OC and SC Test On Single Phase Transformer
OC and SC Test On Single Phase Transformer
Aim: To perform open circuit and short circuit test on single phase transformer and thus calculate
a) Equivalent circuit parameters
b) Efficiency at full load
0.85 lagging power factor
Unity power factor
Half the full load, 0.8 lagging power factor
c) Voltage regulation at full load
0.85 lagging power factor
0.85 leading power factor.
Apparatus Required:
Theory:
A transformer is a static piece of apparatus which by electromagnetic induction transforms energy from ac
circuit to another ac circuit at different voltage and currents keeping frequency constant. The efficiency of small
rating transformers can be found by direct loading method, but in case of large rating transformers arrangements
for actual loading cannot be done in laboratory and also it is costly. To determine efficiency of single phase
transformer through open circuit and short circuit test is an indirect method of testing, because the transformer
is not actually loaded during these tests.
Open Circuit Test:
This test is performed to determine the iron or core losses of single phase transformer. The
I W R X
no-load current 0 , the iron losses 0 are measured. From these, c and m parameters of the Equivalent circuit
can be calculated.
One of the windings of transformer is kept open and rated voltage at rated frequency is applied to the
other winding. Generally HT is kept open circuited and the rated voltage is applied to LT winding.
The connections are made as shown in Figure 1 and rated voltage is supplied through an auto
transformer. The readings of wattmeter, ammeter and voltmeter are noted. Let
Wattmeter reading =
W 0 watts.
I
Ammeter reading = 0 amps
Voltmeter reading = V 1 volts.
Short Circuit Test:
This test is performed to determine the equivalent resistance
Req and the equivalent leakage
X
reactance eq of the transformer. The connections are made as shown in Figure 2. The LT winding is short
circuited and rated current equal to HT winding is applied through an autotransformer. Since the applied voltage
is low, the iron losses are negligibly small as compared to the full load copper losses. Therefore, the wattmeter
reading indicates the full load copper loss. Let
Wattmeter reading =
W sc watts.
I
Ammeter reading = sc amps
V
Voltmeter reading = sc volts.
Circuit Diagram:
Procedure:
(i) For Open Circuit Test:
a. Connect the circuit as shown in figure 1.
b. Put the variac at a low output voltage.
c. Switch on the ac supply.
d. Adjust the variac to the rated voltage of the side (i.e. LT winding) to which the instruments are
connected.
e. Record the wattmeter, ammeter and voltmeter readings.
f. Switch off the ac supply.
Observation Table:
Rc =................... Ω
X m=................... Ω
Re1 =....................Ω
X e1 =....................Ω
The efficiency at various loads have been calculated and is found as below
The voltage regulation at various loads have been calculated and is found as below
Precautions:
1. All the connections must be tight and clean.
2. Instruments of proper ratings must be used.
3. Don’t touch the bare wire.
4. Before switching on the supply, the zero readings of the wattmeter, voltmeter and ammeter must be
ensured properly.
Viva-vice questions:
Ques1: What is the importance of open circuit and short circuit tests on single phase transformer?
Ques2: Why indirect loading test of large rating transformers is necessary?
Ques3: How do copper losses vary with load on the transformer?
Ques4: How do core losses vary with load on the transformer?
----------------------------*-----------------------------*-----------------------------------*---------------------------------