MS-01-Method Statement For Site Establishment

The document summarizes the approval of a method statement submitted by a contractor for site establishment during the construction of a canal project in Sri Lanka. [1] The resident engineer approved the method statement, subject to some conditions and improvements being made to address environmental safeguards and missing details. [2] Key information missing from the original submission included land use and ownership details of proposed establishment areas, as well as approval requirements and statuses. [3] The contractor was asked to provide additional details on these topics, including source and transportation of construction materials, waste management, and water quality monitoring.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
465 views26 pages

MS-01-Method Statement For Site Establishment

The document summarizes the approval of a method statement submitted by a contractor for site establishment during the construction of a canal project in Sri Lanka. [1] The resident engineer approved the method statement, subject to some conditions and improvements being made to address environmental safeguards and missing details. [2] Key information missing from the original submission included land use and ownership details of proposed establishment areas, as well as approval requirements and statuses. [3] The contractor was asked to provide additional details on these topics, including source and transportation of construction materials, waste management, and water quality monitoring.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 26

MAHAWELI WATER SECURITY INVESTMENT PROGRAM (MWSIP)

CONSTRUCTION OF UPPER ELAHERA CANAL PROJECT

CONSTRUCTION OF MAIN CANAL FROM NEBADAGAHAWATTA TO MAHAKITHULA RESERVOIR INLET


TUNNEL (5+250 KM TO 22+300 KM)
APPROVAL SHEET FOR DOCUMENTS PREPARED BY THE CONTRACTOR
Contract No.: MWSIP/MMDE/ADB/ MWPCP/ICB-2/3267-3268-SRI/ICB/2017/003
Name of Contractor: China State Construction Engineering Corporation Ltd.,
Title of the Document: Method Statement for Site Establishment
Drawing / Document No.: NWPCR-ICB-2-CSCEC-HSC-03 Revision: 1 02 (B)

Received by Letter Ref.: CSCEC-NWPCP-ICB2-PMDSC- 082- Dated: 18 February 2019


2019
Previous Approval Status: RR Appr. Sheet No. XXXXXXXXXX
Present Approval Status: AN Appr. Sheet No. XXXXXXXXXX
A = Approved
AN = Approved except as Noted
Comments: RR = Return for Correction and Resubmission
Comment on Environmental Safeguard Management
1. The submitted MS satisfactorily addressed the required environment safeguard measures to be
implemented compared to the previous version, and hence, the MS is approved (AN) subjected to
following conditions and improvements.
2. It was noted following key aspects are missing:
i. Affected area and status of land use of the proposed areas for the site establishment including land
ownership
ii. Approval requirements and status of approvals
3. Please follow following format to update with the missing details
i. Land use/ownership (See sample format)
Name of Location (GPS Land ownership and Remarks (include land use prior to establish contractor
Contractor and address) the consent facility, briefly mention the land owner’s requirement
facility on site restoration etc.)
Contractor’s
office
Contractor’s
accommodation
building
Workshop
Laboratory
Batching Plant
&
Reinforcement
yard
Contractor’s
sub camp
Tunnel team
camp
ii. Approval requirements and status of approvals (see example table)
Project activity / Type of approval Responsible Compliance status Update
facility Institution Reference Validity period
Contractor’s office Trade Licence Pradeshiya Sabha
Contractor’s Environmental CEA
accommodation protection Licence
(EPL)
Workshop
Laboratory
Batching Plant &
Reinforcement yard
Material for site
establishment (sand/
gravel/ rubble etc.)
Disposal of
construction waste
Water extraction for
the contractor
facilities
4. It is understood that you may need several types of geo material (soil, rock, sand etc) for construction, but
source of material, approval requirements as per GoSL regulations (CEA, GSMB etc) for borrowing
material (if any), transportation of material, stockpiling etc. not identified. Indicate the source of material,
approval requirements and status of approvals with the document proof.
5. Provide details on water extraction for construction work and approval status as per GoSL regulations.
6. Explain waste management system at the work site including waste water disposal/ treatment
arrangements.
7. Ensure periodical (minimum quarterly) water quality, ambient air quality (specially in the batching plant
area) , noise and vibration where applicable through a qualified 3rd party laboratory and submit the test
report to the engineer to prove that you are carrying out the work complying with National Environmental
Quality standards as stipulated by CEA
The approval of drawings and documents shall not relieve the Contractor of any of his duties, obligations or responsibilities
under the Contract.

