General Notes
General Notes
General notes are guides from the structural engineer to the structural elements of
the buildings such as Beams, Columns, Slabs, etc. for the construction of the H-Shaped
Building.
2. The contractor shall coordinate with the AR, ME, SE, EE, and other utilities and
equipment plans for the exact size, number and locations of all sleeves or openings
3. All reinforced concrete work shall be done in accordance with the Building Code
requirements (ACI 318) and all structural steel work shall be done in accordance with
AISC specifications (latest edition) in so far as they do not conflict with the local
4. Materials, and parts necessary to complete each item through such work which is not
5. All slabs, beams, girders, and other structural elements which are not indicated,
architectural and other allied engineering plans as well as to complete the structural
works in accordance with the intent of the plans and specifications shall be brought up
during pre - bids/ meetings/ negotiations. It is understood that the contractor has
indicated on drawings without extra compensation including all other excavations required
1. Cut slope for permanent excavations shall not be steeper than 1 - ½ horizontal to 1
vertical, and slopes for permanent fills shall not be steeper than 2 horizontals to one
vertical unless a substantiating data which justify steeper slopes are submitted.
2. Deviation from the foregoing limitations for slopes shall be permitted only upon
3. Trim the excavation to the required depth, lines and grades and other incidental
excavations to level up the footing plus compacting and tamping which are included
4. The materials to be excavated shall include: any rock, earth and other materials of any
nature and description encountered in obtaining the indicated lines and grades.
5. If the required safe bearing power of the soil is not obtained at the excavation depth
indicated on the drawings, the excavations shall be continued until such bearing
power is reached.
6. Piers and walls shall be lengthened accordingly and likewise, the footings shall be
revised to suit the new conditions for which the Contractor shall be paid at the unit
7. No fill or other surcharge loads shall be placed adjacent to any building or structure
lateral movement.
9. Fills to be used to support the foundations shall be placed in accordance with accepted
10. Additional payment for excavation will be computed per unit bid price and/or at
a. All materials of every nature and descriptions, which in the Owner’s opinion will
These are necessary when existing surface levels are lower than the sub-grade levels required
for work, or where excess or unauthorized excavation takes place beyond the indicated lines
and grades, the contractor shall fill the indicated line and grade at his expense under the
following conditions:
1. Where the footings and foundations occur, use concrete fill od the same class as
2. Where slabs occur, use a well compacted sand and gravel fill.
1. All excavations shall be back-filled immediately as work permits after concrete walls
and pers have attained full design strength and or as the Owner’s Engineer directs.
2. After the forms have been removed from the footings, walls, and piers, the materials
taken from excavations (free from waste and objectionable matter) shall be used for
tamped before the next fill is placed. Excess excavated materials shall be placed and
however, that the Contractor shall not be required to remove such materials more than
4. All exterior grades shall be formed in accordance with the drawings and
specifications, taking into account the requirements for landscaping work, if any, and
5. The Contractor shall grade the area included within clearing lines as defined in
“Clearing” under the General Conditions, and all such grading work shall be included
in the building Contract without extra or additional cost Banks of graded areas shall
6. Extra grading (cut or fill) beyond the 4.5meters and due to change of grade shall be
The Contractor shall protect trees indicated to remain in place by boxing then, by using guys
B. FOUNDATION NOTES
1. The foundation is designed for a net allowable soil bearing pressure of 250 kPa (5222
psf) at a minimum depth of 2.5 meters from the natural grade line. Contractor shall
report in writing or the structural engineer on the actual soil conditions uncovered and
3. Provide temporary removal of water from any source during construction. Dewatering
shall be carefully and properly performed to avoid disturbing the foundations and slab
bearing surfaces.
required for the protection of adjacent properties and provide all measures and
or new construction.
6. Do not back fill against basement walls until ground floor slabs have been placed and
1. Portland cement shall conform to the requirements of ASTM C-150 Type for
normal Portland Cement, Type III for High Early Strength Portland Cement.
Sand shall be clean, hard, coarse river sand or crushed sand free from injurious
amount of clay loam and vegetable matter and shall conform ASTM C-33 or C-330.
C-1-3 COARSE AGGREGATE
Gravel shall be river run gravel or broken stones. The maximum size shall be
1/5 of the nearest dimension between sides of forms of the concrete, or ¾ of the
minimum clear spacing between reinforcing bars, or between rebars and forms
whichever is smaller.
Water used in mixing concrete shall be clean and free from injurious number
C-1-5 ADMIXTURE
ASTM C-494.
The mixing and measuring equipment shall be approved by the supervising Architect
or Engineer. Unless otherwise authorized, concrete shall be machine mixed at the site or by
ready-mixed concrete.
C-3-1 Site Mixed Concrete
Provide a batch mixer equipped with accurate timing and measuring devices
1. For each batch, after all solid materials are placed inside the mixing drum, and
water is introduced before ¼ of the mixing time has elapsed, shall not be less
than 1 minute for mixers having a capacity of one(1) cubic meter or a fraction
revolutions per minute. Speed greater than 20 revolutions per minute and less
1. All concrete work shall be protected from drying out after removal of forms
equal to 90% based on ASTM C-309 and C-156, applied in accordance with
3. Wet burlap as often as required to keep concrete wet throughout each day for a
period of at least 7 days where normal Portland cement is used and 3 days
where high early strength cement is used.
1. The soil subgrade and fill layers below all slabs on grade, paving and pit slab shall be
2. All slabs - on - grade shall be provided with a minimum of 100mm thick. Compacted
and clean coarse sand bed, except as otherwise detailed in the plans.
3. Unless otherwise noted, all bedded slabs shall be reinforced with bars at 120mm O.C.
4. Place concrete for all slabs - on- grade in checkerboard fashtion between construction
joint areas not to exceed 300 sq. meters with a minimum of 24 hours between adjacent
areas of placement. Construction joint shall not be farther apart than 8.00 meters in
any direction. All slabs on grade shall be saw cut on each grid line and mid bay line
The scope of work under this section consists of furnishing of all materials, labor, tools,
equipment and performance of all operations relative to the fabrication, delivery to the site,
component parts of the structures, including the location, type and sizes of all rivets, bolts and
welds, shall clearly distinguish between shop and field rivets, bolts and welds.
2. Shop drawings shall be made in conformity with the best modern practice and with
E-2 MATERIALS
1. All structural steel shapes and plates shall conform to ASTM A-36.
3. Machine Bolts shall conform to ASTM A-307. Each bolt shall be provided with
E-3 WELDING
1. The technique, appearance and quality of welds and the method of correcting
defective work shall conform to the applicable provisions of “Workmanship of the Standard
2. Welding of structural members in shop and on field, shall be done only by certified
temporary attachment that are welded, shall be removed by a flame torch above the parent
5. Note shall be made on the Plans and on the shop drawings of those joints or group
of joints in which it is especially important for the welding sequence and technique of
welding to be controlled carefully, to minimize welding under restraint, and to avoid undue
distortion.
6. Weld length called on the Plans and on the shop drawings shall be the net effective
length.
Connections shall be as shown in the drawings and shall develop the full capacity of
the members.
shall comply with the cleanliness requirements of all joint's surfaces and
2. Holes shall be punched or drilled at right angles to the surfaces of the metals