Project I Nec
Project I Nec
PRACTICE IN NEPAL
Submitted By :
Purna Bhahadur Baduwal (019-071)
Advisor
CHANGUNARAYAN, BHAKTAPUR
(JANUARY,2022)
ACKNOWEDGEMENT
The success and final outcome of this project required a lot of guidance and
assistance from many people and we are extremely privileged to have got this all
along the completion of our project. All that we have done is only due to such
supervision and assistance and we would not forget to thank them. I respect and
thank Mr. Sushil Acharya for providing us an opportunity to do the project work
in Road Construction and procedure practice in Nepal. Its Development in Nepal
and giving us all support and guidance, which made us complete the project duly.
We are extremely thankful for providing such a good guidance. We owe our deep
gratitude to our project supervisor Mr. Sushil Acharya, for guiding us all along,
till the completion of our project work by providing all the necessary information
for developing a good system.
i
TABLE OF CONTENT
ACKNOWEDGEMENT.............................................................................................................................................................i
TABLE OF CONTENT.............................................................................................................................................................ii
LIST OF TABLES....................................................................................................................................................................iv
LIST OF FIGURES....................................................................................................................................................................v
1 INTRODUCTION..........................................................................................................................................................1
1.1 Background..........................................................................................................................................................1
1.2 Objectives.............................................................................................................................................................5
2 LITERATURE REVIEW...............................................................................................................................................6
2.5 Embankment.........................................................................................................................................................8
2.6 Subgrade...............................................................................................................................................................9
3 METHODOLOGY.......................................................................................................................................................14
3.1 Flowchart............................................................................................................................................................14
5 POSSIBLE OUTCOMES.............................................................................................................................................18
ii
6 REFERENCE...............................................................................................................................................................20
iii
LIST OF TABLES
iv
LIST OF FIGURES
v
1 INTRODUCTION
1.1 Background
Roads are an integral part of the transport system. A country's road network should be
efficient in order to maximize economic and social benefit & They play a significant role in
achieving national development and contributing to the overall performance and social
functioning of the community. It is acknowledged that roads enhance mobility, taking people
out of isolation and therefore poverty. An important infrastructure required for development to
take place is indubitably road development. Roads are the arteries of development. The
development of roads has a domino effect on other sectors. In other words, the development of
roads results in the development of other sectors, such as tourism, agriculture, commerce and
industry.
For a developing country like, Nepal, roads play vital roles in lifting up the country’s
economic condition. The history of road construction in Nepal is not long. The road
between Amlekhgunj and Bhimphedi constructed back in and around 1930 A. D. (1986
B. S) can be considered as the first road in Nepal. However, after the political change of
1950 (2007 B. S.) with establishment of democracy, road development was given emphasis
with priority. The road strategies established after
B.S 2007 included:
1
Recently plastic road technology has been experimented in Pokhara on a small stretch of a road. This
should be verified and if desirable, other cities can adopt the technology.
Roads made of recycled plastics are the future of the world. Urban development has made massive
use of plastic materials which are now creating huge environmental threat due to its non-
decomposable nature. Reusing plastic is not an easy task. Not only in Kathmandu but also all around
the globe, it has become a burning problem. Plastic garbage in mega-cities, in rivers and oceans, has
emerged as a big environmental issue.
May be it’s a time we started paying attention to plastic road technology. This is a fact that
we need a good road which are list affected by rain water and water stagnation, have no
stripping with no potholes, strong list cracking and can be constructed in less time and
cheaply. All these properties of such road is in plastic road. Plastic roads are different from
standard roads as the latter are made from asphalt concrete, which consists of mineral
aggregates and asphalt. The technology of plastic roads is relatively new but rapidly growing.
2
The technology was developed by the “Plastic Man” of India, Rajagopalan
Vasudevan, a professor of chemistry at Thiagarajan College of Engineering,
Madurai. He developed the technology in 2002 and first built a plastic road in his
college.
At least 11 states of India have used the technology to build more than 100,000
kilometers of roads. The government of India ordered in November 2015 that all
road developers in the country use waste plastic, along with bituminous mixes, for
road construction.
The most attractive feature of a plastic road for Nepal is its low operating cost and
durability. It is cheaper as it uses recycled, post-consumer plastics than asphalt.