(Signature) (Date)
XXXXXXXXXXXXXX.
Resident Engineer
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Construction of Main Canal from Nebadagahawatta

To Mahakithula Reservoir Inlet Tunnel

(From 5+250km to 22+300).

Method Statement for Site Establishment

MS-001

Rev.B

Contractor: China State Construction Engineering Corp.

No Dat Prepared Checked Approved Remark


REV- A e
2018.10.30 Jack Lee Li Jianshuang Li Xinguang

REV- B 2019.02.18 Jack Lee Li Jianshuang Hou Jie

Ref.Letter
No :
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Contents

1 Introduction and general information ........................................................................... 1

2 Relevant documents and standards ............................................................................... 1

3 Responsibilities for activity describe within this method statement ............................... 1

4 Details of carrying out method statement activity.......................................................... 1

4.1 Work activities: ....................................................................................................... 2

4.2 Resource allocation ................................................................................................. 3

4.3 Work schedule ...................................................................................................... 3

4.4 Construction method ............................................................................................ 4

5 Quality control measures .............................................................................................. 6

6 Safety control measures................................................................................................. 6

7 Environment safeguard management ............................................................................ 6

Annexures
 Environment safeguard management Plan for Site establishment
 General layout of contractor site
 Plan of contractor’s main camp
 Concrete batching plant map
 Concrete batching plant layout plan
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

1 Introduction and general information

This project mainly consists of construction of main canal approximate length of 17km
with associate structures and two tunnels. The establishment works such as contractor’s
office, batching plant, laboratory, engineer’s/ employer’s facilities, laboure camps and
etc. should be finalized to ensure smooth construction work. Therefore this method
statement is described the site establishment arrangement details which are executed by
the contractor.

2 Relevant documents and standards

Following standards/documents shall be used to execute these activities


1. The contract signed between CSCEC and Ministry of Mahaweli Development
& Environment.
2. The Employer’s Requirements(ER) and drawings

3 Responsibilities for activity describe within this method statement

Project manager, construction manager, section manager, section engineer and other
relevant personnel within whose scope of works shall be responsible for referred
construction activities in related to construction of site establishment. This work
activity shall be carried out according to the employer’s requirement (ER), reference
drawings and method stipulated in this statement unless otherwise changed by the
Engineer.

4 Details of carrying out method statement activity


Following specified work activities shall be carried out under this method statement.
The approved materials, skill workers and proper equipment are used to ensure the
quality of the works.

1
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

4.1 Work activities:

a) Repair and renovation of existing dilapidated building located at irrigation


department premises close to Dewahuwa reservoir. Provisions shall be provide
for all works, furniture, fittings, equipment and all other services/facilities
necessary to establish the Employer’s and Engineer’s sub-office. Also the
maintenance works of the sub-office including all facilities shall be carried out
by the contractor.

b) Provision and operation of new permanent guest house accommodation


building within the existing office compound of the division irrigation engineer
at Dambulla, including all services and associated facilities.

c) Provision of new office building in the compound of irrigation department


divisional irrigation engineer’s office in Dambulla. This office building shall
complete including design and construction as specified.
d) Preparation of the site establishment areas and compounds for the use of the
Contractor including earthworks, drainage, landscaping and fencing, surfacing
and road works etc. Those areas and works shall be identified and execute
during the canal construction works. However the prior approval shall be
obtained from the engineer before start such works.
e) Construction of the Contractor’s temporary buildings including workshops,
construction team camp, office building (Contractor already rented a land with
existing building. This land is located 1.5km far from Galewela to Dambulla
side on A6 road), laboratory, stores, housing, canteen, and First Aid station,
and erection of the concrete batching plant(s) and the aggregate crushing plant;
f) Construction and finishing of other buildings and facilities as specified for the
Employer and the Engineer.

2
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

4.2 Resource allocation

Resource allocation for site establishment activities shall be as shown in following


tables. The manpower/personnel allocation and equipment/machinery allocations are
tabulated below for easy reference.

