This document provides a construction safety and health plan for a proposed 2-story duplex residential project. It outlines the company's safety policy, project details, roles and responsibilities of personnel, and safety procedures. A construction safety and health committee will oversee accident prevention programs and conduct daily toolbox meetings to discuss hazards and safety tips. Basic personal protective equipment like safety shoes and helmets will be provided and their use enforced. First aid kits and facilities for worker welfare will also be available on site. Working hours will be 8 hours per day with breaks. Construction waste will be properly segregated and disposed of. Specific safety work practices are identified for tasks like welding, use of power tools, material handling, and electrical works.

Uploaded by

Jehrome Cruz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
113 views

Simplified CHSP Template

This document provides a construction safety and health plan for a proposed 2-story duplex residential project. It outlines the company's safety policy, project details, roles and responsibilities of personnel, and safety procedures. A construction safety and health committee will oversee accident prevention programs and conduct daily toolbox meetings to discuss hazards and safety tips. Basic personal protective equipment like safety shoes and helmets will be provided and their use enforced. First aid kits and facilities for worker welfare will also be available on site. Working hours will be 8 hours per day with breaks. Construction waste will be properly segregated and disposed of. Specific safety work practices are identified for tasks like welding, use of power tools, material handling, and electrical works.

Uploaded by

Jehrome Cruz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 5

1

CSHP TEMPLATE FOR SMALL CONSTRUCTION PROJECTS

RESIDENTIAL PROJECT/S (2 STOREY AND BELOW) OR MINOR REPAIR WORKS

1.0 Company Safety and Health Policy


It is the general policy of JEFFERSON GO JUAN___ to perform work in the
safest manner possible consistent with good construction practices.

To achieve these objectives, we are committed to the following:

 Identification of potential hazards that may arise from the


programmed/scheduled work activities;
 Organizing the work activities so as to minimize the risk arising from them;
 Ensuring that all workers are given orientation/briefing or induction prior to
deployment to the site;
 Establishing a site safety committee to act as policy making body of the project
on all issues pertaining to safety and health;
 Ensure the conduct of daily toolbox meetings;

2.0 Project Details


Project description:

a. specific name of project: PROPOSED 2 STORY DUPLEX

b. Address/location: LOT 7 BLOCK 5 ELM STREET EXECUTIVE HEIGHTS


SUBDIVISION PARANAQUE

c. classification of the project: (2 storey residential or minor repair works 15 workers


and less) 2 STOREY RESIDENTIAL

d. project owner: JEFFERSON GO JUAN

e. name of main contractor and list of sub-contractors (if any) and PCAB License,

NA

f. estimated number of workers in the site: 10__________________________

g. estimated start date of (execution of the project) construction MAY 10 2022


h. duration of the project (no. of calendar days) and; 180

i. specific scope of work to be undertaken: Residential Construction

3.0 Composition of Construction Safety and Health Committee (CSHC).


2

I/We ____ JEFFERSON GO JUAN________ am/are committed to organize a CSH


Committee at the project site to act as a policy making body of the project on all issues
pertaining to safety and health.

3.1 Composition of Construction Safety and Health Committee (SHC)


Our CSHC at the PROPOSED 2 STOREY DUPLEX consist of:
o Chairman – SAMUEL JEHROME CRUZ

 Members : ARIS SAYO


ALVIN BALLESTER
CHRISTIAN VELASCO
CHRISTOPHER VELASCO
 Secretary – NORWINA DELEON CRUZ

3.2 Functions of CSH Committee shall include but are not limited to the following:

 Plans, develops and oversees the accident prevention programs for the
construction project;

 Gather feedback, discuss, review safety policies, procedures and


recommend improvements;

 Conducts safety/toolbox meetings.

 Communicate safety and health concerns and information to management


and staff personnel;

 Reviews reports of accident investigation and implementation of program;

 Solicit, evaluate and confirm implementation of safety and health


suggestions from employees.

4.0 Composition of Health & Safety Personnel (if there is any)

 5.1 Complete Name of Safety Officer/s: Samuel Jehrome E. Cruz


(please attached the certificate of COSH training)

 5.2 Complete Name of First-Aider/s: ___________________


 (please attached the certificate of First-Aid training)
3

5.0 Duties and Responsibilities


a. Owner
 Responsible in operation, safety and health of the entire project.
 Delegate personnel for the implementation of safety
 Chairman of the safety and health committee. Arranges schedule and place of
meeting and notifies members.

b. Project Coordinator
 Ensures that all workers under his supervision understand safety responsibility.
 Ensures that proper use of PPE
 Acts without delay in addressing all hazards and unsafe conditions or actions
within the scope of their area of responsibility.
 Holds toolbox safety meeting with the workers.

c. Worker
 Consistently observes work conditions, operation, equipment and tools for the
purpose of accident prevention.
 Complies with all the regulations as well as safe work practices and safety rules.
 Uses all necessary personal protective safety equipment and other safe working
practices.
 Corrects any unsafe practices within the scope of work operations and reports
any unsafe conditions.
 Attend all committee/toolbox meetings.