Plastic-bitumen composite roads have better wear resistance than standard asphalt
concrete roads. They do not absorb water and have better flexibility, which results
in less rutting and less need for repair.
Road surfaces remain smooth, need minimal maintenance and absorb sound
better. The use of plastic in road construction reduces the amount of asphalt. This
is beneficial to the environment since asphalt is responsible for 2 per cent of
global carbon emissions.
3
A study report published in a journal of Indian Engineering and Technology in
February 2017 shows that the use of plastic saves Rs 320,000 per kilometer of
road compared to the traditional method. This means if we are to pave road from
Kathmandu to Kerung boarder, which is about 175km, it will save us Rs56
million.
Plastic roads have a hollow space that can be used to (temporarily) store water,
thus preventing flooding during extreme precipitation. The hollow space can also
be used for the transit of cables and pipes, thus preventing excavation damage.
The patch-up process for potholes is very easy as roads can be created as
individual pieces (sections), which can be switched out in case of damage. This is
different from traditional ways of road repair.
1.2 Objectives
4
2 LITERATURE REVIEW
5
There were different highways made. The mid hill highway was started from 2062
B.S. Mahendra Highway is longest highway in Nepal. It links Eastern border with
6
India to Western border with India. The East Pont is at Kakarbhitta. It is also an
Exit point to Northeast India including Darjeeling and Sikkim. The West Point is
at Mahendra Nagar. The Araniko Highway road was built in the 1960s with help
from the Chinese on an older yak track. They also planned to expand the road in
2012, but keeping the route open was made more difficult by landslides from
monsoons. The road became a conduit for a large amount of trade between China
and Nepal, and also for some trade between India and China when it is open.
Postal Highway also called Hulaki Raj Marg runs across the Terai region of
Nepal, from KechanaKawal, Jhapa in the east to Dodhara, Kanchanpur in the
west, cutting across the entire width of the country. It is the Oldest highway in
Nepal constructed by Juddha Shumsher Jung Bahadur Rana & Padma Shumsher
Jung Bahadur Rana to aid transportation and facilitate postal services throughout
the nation. Different roads are constructed more and more in present.
7
The road density per 10000 population and 100 square km of land are 6.68 and
10.4 km respectively in Nepal.
Having a clear description of the methods that will be used to accomplish your
project objectives will make a strong application even more competitive.
Developing a methodology is not only helpful to the funding agency, but also
allows you to definitively address how you expect to use awarded funds to fulfill
your project’s purpose. This publication details the purpose of the methodology as
a part of the proposal narrative and what it should address.
Key Points
Before any construction the roadway must be cleared of all vegetation and
trees including their roots removed.
Cross sections should be taken prior to any excavation works.
All construction works must be carried out in as safe a manner as possible.
Excavated suitable materials should be used when possible in the works.
Provision has to be made for drainage of the temporary and permanent
works.
Soil containing vegetable matter is not suitable as fill material.
Borrow pits should not affect the stability of the road, or any other structure.
2.5 Embankment
Key Points
All fill materials must be free from vegetable matter and the material must
be approved as suitable.
The material should be of an appropriate nature and at a moisture content
that it can be compacted to form a stable layer.
8
Generally, embankments should be constructed in 150 mm compacted
layers parallel to the finished grade of the road.
For each completed layer the density should be checked (One test for each
1,000 square meters) by laboratory personnel. If test results show the
required density is not achieved further compaction is necessary
Any soft areas must be rectified before further material is placed. Each
earthworks layer requires to be approved before the next layer can be
started
2.6 Subgrade
Key Points
Key points
9
The material for sub base and base must be graded, with sufficient fines
that they can be properly compacted. All areas of segregated coarse or fine
material must be corrected, or removed and replaced with complying
material.
Continued checks on materials must be carried out throughout the contract
period. If the materials’ tests indicate changes have occurred the contractor
and the Engineer must be immediately informed.
The moisture content of the material at the time of compaction must be
appropriate to produce a dense compacted layer.
If a pavement layer, does not conform with the thickness or tolerance
required, the layer must be corrected. Once the correction is completed the
area should be rechecked to ensure it conforms to the correct depth, cross
fall and degree of compaction.
Each layer should be tested for compaction (3 tests for each 1000 square
meters). If the test results show that the required density is not achieved,
further compaction must be undertaken.
Each layer of pavement must be shaped, compacted and approved ahead of
the placing of subsequent material.