Table 1: Manpower/personnel allocation for Site Establishment


No. Category Numbers Remark
1 Site Engineers 2 Chinese
2 Site Engineers 3 Local

3 Skilled Workers 25 Local

Table 2 Equipment/Machinery allocation for Site Establishment Area


No. Description Model Quantity Remark
1 JCB 3
2 Dumper Truck 20t 3
3 Concrete Truck Agitator 6m3 2
4 Welding Machine 2
5 Wheeled loader 4m3 1
6 Mobile crane 20 Ton 1

4.3 Work schedule

The detail proposal shall be submitted within 28 days after the commencement date.
Detail proposal shall be included the layout, detailed drawings, building standards,
detailed specifications for construction work, fittings & fixings details, services &
utilities, procedures for operation of facilities and provision of services to the
Employer and Engineer, the Contractor’s assigned service and maintenance etc.

All the facilities covered by Sub-Clause (ER) shall be completed and fully operational
as specified no later than 182 days after the Commencement Date unless otherwise
agreed by the Engineer.

3
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

4.4 Construction method


The preparation of the site establishment areas and compounds for use of the Contractor,
the Employer and the Engineer shall be as per specified in the following steps:
As per requirements of contract and for execution of this project, site establishment
areas and temporary facilities including:

1. Contractor’s main camp, sub camp, living accommodation, workshop, concrete


batching plant , site laboratory, the Contractor’s general layout of main camp, sub
camp, living accommodation and other auxiliary facilities are proposed as shown
in attachment 1.

2. The Contractor’s main camp located in one compound where already existing
building which can be used as part of office area, and the laboratory area, the
workshop will be newly constructed within this compound. Please refer the
attachment 2 for details.
The estimated covered area of the office and accommodation facilities, workshop and
laboratory are shown in the following table.

Table 3 Estimated Covered Areas of the Facilities


No. Facilities Covered Area (m2) Remarks
1 Contractor’s office 300 Existing room
2 Contractor’s accommodation building 400 New Construction
3 Workshop 200 New Construction
4 laboratory 162 New Construction
5 Batching Plant & Reinforcement yard 10000 New Construction

3. The Contractor's Sub Camp - which is now proposed at K11 for the use of
construction team camp. The location of DP2 indicated in drawing is chosen
specifically as a storage area for aggregate materials and for the establishment
of the batching plant and crusher unit due to the convenience to transport and
less disturb to the local residents

4
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

4. The Employer and the Engineer’s facilities provided by the contractor is listed
below for easy reference
a. The Employer’s and Engineer’s sub office is to be established in a
dilapidated single stored buildings. The buildings will be repaired and
renovated. Also contractor shall provide furniture, fittings and equipment
necessary to establish the Employer’s and Engineer’s sub office in
accordance with the detailed layouts and specification. The detailed plan
shall be submitted separately.
b. A new office building is to be established within the existing compound of
the Irrigation Department Divisional Irrigation Engineer's office in
Dambutla. This new office building is intended to replace the existing
office building which is presently being used by the Divisional Irrigation
Engineer, and will be used for the operation and maintenance of the water
diversion facilities established under the NWPCP comprising the Nalanda-
Wemedilla diversion and the Mahaweli water diversion through Dambulu
Oya. The relevant drawing shall be submitted separately.

c. The contractor shall design, construct and maintain an accommodation


building and associated facilities which is to be exclusively available for
the use as a Project guesthouse by the Employer and the Engineer. The
location of this accommodation building shall be within the existing office
compound of the Divisional Irrigation Engineer at Dambulla. Not later than
28 days after the Commencement Date, the Contractor shall submit to the
Engineer for approval including detailed drawings and specifications of the
accommodation building and facilities, including all supporting
infrastructure of road works and surfacing, surface and foul drainage, water
reticulation, power distribution, telephones and plot fencing.

5. All structures, buildings and facilities will be maintained and repaired during
whole contract period to satisfactory of the Employer and Engineer.

6. All the facilities including site office, accommodation, workshop and laboratory
shall be removed and the area reinstated in accordance with the relevant
specifications at the completion of construction works on the approval of the
Engineer.

