FM.07.01.01 Field Change Request and Drawing Modification Request Form Rev2
FM.07.01.01 Field Change Request and Drawing Modification Request Form Rev2
Location: Discipline:
Reason for Modification: Code A: for design errors / constructability issues, B: for revised
project requirements / value engineering, C: for Engineer Instructions, D: for interface issues &
E: for Combination of all or any other
☐A ☐B ☐ C ☐D ☐E
Explanation:
☒ Construction Manager
☒ MEP Manager
Name & Signature:______________________________________ Date:__________
FM 07.01.01 Rev2
4. External Technical Review Requirements (to be completed by the Technical Office Manager)
______________________________________
☐ Other Designer’s / Consultant input required ) ☐ Other Designer’s input not required
(Please define the name of other Designer / Consultant)
_______________________________________
_______________________________________
_______________________________________
_______________________________________
FM 07.01.01 Rev2
6. Technical Review Outcome Details (to be completed by the individual Reviewers as identified above)
In the case of more than one Reviewer, each reviewer shall insert their name, date of review and signature along with
comments if they have any. If additional space is required, please refer to an attachment and add the details on it
If additional space is required, please refer to an attachment and add the details on it
FM 07.01.01 Rev2
8. Approval (each individual signing below confirms that the modifications have been assessed, evaluated, impacts
identified and addressed and that the compliance is maintained). After all signatures on this clause, the Technical
Office Manager shall instruct the drawing owner to proceed with the modification(s) included in this FCR
Technical Office Manager Designer:
Name: Name:
Signature: Signature:
Date:
Date:
Any other specified Designer /
Consultant:
Name:
Signature:
Date:
Construction Manager Subcontractor:
Name: Name:
Signature: Signature:
Date: Date:
Name: Name:
Signature: Signature:
Date: Date:
Project Manager
Name:
Signature:
Date:
FM 07.01.01 Rev2