, open manipulator hands.
8. Retract manipulator hands to stored position. The machines are due to be the center point of a multiple-year
9. Open midpoint centralizer lock. project at Eagle Downs Mine. We have, at this point, met all the
10. Retract midpoint centralizer to stored position. engineering and manufacturing challenges. As this design goes to
11. Open top centralizer. work in its intended environment, J.H. Fletcher & Company looks
12. After hole has reached full depth, reverse feed direction to bring forward to providing more innovative solutions to improve operator
drill steel out of hole. safety and mine production.
13. Move manipulator hands to drill centerline.
14. Close manipulator hands to guide retracting drill steel. REFERENCES
15. Stop the drillhead at the correct height for uncoupling.
16. Uncouple drill steel and clamp with manipulator hands. Latimer, C. (2013). “WDS wins massive Eagle Downs coal
17. Lower drillhead and store drill steel. contract.” Australian Mining. http://www.miningaustralia.com.
au/news/wds-wins-massive-eagle-downs-coal-contract
This list does not include boom positioning, applying resin/
grouting, or installing and torqueing the bolt. The tasks required New South Wales Trade & Investment. (2014). Mining Design
can be overwhelming for a drill operator without the assistance of Guidelines. http://www.resourcesandenergy.nsw.gov.au/miners-
a computer system to help automate the process. Through a series and-explorers/safety-and-health/publications/mdg
of custom package and cam valves, Fletcher was able to automate
steps 5 through 15, significantly aiding the drill operator in their
duties without adding any electric components that would need to
meet the Australian MDG regulations.
BUILDING/TESTING
184
33rd International Conference on Ground Control in Mining
Development of Mechanized Ground Support Installation Equipment
for Improved Safety in Narrow Vein Mine Conditions
William Kendall, Manager ofKendall, W.
Research and Development Engineering
J.H. Ferster, M.
Fletcher & Co.
Huntington, WV
185
33rd International Conference on Ground Control in Mining
The machine had to be acceptable to the miners and be cost approved canopy. The machine uses a low profile rotary percussive
effective. It needed to not only provide a safer environment for drill head and can install virtually any type or length of bolt.
ground support installation, but also match the flexibility of the
hand-held equipment, perform the ground support installation in a During the first six weeks of 2014, they were trammed up and
productive manner, and compare favorably to the current support down numerous ramps and operated by a variety of operators in
installation process. This meant the machine had to be able to different areas of both mines to gain experience. Modifications
install a variety of roof support types and mesh for surface control. were made as needed. In mid-February of 2014, the machines were
It also had to provide a reliable tram system, capable of negotiating turned over to the mines as production machines.
uneven floor, make 90-degree turns in narrow openings, and travel
ramps of up to 19% grade (Figure 2 – Stope Cross Section). The machines were evaluated against the following
design requirements:
J.H. Fletcher design engineers worked with Stillwater engineers, • Operator is under a protective canopy for protection from rock
operators, managers, and maintenance personnel at both mine falling while bolting and installing mesh.
sites to identify specific characteristics and requirements (mine • Operator only handles drilling tools and bolts versus handling
opening irregular dimensions, available power systems, operational the jackleg with hoses and handling mesh.
production sequencing, etc.). Throughout the process, Stillwater • Wire mesh can be installed remotely using the machine—
personnel were actively involved in the design of the machines. In no temporary supporting of mesh on scaling bars or using
2013, Stillwater ordered two machines, one for each mine, to allow “mickies” (short split set bolts which fit inside existing split
evaluation of the concept and the machines (Figure 3 – Bolter set bolts)
on Surface). • The noise level is reduced versus a jackleg. Maximum noise
level at the operator’s ear was measured at 113.6 dba. (For
reference, a jackleg drill operates at 117 dba to 125 dba.)
• The lifting and swinging boom keeps the operator close to the
drilling area, even at a maximum working height of 14.5 ft.
186
33rd International Conference on Ground Control in Mining
(See Figure 10 – Bolts Perpendicular) Although the new machine is an improvement, there are still
some inefficiencies to address. The operators must become familiar
with the controls and gain experience in using a mechanized piece
of equipment. This can be a difficult change for many operators.
Ergonomics must also be improved. Currently, the valve placement
obstructs the operator movements. The movement direction and
number of control valves has proved to be a challenge. Efficiency
in positioning of the machine is limited by lack of a basket
extend and auto basket level. During planned upgrades all control
valves will be replaced with electro-hydraulic joysticks and a 3
operating mode selector system to reduce the number of controls,
space required, and to provide logical movement direction of the
handles. Written labels will be replaced with pictograms back
lit with distinctive light colors based on mode of operation. Auto
basket level and basket extend will be added. Changes will be made
to the feed positioning system to provide a more open material
Figure 10. Picture of bolting the hanging wall. handling area.
WHERE WE GO FROM HERE
• Lifting boom allows bolts to be installed perpendicular to
faces even at height. (Figure 10 – Bolts Perpendicular) Stillwater is very committed to continuing development of new
• The machine possibly allows for changes to the blast pattern generation drilling and roof bolting machine to replace jacklegs.
for better ore recovery since the high reach bolts can be To date they have shown that they are safe to operate with reduced
installed at a better angle than was possible with jacklegs. operator exposure and no injuries to date, reduced noise level,
flexible in the type and length of bolts which can be installed,
Handling mesh with feed and comparable to a jackleg from a productivity standpoint
(planned upgrades should significantly improve efficiency). The
• Operators can wire together up to three pieces of mesh and lift current machines will run until the upgrades are available in mid-
them into position using the feed. 2014. After the upgrades are complete, Stillwater will re-evaluate
• The operator can bolt the mesh into place without leaving the both machines.
machine, installing “mickies,” or setting scaling bars.
188