5
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

5 Quality control measures


1. The construction must be implemented strictly according to the drawings and
specifications.

2. Raw materials which used for construction activities are from approved sources
and compliance with requirements.

3. The quality and moisture content of the filling material must be strictly
controlled. The type and the technical condition of the material must meet the
design requirement.

6 Safety control measures


1. Well experience safety officer with safety department shall be assign to avoid
all the unexpected safety issues.
2. Site staffs are allowed to enter the construction site only with all necessary
personnel protective equipment (PPE).
3. All the equipments and tools which used for this work activity shall be
maintained regularly.
4. Safety measures must be taken during the excavation close to buildings,
facilities’ foundations, electricity posts and scaffolds.
5. The speed and safety distance in between vehicle in the construction premises
should be maintain properly. also Lighter vehicles should give way to heavier
vehicles when passing each other

6. It is forbidden to stand within the operating area of a running machine. All the
operations of machines shall strictly conform to the regulated process of safety
operation.
7. If the soil structure is unstable, collapse, water level rises suddenly or any other
dangers occur, then all the site staffs should immediately stop the work and be
evacuated to safe places. They can go back and resume the construction only
after the site is confirmed to be safe.

7 Environment safeguard management


The details of environment safeguard management measures to be implemented during
the site establishments are attached in annexure.

6
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Annexures

7
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Environment safeguard management Plan for Site establishment


The initially identified land areas for contractor’s office usage, batching plant and
workers camps are shown in attached drawings. The contractor shall be obtained
required permission from relevant authorities for those land usage. As well as contractor
will come to the sign agreement with relevant land owners (if private lands are use).
However the contractor will informed in advance to the engineer prior to sign such kind
of agreements. As well as all the land areas which were summarized in section 4.1
(method statement) will not be utilized at the start time of the project. The identified
such areas will be utilized when the construction works are in progress and according
to the actual requirements are arisen.
As summarized in section 4.1 of method statement, some buildings are needed to
renovate and newly construct by the contractor for the use of employer and engineer.
The contractor will be discussed later in details wise with engineer and employer
regarding to obtain required approval for such buildings works.
The anticipated environmental impacts and mitigation/alternative proposal is tabulated
below for easy reference.

Anticipated Source of Mitigation measures for


the Alternatives/
Environmental impact identified impact other
Impact remarks
Dust emission Transport Covering the material during Identify
material transportation transport route
with less
environmental
significance
Noise/Vibration Machineries  Strictly adhere the CEA Less Sound
regulations machineries
 All machinery and equipment use
should be well maintained and
fitted with noise reduction devices
in accordance with manufacturer’s
instructions.

8
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

 If the site establishment is within


20m to the nearest habitation,
noisy construction work such as
clearing, concrete mixing and,
mechanical compaction, etc.,
should be stopped between 18.00
hours to 06.00 hours

 Careful planning of the operation


of construction equipment is
required dumping this period so
that minimum distances so that
minimum distances are caused
 Construction camps and
temporary labour sheds located
away from the immediate vicinity
of the construction sites and major
road traffic
Pollution of waste
surface water management  The Construction activities /erosion
ways and would be limited to possible
ground water smallest area
 Control the quality of construction
site waste water within the
construction site through suitable
drainage system with traps for
arresting the sediment loads for its
proposed disposal in to the main
natural drainage system around the
site
 Implementation of suitable disposal
methods of sediment construction
debris in tune with the local
condition to avoid water logging at
construction site
 Proper drainage and sanitation
facilities will be provided at the
construction site

9
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

 Formation of stagnant water pools


will be eliminated to avoid soil
erosion and breeding of mosquitos
 Minimum quantity of water will be
used to meet the essential
construction requirements. The
contractor will ensure to avoid
unnecessary use of water for
washing of equipment and vehicles
during construction
 The contractor will be disposed the
construction wastewater from the
work site through a soaking pit of
appropriate capacity, which be
levelled back after completion of
construction work. For toilet
waste, appropriate arrangements
such as septic tanks with soaking
pits will be arranged.
 Regular maintenance of the septic
tank and Soakage pit will be carried
out for safe disposal of toilet
wastewater
 The location of toilet will not be
close to the hand pump or tube well
or any other ground water source to
avoid seepage and contamination of
well water.
 Immediate cleanup of accidental
spills of soil or other materials on
the roadway or in gutters

