Technical Report PDF
Technical Report PDF
BY
SAPTADEEP SARKAR
ROLL NO- 13031616045
AT
2
Contents
1. Acknowledgement
2. Introduction to DVC & DVC-CTPS
3. Complete description of Power plant
4. Coal Handling Plant
5. Boiler
6. Turbine
7. Condenser
8. Cooling Tower
9. Turbo generator
10. Transformer
11. Switchyard
12. Switchgear
13. Communication
14. Ash Handling plant (AHP)
15. ESP
16. Motors
17. Safety
18. Conclusion
19. Reference
3
Acknowledgement
The dissertation has been prepared based on the vocational
training undergone in a highly esteemed organisation of Eastern
region, a pioneer in Generation Transmission & Distribution of
power, one of the most technically advanced power stations in
India , the Chandrapura Thermal Power Station (C.T.P.S), under
DVC.
I would like to express my heartfelt gratitude to the
authorities of Chandrapura Thermal Power Station for providing
me such an opportunity to undergo training.
I would also like to thank the highly experienced Engineers,
without whom such type of concept building in respect of thermal
power plant would not have been possible. At last but not the least,
I would like to convey my thanks to all the members of the staff
of DVC-CTPS who have helped me at every stage of training.
4
INTRODUCTION
Damodar Valley Corporation (DVC) is a public sector company
which operates several power stations in the Damodar River
area of West Bengal & Jharkhand, India.
The company operates both thermal power station and hydel
power dams under the Indian Ministry of Power. The present
capacity of DVC is 6357.2 MW . The Damodar Valley
Corporation has been generating and transmitting power since
1953.
5
Thermal Power Plants
6
5 Mejia Thermal West 2340MW
Power Station Bengal
DVC-CTPS -
CHANDRAPURA
Chandrapura Thermal Power Station (CTPS) is
located at Bokaro district in the State of Jharkhand.
It has five working unit with a total installed capacity
of 890 MW. All of the units are coal-based. CTPS had the
pride of being largest pulverized fuel fire power
station of Asia and unit number one was the first
reheat unit installed in India with highest steam
parameters. Electrical switchyard of CTPS is a pride
of DVC, being India’s 2nd biggest network.
7
Technical Aspects
➢ 3 X 130 MW (U#1,2&3)
➢ 2 X 250 MW (U#7&8)
8
Capacity
Project Cost.
The approved cost of Unit 7 & 8 (2 X250 MW) is Rs. 2500 Crore.
(The current production cost is approx
Rs. 3.50/KW)
9
OVERVIEW OF A
THERMAL POWER
PLANT
Simplified Diagram
10
LPH – Low Pressure Heater
DA- Deaerator
HPH- High Pressure Heater
OAC- Open Approach Channel
RAH- Regenerative Air Heater
DM water- De-Mineralized water
The coal from mines is received at track hopper in
CHP through Wagons. The unloaded coal (max. size
250 mm2) is scooped into conveyor by Rotary Plough
Feeders & is passed through suspended magnet,
magnetic separators, and metal detectors, to ensure
that sized coal, free of foreign material is supplied.
Then it is sent to Crusher House for further crushing
to 25- mm2 size. After crushing, the coal again
screened for elimination of extraneous materials,
weighed and sent to boiler bunkers. Excess coal, if
any, is sent to coal yard for stacking. It then falls
through a weigher into the Bowl Mill where it is
pulverized. The mill usually consists of a round metal
table on which large steel rollers or balls are
positioned. The table revolves, forcing the coal
under the rollers or balls which crush it. Air is drawn
from the top of the boiler house by the FD Fan and
passed through the RAH, and then send to boiler for
burning of coal. PA Fan takes air from atmosphere
and distributes them into 4 parts and fed directly to
Mill blowing coal along pipes to boiler furnace.
The boiler consists of a large number of tubes
extending the full height of the structure and the
heat produced raises the temperature of the water
circulating in them to form superheated steam which
passes to the Boiler drum. The steam is fed through
the outlet valve to the HP Turbine(High Pressure
turbine) at around 540°C and 147kg/cm^2.After
11
this, it is returned to the boiler and reheated before
being passed through the IP & LP
Turbine(Intermediate and Low Pressure
Turbine).The water fed into boiler is DM water.
From the turbine the steam passes into Condenser
to be turned back into water. This is pumped
through CEP which sends water through LPH, and
HPH for further heating and BFP then sends it to the
Economizer where the temperature is raised
sufficiently for the condensate to be returned to the
lower half of the steam drum of the boiler.