6.0 Conduct of Toolbox Meeting


To hold a daily safety toolbox meeting every morning before the start of work to attain
the following objectives:
 To discuss matters pertaining to the job;
 To provide briefing on the planned work;
 To predict potential hazards or actual occurrence of accidents at the site;
 To provide tips and suggestions on how to prevent possible accidents, and;
 To discuss other pertinent matters (e.g. accident prevention)

7.0 Personal Protective Equipment


The company will provide the following basic PPEs and enforce the use of the
adequate and approved type of personal protective clothing and equipment suited to the risk
inherent in the work and operations performed:

 Safety shoes - will be used for general works and to be worn at all times on the
site.
 Safety helmet – all workers must wear an approved safety helmet while on the
construction site.
 Safety gloves - to be worn wherever possible for hand protection
 Safety goggles/Face shield – protection against flying objects from doing work
such as chipping, grinding, cutting, drilling works and alike.
 Safety belt/harness – to be used whenever working at height.
 Others (specify depending on the nature of work and hazard identified)
_____________________________________________________________
4

_____________________________________________________________

8.0 First-Aid, Health Care Medicines and Equipment Facilities


The owner/employer will provide the following basic first-aid kit and health care
medicines and facilities for workers in the site:
BETADINE AND BANDAID STRIP
PAIN RELIEVERS
ALCOHOL AND HYDRGEN PEROXIDE
MEDICAL TAPES AND BANDAGES
FACE MASK AND SURGICAL GLOVES

9.0 Workers Welfare Facilities


The following welfare facilities will be provided in the site to ensure humane working
conditions:
a. Adequate supply of safe drinking water
b. Adequate sanitary, washing and sleeping facilities separate for men and
women workers
c. Adequate facilities for changing and for the storage and drying of work clothes.
d. Adequate accommodation for taking meals.

10.0 Working Hour & Break Time (Indicate the maximum number of work hours per day).
8 HOURS WORK DAY
15 MINUTE MORNING AND AFTERNON BREAK
1 HOUR LUNCH BREAK
11.0 Construction Waste Disposal
The main constructor including subcontractors will be responsible for minimizing
waste generated during the implementation of the project. The following procedures for
disposal of wastes will be implemented in the site:

1. Ensure that the construction wastes are segregated from that of domestic
waste.
2. All domestic wastes are to be collected on a daily basis.
3. Construction debris (broken hollow blocks, spoiled concrete, loose
concrete, etc) should be taken out on the staging area.
4. Oil spills and spoiled greases should be wrapping in the black garbage bag
and will be properly disposed.
5. Application of good housekeeping.

12.0 Safety Work Practices - (indicate safety work practices based on the scope of work to be undertaken.
Use additional sheet if necessary)

12.1 Welding and Cutting CHECK WIRING AND EQUIPMENT / USE WELDONG GLOVES AND MASK

12.2 Hand and Power Tools CHECK WIRING & EQUIPMENT / USE MASK AND GOGGLES EAR
PLUGS
5

Safe Handling of Materials –USE STABLE STORAGE AREAS AND SECURE MATERIALS TO
PREVENT FALLING. PROVIDE PROPER VENTILATION FOR PAINTS AND OTHER CHEMICALS

12.4 Electrical Works and Installation - INSPECT WIRING INSTALLATIONS UPON


PLACEMENT, USE ELECTRICAL GLOVES AND ENSURE NO POWER IS RUNNING THROUGH THE
CURRENT BY TURNING OF CIRCUIT WHILE INSTALLING.

13.0 Enumerate/describe other safety procedures in accomplishing the project.

SAFETY OFFICER SHALL INSPECT SITE FOR HAZZARD AND APPLY PROPER MITIGATION.
ENSURE PROPER PPE FOR WORKERS. INSTALL WARNING SIGNS AND SAFETY
PROCEDURE IN EACH SECTION TO REMIND WORKERS. MONITOR HEALTH AND WELL
BEING OF WORKERS AT ALL TIMES. WORKERS SHALL NOT CARRY MATERIALS THAT
ARE TOO HEAVY WITHOUT PROPER ASSISTANCE.

14.0 Penalties/Sanctions – as a matter of policy and to ensure that the safety and health rules
specified herein are complied with, the owner recommended the following sanctions/penalties for any
violations of CSH program(Please attach company policy on penalties, if there are any). :
 First offense – ______warning – (written)______
 Second offense -- penalty – (one (1) day salary deduction)
 Third offense – penalty – (three (3) days salary deduction)
 Fourth offense – dismissal

Jeffersn Go Juan May 6, 2022


Name of Project Owner Date
Signature over Printed Name

Samuel Jehrome E Cruz May 6 2022


Name of Person who will supervise the project Date
Signature over Printed Name