Aggregation of  The debris and spoil shall be Waste


construction disposed in such a manner that; segregation at
waste (i) waterways and drainage paths the site
are not blocked
(ii) the disposed material should Making the
not be washed away by runoff and workers
(iii) should not be a nuisance to the aware on the
public waste
management

10
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Soil erosion  Unstable banks will be Frequent


protected / stabilized by Monitoring
mechanical means such as programs
retaining walls.
 Diggings, if required for Only the
foundation, will be carried out required area
only in specified area, as per to be cleared
the engineering drawings and And keeping
excavated earth material will the vegetation
be used for filling and cover as much
compaction. as possible
 Tree plantation will be carried
out, along the canal path to
enhance soil stability and
control erosion
 Borrow pits will be restored
and leveled back to control soil
degradation
 Left over construction
materials and excavated soil
will be disposed in designated
areas to avoid soil
contamination/land
degradation.
Traffic issues  In order to ease traffic within Prepare a
the city, transport of traffic plan to
construction material and avoid
machinery will be done prior Congestion
to 6.00 am and after 6.00 pm
Impact on  Avenue plantation is proposed Avoiding the
flora/fauna/ to be implemented cutting or
habitat(if any)  Provision of cooking fuel for removing of
trees as much
construction workers to avoid
as possible
cutting/felling of trees for fuel
wood wherever possible, site
cooking will be avoid
 Listed and identified trees will
be removed as per the approval
granted, that would disturb the
construction activities.

11
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

 Trees will be removed from


the construction sites before
commencement of
construction with prior
permission from the concerned
Department.
Air emission  Proper and prior planning and
scheduling of all major
construction activities
 Identification of infrastructural
supports needed for the
construction programme and
ensuring their timely
availability
 Construction materials would
be stored in covered stores or
enclosed spaces
 Adequate dust suppression
measures such as regular
sprinkling of water around
vulnerable areas of the
construction site by suitable
means to control fugitive dust
during construction material
handling/over hauling
activities particularly near
habitation

Environmental Monitoring Plan


The Environmental Monitoring Plan (EMoP) is an important component of
environmental management aspects relevant to the proposed works. To ensure the
effective implementation of the CEMP, it is essential that an effective monitoring
programme be designed and carried out. The Constructor objectives are:
 Verification of the estimated expected impacts based on selective parameters
and determine the actual scale of impacts, as well as registration of unforeseen
effects
 To evaluates the performance of mitigation measures proposed in the CEMP;
 To evaluates the adequacy of Environmental Impact Assessment;
12
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

 To suggests improvements in management plan, if required;


 To enhance environmental quality; and
 To satisfies the legal and community obligations.
The monitoring plan will be used for performance monitoring of the project. A
monitoring plan defining all parameters to be monitored, with tentative location, project
stages for measurements.
Constructor is responsible for the implementation and monitoring of Environmental
Monitoring Plan. Potential environmental impacts and safety of people can easily be
avoided or mitigated by adopting good engineering practices. The contractors that will
carry out the works will also follow the requirements of national legislation on
territorial planning and the current environmental management plan. Constructor will
assign some monitoring activities during construction and operation of the investments
under the project to a supervision engineering consultant. The results of monitoring
activities will summarized by Contractor in 6 monthly report to be submitted to the
Resident Engineer (RE). In case there are discrepancies with the statutory requirements
for environmental, Contractor develops additional mitigation measures for unforeseen
impacts that exceed the established norms. Competent authorities confirm the results of
the monitoring and the proposed additional measures, where appropriate.
All the site establishment shall be done under the supervision of a qualified staff and
skilled workers.
Monitoring on following factors will be done by third party monitoring group accepted
by Central Environmental Authority (CEA), Supervision Consultant (SC), PMU and
Local authorities (LA).
 Soil erosion
 Disposal waste
 Loss of vegetation cover and Spreading on invasive species