The flue gases produced in boiler are used to
reheat the condensate in the Economizer and then
passes through the ESP where ash is collected.
Finally, they are drawn by the ID Fan into the main
flue and to the chimney.
From the boiler, a steam pipe conveys steam to
the turbine through a stop valve (which can be used
to shut off steam in an emergency) and through
control valves that automatically regulate the supply
of the steam to the turbine. The turbine shaft usually
rotates at 3000 RPM. This speed is determined by
the frequency of the electricity system and the
number of poles of machine (2- pole machine here).
Cold water from feed pool is circulated through
the condenser tubes and as the steam from the
turbine passes round them it is rapidly condensed
into water. Water which gets heated up in condenser
by cooling steam is sent to Cooling tower and then
left into feed pool from where it can be further used.
The electricity is produced in turbo generators
and is fed through terminal connections to Generator
Transformer, those steps up the voltage to
12
220kv(U#7&8). From here conductors carry it to
Switchyard from where it is sent for use.
13
CHP: Overview
Track Paddle Magnetic
Coal Mine
Hopper Feeder Separator
Crusher House
Coal
Bunker
Stack Yard
14
after that it is either stored at Stack Yard to be carried to
coal bunker for burning.
WATER TREATMENT
PLANT
15
Deaeration
Coagulation
Filteration
16
organic compounds with relatively unknown structures and
chemical composition
DM (Demineralised
Water) Plant
In De-mineralised Plant, the filter water of Water Treatment Plant
is passed through the pressure sand filter (PSF) to reduce turbidity
17
BOILER
Boiler is device for generating steam for power processing or
heating purposes. Boiler is designed to transmit heat from an
external combustion source contained within the boiler itself.
Boilers may be classified on the basis of any of the following
characteristics:
4. Size: Rating core for boilers standardize the size and ratings
of boilers based on heating surfaces. The same is verified by
performance tests.
18
7. Heat Source: The heat may be derived from
a) The combustion of fuel
b) The hot gases of other chemical reactions
c) The utilization of nuclear energy
19
10. Circulation: The majority operate with natural
circulation. Some utilize positive circulation in which the
operative fluid may be forced ‘once through’ or controlled with
partial circulation.
20
to the boiler is indicated by the description of the furnace as
being internally or externally fired. The furnace is internally
fired if the furnace region is completely surrounded by water
cooled surfaces. The furnace is externally fired if the furnace is
auxiliary to the boiler.
Boiler Accessories
Igniters: There are 12 side Eddy plate oil/ H.E.A igniters per
boiler. The atomizing air for igniters is taken from plant air
compressor at 7 kg/cm2. There are 2 igniter air fans supply air
for combustion of igniter oil. Mainly 2 types of igniters are
used:-
22
TECHNICAL SPECIFICATION OF BFP
Unit 7 & 8
• No. of BFP - 3 (2 running + 1 Standby)
• CAPACITY (M3/HR) - 380
• DELIVERY HEAD - 2320 M
• PERMISSIBLE +VE SUC. HEAD - 10kg/cm2
• FEED WATER TEMP.(0C) - 165
• NO. OF PUMP STAGES - 11
• PUMP I/L TEMP.(0C) MAX. - 165
• NOMINAL SPEED (RPM) - 2890
• Power - 6.6 MW
• FLOW RATE THROUGH R/C( M3/HR) - 130
STEAM TURBINE
A steam turbine is a mechanical device that extracts thermal
energy from pressurized steam, and converts it into useful
mechanical work.
23
turbine has double flow unit so as to accommodate the
increase in volume of steam due to the drop in pressure.
24
Impulse and
reaction
Turbine
25
Turbine Auxiliaries
Regenerative Heaters
Ejector
27
Cooling Tower
28
Turbo-GENERATOR
29
among the two circuits in order to increase the amount of output
current by reducing the branch impedance since voltage induced
remains constant.
Generator Components
31
Generator Cooling
33
Ratings of Turbo
Generator
For Unit # 7 & 8
Rated Voltage: 16.5 kV
Rated Power: 250 MW
Rated KVA : 250 MVA
Stator Current: 10219 A
Rotor Current: 2395 A
Frequency: 50 Hz
Connection: YY
Power Factor: 0.85 LAG
Coolant Used: Hydrogen
Rated H2 Pressure: 3KgF/cm2
Operational Duty: S1
Class of Insulation: F
Manufacturer: BHEL
34
TRANSFORMER
The transformers used in a power station have its sides abbreviated
as Low Voltage (LV) and High Voltage (HV) rather than primary
and secondary.
