Velocity Burndown Chart

This document summarizes the progress of a coffee shop build project across multiple sprints. It tracks planned points versus actual points completed for each feature. While the project started behind schedule, it was able to catch up by the end of sprint 4 and has remained ahead of plans since then. Velocity lines show the number of additional points completed in each sprint beyond what was planned.

Uploaded by

Bari Kokani
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
16 views

Velocity Burndown Chart

This document summarizes the progress of a coffee shop build project across multiple sprints. It tracks planned points versus actual points completed for each feature. While the project started behind schedule, it was able to catch up by the end of sprint 4 and has remained ahead of plans since then. Velocity lines show the number of additional points completed in each sprint beyond what was planned.

Uploaded by

Bari Kokani
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Project: Coffee shop build Updated By:

PM: Antonio Mendez Update Date:

Features Actual Points


Name Points Sprint #5 Sprint #4
Sign the lease on the building 10 10 0
Complete the dry walling 25 10 15
Paint the walls 10 0 0
Install the appliances 35 5 15
Procure the furniture 15 0 0
Complete the staffing 25 5 5
Laminate the menus 5 0 0
Sign contracts with local vendors 30 0 15
Launch a social media ad campaign 36 8 8
Install the neon signs 17 0 0
Complete the interior design 22 0 0
Baseline Points 230 184 138
Actual Points 230 192 134
Velocity Points 38 58

250

200

150

100

63
58
50 38

0
Sprint #5 Sprint #4 Sprint #3

Commentary: The project started behind the planned points, but was able to
catch up at the end of the 4th sprint, and since then has been ahead of the
plan. The green velocity line denotes the number od points achieved in each
sprint.
Cynthia Lin
###

Actual Points
Comments
Sprint #3 Sprint #2 Sprint #1
0 0 0
0 0 0
10 0 0
15 0 0
10 5 0
5 5 5
0 0 5
5 10 0
A snag on sprint #2 was
8 0 12
fixed on sprint #1
0 5 12
10 8 4
Assumed linear
92 46 0
achievement of points
71 38 0
63 33 38

Baseline Points
Actual Points
Velocity Points

63
8

38
33

nt #4 Sprint #3 Sprint #2 Sprint #1


Baseline Points
Actual Points
Velocity Points