 Surface water
 Ground water

13
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

 Noise and vibration


 Dust
 Fauna and Flora

Monitoring Plan
Impacts Parameters to Frequency of Location of Monitoring
Monitored Monitoring Sampling points responsibility
agency/agencies
Soil erosion Siltation As required by All Site CEA/
Consultant establishment Supervision
area Consultant (SC),
PMU /LA
Dumping As required by All Site
Disposal Procedure Consultant establishment CEA/
Waste area Supervision
Responses from Consultant (SC),
local residents PMU, LA
Loss of Water quantity in As required by All Site
vegetation steams, Ponds Consultant establishment CEA/
cover and during dry area Supervision
Spreading on periods Consultant (SC),
invasive No and frequency PMU/LA
species of flora observed
Effluent quality As required by All Site
Surface water Water quantity in Consultant establishment CEA/
steams with area Supervision
special reference Consultant
to suspended (SC)/,PMU,
solids, PH, BOD, Water board /
DO pesticide LA
residual levels
Ground Water Water Level As required by All Site CEA/
Consultant establishment Supervision
area Consultant (SC),
PMU /Water
board/LA

14
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Noise and Noise levels As required by All Site CEA/


vibration As instructed by establishment Supervision
GSMB area Consultant (SC),
PMU, LA
Elephant Elephant Fence As required by All Site CEA/
human strength Consultant establishment Supervision
conflict and area Consultant (SC),
Loss of PMU/LA
habitats
Fauna and No and frequency As required by All Site CEA/
Flora of fauna and Consultant establishment Supervision
Flora observed area Consultant (SC),
PMU/LA
Dust Dust emission As required by All Site CEA/
Consultant establishment Supervision
area Consultant (SC),
PMU/LA
Source approval for geo materials
The source approval for the material such as rubble, coarse aggregate and fine aggregates
shall be obtained separately through CMS (contractor’s material submissions). As well as
separate approvals will be obtained from relevant authorities and from the engineer for the
borrow pits area, disposal areas (for temporary and permanent disposal areas) and
stockpiling areas.
Water extraction for construction works and contractor’s usage
When it possible, all the time required water for contractors office, accommodation and
workers day to day activities shall be brought from National water supply and drainage
board. The required tariff will be paid by the contractor. The required water for batching
plant will be extracted by available well in batching plant. The required approvals from
relevant authorities for that purpose will be obtained by the contractor. The required water
for site construction activities such as earth backfilling works will be supplied by bowsers.
Water for bowsers will be filled by approved source and required approvals for such water
source will be obtained by the contractor.

15
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

Establishment of concrete batching plant


The concrete batching plant shall be established at near to chainage 13+400 as specified in
attached drawings. Environment management Plan for Batching Plant is prepared
separately for easy reference.
Environment management Plan for Batching Plant

Anticipated Source of Mitigation measures for the Alternatives/ot


Environment impact identified impact her remarks
al Impact
Paving All working areas are paved in
Water quality hard non-porous surface.
Bunding  Bunding is able to contain
runoff.
Collection pit
and recycle tank  Primary and secondary
pumps fitted to collection
 Excess water pumped to
recycle tank
 Collection pit empty of
water, sand and gravel.
 Level controls working
properly.
 Recycle tank large enough
to store runoff from 20 mm
rainfall event.
Monitoring  Visual alarms on console –
offsite to indicate when water is
discharges discharged from site – are
installed and operable
 pH of offsite wastewater
discharges between 6.0 and
9.0.Suspended solids levels
of wastewater discharges
less than 80 mg/
Fuel and  Chemicals and fuels are
chemical storage stored in a dedicated and
adequately protected store.
 Bund around the storage
facility is adequate.

16
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

 Underground storage tanks


tested in accordance with
applicable Regulations.

Air quality Aggregates  Aggregates are damp at all


times.
 Wind shields are in place
and offer adequate
protection from the wind
Soil  Filler caps are clearly
identified and capped.
 Filler cut-off valve is
installed and operating.
 High level alarms are
installed and operating.
 Adequate test circuit.
 Hatches are air-tight.
 Dipping points are air-tight.
 Filter vents and silo
protection valves are
ducted to a ground level
collection point.
 Cement discharge valves
have fail-safe actuators.
 Flexible joints downstream
of valves.

Conveyors  Conveyors covered and


protected from winds.
 Transfer points fully
enclosed.
 Conveyor spillage control
provided.
 Conveyors fitted with belt
cleaners.
Filter  Filter system in correct
operating condition
(service and maintenance
records complete).
Weigh hoppers  Separate filters on cement
silo and weigh hoppers.