35
Fig: Generator Transformer Unit # 7
Major transformers in a power station:
1. Generator transformer:
The generator is connected to this
transformer by means of isolated bus duct. This transformer is used to
step up the generating voltage of 15.75 KV or 21 KV (depending on
the generator) to grid voltage normally 220 kV. This transformer is
generally provided with OFAF cooling.
36
2. Unit Auxiliary Transformer (UAT):
The UAT draws its input from the main
bus duct connecting generator to the generator transformer. It is used
for the working of large devices such as boilers, heavy motors etc.
The total kVA capacity of UAT required can be determined by
assuming 0.85 power factor and 0.9 efficiency for total auxiliary
motor load. For large units, it has become necessary to use more than
one auxiliary transformer. It uses the generated 16.5kV to c overt
into 6.6 kV.The maximum short circuit currents on auxiliary bus
should be limited with in the maximum switch gear rating available.
The maximum permissible voltage dip while starting the largest
single auxiliary motor, usually boiler feed pump, shall remain within
acceptable limits.
3. Station Transformer:
The station transformer is used to feed the
power to the auxiliaries during the start up. This transformer
normally rated for the initial auxiliary load requirements of unit. In
physical cases this load is of order of 60% of the load at full
generating capacity. It is also provided with on load tap changer to
cater to the fluctuating voltage of the grid.
4. Auto Transformer(AT):
It connects 220KV substation to 132 KV
substation & Vice-Versa.
Cooling of Transformer
37
Heat is produced in the winding due to the current flowing in
the conductors (I2R) and in the core on account of eddy
currents and hysteresis losses. In small dry type transformer
heat is dissipated directly to the atmosphere. In oil immersed
transformer heat is dissipated by Thermo Siphon Action.
UNIT # 7 & 8
GENERATOR TRANSFORMERS 2 Nos. (one for each unit)
Rating: 250MVA
No load voltage : 220/sqrt(3)/16.5kV
Current : 10291/656.08
Cooling : OFAF
Vector group: Ynd11*
Phase : 3
Freq.: 50HZ Manufacturer
: BHEL
*after 3 phase bank formation.
TRANSFORMERS (UAT)
Rating : 32 MVA
Transformation ratio: 16.5v 12% / 6.9-0-6.9 Vector
group: d/ d-d 11-11
39
STATION SERVICE 2 Nos. (One for each unit)
TRANSFORMER (SST)
Rating : 66 MVA
Transformation ratio: 220kV 12% / 6.9-0-6.9 kV Vector
group: Yo/ d-d 11-11
Make: BHEL
40
SWITCHYARD
It is a switching station which has the following credits:
(i) Main link between Generating plant and Transmission
system, which has a large influence on the security of the
supply.
(ii) Step-up and/or Step-down the voltage levels depending
upon the Network Node.
(iii) Switching ON/OFF Reactive Power Control devices,
which has effect on Quality of power.
Switchyard Equipments
41
Transformers:
Transformer transforms the voltage levels from higher to
lower level or vice versa, keeping the power constant.
Auto transformer (AT) are used to connect 400KV switchyard
to 132KV switchyard.
Circuit breakers:
Circuit breakers makes or automatically breaks the electrical
circuits under loaded condition.
Isolators:
Opens or closes the electrical circuits under No-load
conditions.
Instrument transformers :
Instrument transformers are used for stepping-down the
electrical parameter (Voltage or Current) to a lower and safe
value for Metering and Protection logics.
CTs are single phase oil immersed type.secondary current is
generally 1A, but also 5A in certain cases.
The CVTS are used at 220KV & above. For lower voltages
electromagnetic type transformers are mostly used. The
secondary voltage is 110/sqrt(3).
Earth switch:
Earth switches are device which are normally used to earth a
particular system to avoid accident, which may happen due
to induction on account of live adjoining circuits. These don’t
handle any appreciable current at all.
42
Lightning arrestors: station type “lightening arresters”
are provided at the terminals of the transformers for
protection against lightening or any surges developing in the
system, the practice is also to install lightening arresters at
the incoming terminals of the line. Shielding of substation
from direct lightening stroke is provided through earth wires
located at structures
‘peaks’. Recently masts are also used for the purpose of
shielding substation.
