This document outlines a marking plan procedure for items during fabrication of a steel structure. It assigns responsibilities for applying the procedure and specifies how incoming materials and fabricated items will be marked. Incoming materials will be marked with color codes to identify their grade, and fabricated items will be marked with identifying codes including the project number, drawing number, and item number before welding. The procedure aims to properly identify materials and ensure markings remain readable after surface treatments.

Uploaded by

AHMED KHAMIS
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
100 views

New Bios 2G Hydrotreatment Unit-Cartagena, Spain Supply and Fabrication of Reformer Steel Casing, Structures and Stack

This document outlines a marking plan procedure for items during fabrication of a steel structure. It assigns responsibilities for applying the procedure and specifies how incoming materials and fabricated items will be marked. Incoming materials will be marked with color codes to identify their grade, and fabricated items will be marked with identifying codes including the project number, drawing number, and item number before welding. The procedure aims to properly identify materials and ensure markings remain readable after surface treatments.

Uploaded by

AHMED KHAMIS
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Documents No. Standard /Spec. Rev.

Date Pages

FMC-M-Pr-0019 EN ISO Standards 00 15/12/2021 1 OF 2

Title of
Procedure MARKING PLAN PROCEDURE
New Bios 2G Hydrotreatment Unit-
Cartagena, Spain
Project Name
Supply and Fabrication of Reformer Steel
Casing, Structures and Stack

Client

Project / Client
P.O. No. P7132

Subcontractor Ferrometalco Steel Construction

FMC
Procedure MARKING PLAN PROCEDURE Project No. 956/100-200

Comments:

00 For Client Approval 15/12/2020


Prepared By Checked By Reviewed By
Rev. Comments Date Remark
Material Eng. QC Head QA Head
Documents No. Standard /Spec. Rev. Date Pages

FMC-M-Pr-0019 EN ISO Standards 00 15/12/2021 2 OF 2

Title of
Procedure MARKING PLAN PROCEDURE
1. Purpose:

To establish a Marking system for Items in Fabrication of Steel Structure with respect to Fabrication
Drawings and shipment documents.

2. Responsibility

• The production Engineers are responsible for applying the procedure at the workshop.
• The Quality Control Engineers are responsible for check proper application of the procedure.
• Technical office is in charge of specifying the mark location.

3. PROCEDURE
3.1. Incoming materials.

• QC Material engineer issue MRIR using form # FQP-8.6A-1B and submitted copy to storekeeper.
• Storekeepers use painting colors to identify raw materials and its equivalents referring to grades on
remarkable place as follows:

S/N Material Color Code


1 S235 (JR, Jo, J2) Yellow
2 S275 (JR, Jo, J2) Gray. White
3 S355 (JR, Jo, J2) Green.
5 Other Grades Red

3.2. Code of Identification as follows:


• The Serial Number must be identified and marked before the beginning of the component welding
process,
• All plates will be marked with Part No. and Heat No.
• QC material inspector mark code number as per incoming material log using Paint marker.
• Numbers and letters will be applied in such a way they are easily readable after the surface
treatments (painting, shout blasting …) has been completed.
• The marking will include (FMC Project no.- DWG no. - Item no.)