17
Construction of Main Canal from Nebadagahawatta to Mahakithula Reservior Inlet Tunnel (from 5+250km to 22+300).

 Overfill protection installed


and operational.
Emergency shut-  Emergency shut-down
down system operates from
console and silo delivery
point.
Loading bay  Loading bay is enclosed
Noise Process  Noisy equipment fitted
emissions equipment with suitable enclosures.
 No excess noise emissions
apparent.
Solid waste Warning devices  No excess noise emissions
management apparent.

Waste concrete  All concrete wastes should


be returned to the plant.
 Concrete waste return and
disposal are monitored and
documented.
 Waste concrete is
reclaimed or recycled.
 Wastes disposed in storage
pit, dried, then removed for
recycling or to a licensed
landfill

18
N

Dormitory
(3) Fence
Tree
Tree Tree
Tree
Tree
Tree
Tree
Tree
Tree
Tree Tree Tree
Tree Tree

Septic tank Tree Tree

Tree
Dining area

Fence
4*5m 4*5m 4*5m
4*5m 4*5m 4*5m 4*5m 4*5m

300
washing room
Door

300
Door

1000
road
dining room

Fence
Dining area Door

kitchen
500

Door

dining room
500

Tree
Door

600
2970
Tree Tree

Big tree
150 398 Tree
Bedside cabinet

Tree
Wardrobe

Dormitory
Door
1.2m*2m

Bed Tree
Basketball court
400

Shower

Tree
250

Toilet Bedside cabinet


bowl
1.2m*2m

Door
Bed

(2)
Basin Wardrobe

Basin
Door
Wardrobe
Bed
250

1.2m*2m
Toilet
bowl Bedside cabinet
400

Tree
Shower
Bedside cabinet

Bed
1.2m*2m

150 Wardrobe Door


Bedside cabinet

Wardrobe Door

Fence
1.2m*2m

Gutter
Bed
water
i
400

Shower
250

tower
Toilet Bedside cabinet
bowl
1.2m*2m

Tree Basin
Door
Bed

road
Basin
Door
Bed
250

1.2m*2m
Toilet
bowl Bedside cabinet
400

1680
Bedside cabinet

Bed
1.2m*2m
Door
Wardrobe

Tree 150 400 stairs


280

Tree
80

stairs
Wardrobe

Bed
Tree
curing tank
Dormitory
1.5m*2m

Tree
400

Bedside cabinet
Shower
Toilet
bowl
Tree
250

Basin Door Door Tree


Tree
Tree 5m*10m
Tree
1200
Basin Door Door

(1)
250

300

Bedside cabinet

Toilet
bowl Shower
1.5m*2m Tree
Wardrobe
Bed
Shower

Toilet
Bed
1.5m*2m
bowl
400

Bedside cabinet

Basin Door

1700
Mechanics room
400

Tree
Door
Wardrobe

Tree 200 400 100

Conference Concrete cube


400

Tree
2300

Tree
room
Operation room
400

Tree
Existing House Equipment and rock
core store room
400

Transformer
200KVA Attendant`s room
400

Tree

Tree
Contractor`s Materials
400

Tree Tree
Tree Engineer`s room
Tree
Tree Tree 400
Tree Tree

road
Tree
Tree Tree

Tree
Tree Tree
Tree
500

Gutter
Tree Tree
Tree Tree Tree
Tree
Tree

Gutter
Tree
Tree

bridge 330 140 330 330 140 330


Tree Tree
Tree Septic tank

Tree
400

400

Tree
Tree Tree
Tree Tree
Tree
Tree Tree
Tree Tree
Engineer room Tree
Tree

Brick wall
Tree
Tree
Flagpole

中 国 建 筑
Tree Tree Public toilet Tree Tree
Tree

Tree road
Brick wall Tree
Driver restroom
Tree
Tree

Tree
2m*2m
Security room Tree
Tree
200

80 80
Tree Tree
200
80

80

Old Gate Gate(6m width)


3300

Galewala side (1.5km from galewala) A6 Road Dambulla side

Contractor

Plan of contractor's main camp