Switchgear
• Isolators
• Switching Isolators
• Circuit Breakers
• Load Break Switches
• Earth Switches
44
Earth switches are devices which are normally used to earth
a particular system to avoid accident, which may happen due
to induction on account of live adjoin circuits. These do not
handle any appreciable current at all.
45
Communication
Types of communication in TPP
1. VSAT
2. PLCC
3. VHF
4. VLDC & Operational Communication
5. Inter Communication
Modes of Communication
PLCC
46
Wave Trap:
It is the device used to separate out the high frequency
communication signal from the low frequency power signal.
Wave traps are installed at the exit point of the switchyard.
It consists of an inductor in series with the transmission line
and a capacitor after the inductor in parallel. The series
inductor bypasses the low frequency power signal and blocks
the high frequency communication signal to enter the
switchyard, whereas the parallel capacitor bypasses the high
frequency communication signal and blocks the low frequency
power signal.
This kind of arrangement ensures the
safety of both the communication as well as power
generation syste
47
ASH HANDLING PLANT
A large quantity of ash is, produced in steam power plants
using coal.
Ash produced in about 10 to 20% of the total coal burnt in the
furnace. Handling of ash is a problem because ash coming out
of the furnace is too hot, it is dusty and irritating to handle and
is accompanied by some poisonous gases. It is desirable to
quench the ash before handling due to following reasons:
1. Quenching reduces the temperature of ash.
2. It reduces the corrosive action of ash.
3. Ash forms clinkers by fusing in large lumps and
by quenching clinkers willdisintegrate.
4. Quenching reduces the dust accompanying the ash.
Fly ash is collected with an electrostatic precipitator (ESP)
48
ELECTROSTATIC
PRECIPATATOR
It is a device which captures the dust particles from the
flue gas thereby reducing the chimney emission. Precipitators
function by electrostatically charging the dust particles in the
gas stream. The charged particles are then attracted to and
deposited on plates or other collection devices. When enough
dust has accumulated, the collectors are shaken to dislodge the
dust, causing it to fall with the force of gravity to hoppers
below. The dust is then removed by a conveyor system for
disposal or recycling.
Flue gas
Gas distribution
ELECTROSTATIC PRECIPATATOR
49
Electrostatic precipitation removes particles from the
exhaust gas stream of Boiler combustion process. Six
activities typically take place:
➢ Ionization - Charging of particles
➢ Migration - Transporting the charged particles to the
collecting surfaces
50
➢ Particle Removal - Conveying the particles from the hopper
to a disposal point
MOTOR
A 3-φ induction motor, stator connected 2 or 3φ supply
produces a rotating magnetic field. Speed of rotation is
proportional to the main frequency and inversely proportional
to the no. of pair of poles. Stator can have single layer windings
with each coil side occupying one stator slot. Many type of
stator windings are encountered. 2 most common types are:-
Induction Motor
There are various types and sizes of motors used in the power
stations. These are used for various purposes as prime movers.
Apart from the simple motor used in different areas, these HT
motors used in the various heavy duty equipments. These are
51
FD, ID, PA fans, boiler feed pumps, CW pumps, etc. These
motors have certain special features like cooling, auto starting,
inter locks and control. These are generally squirrel cage
motors. The rotor never rotates at the synchronous speed. Off
load, the induction motor has poor efficiency and power
factor. On load we get an efficiency of 85% and 0.8 power
factor.
Synchronous Motor
52
4) CWP-2000 kW, 6.6 kV, 250 A, p.f.-0.74, 300RPM.This is also
a big motor which needs to pump large quantity of water
thereby reducing its speed.
SAFETY
➢ Control and elimination of Hazard to attain an acceptable level
of Risk is termed as Safety
Common Hazards
53
➢ Outcomes Of Accidents
Contact with hazardous chemicals
Negative Positive
❖ Engineering Methods
❖ Administrative controls
❖ Personal Protective Equipments ( A Second Line of Defence )
❖ Training & Education ( Imparting Morale & Knowledge )
54
Prevention systems for Fire hazards
( At DVC – CTPS )
➢ Fire extinguishers
➢ Co2 flooding system
➢ Water spray system
➢ Nitrogen flooding
➢ Gas flooding system
55
CONCLUSION
56
BIBLIOGRAPHY
• GOOGLE.CO.IN/DVC-CTPS
➢ WEBSITES VISITED :
• WWW.GOOGLE.COM/DVC-CTPS
• WWW.DVC.ORG
• WWW.WIKIPEDIA.COM/DVC-CTPS
57