Key points
10
The entire surface to be primed must be covered evenly. Prior to any
spraying, the nozzles on the spray bar of the distributor should be checked
to ensure that they are all working. Where appropriate the distributor
should be calibrated to ensure the required rate of spray is achieved.
Depending on the nature of the surface to be primed a light application of
water just prior to priming may be beneficial to aid penetration of the
bituminous material.
No bituminous mixtures should be placed until the prime coat has dried.
Tack coat may need to be applied to make the road surface sticky prior to
the bituminous carpeting layer being placed.
No dense bituminous surfacing can occur until both the job mixes formula
and the trial sections have been approved.
Thereafter all asphalt work is required to follow the approved Job Mix
formula and the procedures established by the approved trials.
Each day dense bituminous surfacing is laid, three Marshall specimens
should be prepared and tested (STP 10.9.10.10). Samples to be collected
from either the plant or the laid mat, as directed by the Engineer. Samples
should also be taken each day to determine the mix composition
(Extraction of bitumen test and grading, STP 10.4.72).
All equipment proposed to be used by the Contractor requires to be in
good condition and operated by competent and experienced operatives.
Dense bituminous surfacing must be thoroughly compacted as soon as the
material will support the roller without undue displacement or cracking.
Excess use of water on the roller drums is to be avoid as this cools the
asphalt mat.
The surface of the mixture after compaction must be close and tight, and
free from dragging cracks. Any mixture that is defective should be
removed and replaced with fresh hot material, which should be compacted
immediately.
After final rolling, samples should be cut from areas of bituminous
surfacing for density and thickness measurement at 50m intervals. Where
samples have been taken, fresh material must be placed and thoroughly
compacted.
11
2.9 Concrete Including Reinforcement
Key points
12
at random to ensure all the concrete placed in the Works meets the
specified requirements.
All surfaces must be kept thoroughly wet for 7 days after concrete is
placed. Thereafter the concrete must be watered daily for the following 2
weeks to prevent the concrete drying out.
13
3 METHODOLOGY
3.1 Flowchart
Literature review
Data collection
Data analysis
14
project’s purpose. This publication details the purpose of the methodology as a
part of the proposal narrative and what it should address.
As a part of the proposal narrative, the methodology is where you can clearly
outline how you will use the requested funds to accomplish your project’s
objectives. It is the component in the proposal narrative where you bridge the gap
between the objectives and the eventual outcome. It is also where you demonstrate
your project’s feasibility by detailing your experiences and resources that will be
drawn upon to carry out the project.
Another important issue to keep in mind is that all project needs must be reflected
in the project budget. Having a logical project methodology within a proposal
narrative is a vital part of a complete proposal narrative. Painting a vivid picture
of how a project will be accomplished will not only demonstrate a carefully
planned application, but will also provide the funding agency with evidence of
your capacity
15
to produce the desired results. In other words, submitting an application with a
detailed yet clear project methodology will increase your chances of securing the
funding needed to make your project possible.
Under this we will collect information from daily newspapers, magazine articles,
television news, through books, project proposals etc.
Methodology is simply the means by which we collect and analyze data. Thus,
how we arrive at results is just as important as the results alone. The importance is
associated with not only the validity of the research itself but also the means by
which others can replicate what we've done in the research.
16
4 TIME AND SCHEDULE
4.1Gantt chart
Data collection
Data analysis
Data Collection: For this portion it took two weeks. Here, we collected data in
two ways one is primary and other is secondary method. Under primary we visited
construction site and under secondary we found standard data through books,
articles, newspaper etc.
Data analysis: During the collection of data we started our data analysis so it took
nearby two weeks for the preparation of this portion.
17
5 POSSIBLE OUTCOMES
18
Sustainability planning may require changing the way people think about and
solve transportation problems.
Road development should, therefore, be the top priority of the government. The
government, in close coordination with development planners and other concerned
stakeholders, should formulate development plans in such a way that almost all
the areas of the country are connected with one another. Proper road connectivity
will definitely spur the development of other sectors, thus leading to overall
national development.
19
6 REFERENCE
[1] Report: 20-year Road plan, Nepal Engineering Consultancy Services Center
(NEPECON), 2001.
[3] Source, Newspaper, The Himalayans Times. Source, Newspaper, The Rising
Nepal.
20