Construction Productivity and Rental Rates

This document provides productivity rates for various construction activities in the Philippines, measured in manhours per unit of work. It includes rates for excavation, backfilling, structural works, formworks, carpentry, masonry, equipment rental and more. Excavation by hand ranges from 6-8 manhours per cubic meter depending on material, while machine excavation is generally faster. Formwork installation is around 2-3 manhours per square meter. Concrete works are 5-16 manhours per cubic meter depending on placement method. Equipment rental rates are provided hourly in Philippine pesos.

Uploaded by

Sulpi Casil
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (3 votes)
3K views3 pages

Construction Productivity and Rental Rates

This document provides productivity rates for various construction activities in the Philippines, measured in manhours per unit of work. It includes rates for excavation, backfilling, structural works, formworks, carpentry, masonry, equipment rental and more. Excavation by hand ranges from 6-8 manhours per cubic meter depending on material, while machine excavation is generally faster. Formwork installation is around 2-3 manhours per square meter. Concrete works are 5-16 manhours per cubic meter depending on placement method. Equipment rental rates are provided hourly in Philippine pesos.

Uploaded by

Sulpi Casil
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

CONSTRUCTION PRODUCTIVITY RATE CRANE & CLAMPSHELL

(Philippine Setting) With 8 men & 2 carpenters - 1.07MH/CU.M

STRUCTURAL EXCAVATION ROOFING AND SIDING

Common excavation Roofing

Hand - 6.00MH/CU.M Metallic - 0.97MH/SQ.M


Machine - 0.50MH/CU.M Non-Metallic - 1.51MH/SQ.M
Rock excavation - 8.00MH/CU.M
Hauling of spoils - 1.00MH/CU.M Siding

STRUCTURAL BACKFILL Metallic - 1.29MH/SQ.M


Non-Metallic - 1.51MH/SQ.M
By hand - 5.00MH/CU.M
By machine - 2.00MH/CU.M CONCRETE WORKS

TRENCHING Grade members

By hand - 6.00MH/CU.M Formworks - 2.54MH/SQ.M


By machine - 0.50MH/CU.M Concreting - 8.54MH/CU.M
Rebar - 0.07MH/KG
EXCAVATION – MANUAL Finishing - 0.40MH/SQ.M

Common earth - 8.00MH/CU.M Suspended members


Loam of sand - 1.31MH/CU.M
Clay or heavy soil - 1.64MH/CU.M Formworks - 3.28MH/SQ.M
Rock - 2.63MH/CU.M Concreting - 16.70MH/CU.M
Rebar - 0.08MH/KG
EXCAVATION – MECHANICAL Finishing - 0.80MH/SQ.M
Embedded metal - 0.27MH/KG
Common earth - 6.67MH/CU.M Water proofing - 1.82MH/SQ.M
Rock with jack hammer - 16.67MH/CU.M Joint filler - 0.30MH/LM

BACKFILLING PLACING CONCRETE

Common manual - 0.82MH/CU.M Slab on Fill - 5.00MH/CU.M


Gravel fill manual - 5.00MH/CU.M Slip Form - 25.00MH/CU.M
Floor Finish Unhardened - 1.00MH/CU.M
TRENCHING & BACFILLING OF UNDERGROUND PIPING Concrete finished hardened - 1.43MH/CU.M

USING EXCAVATION MATLS MANUAL FROM: REBAR WORKS

0 – 2m Depth - 1.25MH/LM Ground floor installation - 0.07MH/CU.M


2 – 3m Depth - 1.67MH/LM Upper floor installation - 0.08MH/CU.M
3 – 4m Depth - 2.50MH/LM Fabrication - 0.10MH/CU.M
4 – 5m Depth - 3.33MH/LM Mixing manual - 16.00MH/CU.M
Mixing machine - 1.80MH/CU.M
Placing binder gravel - 0.11MH/CU.M
Escombro backfilling - 0.21MH/CU.M MORE THAN 1.8 CU.M POUR
Spreading, tamping & grading - 0.48MH/SQ.M
Mechanical compaction, plate compaction - 0.06MH/CU.M Chute from truck - 7.00MH/CU.M
Crane & bucket - 14.00MH/CU.M
MANUAL CLEARING & GRUBBING Wheeling - 27.00MH/CU.M
Finishing - 2.80MH/CU.M
Clearing under growth & trees – 12″0.05MH/SQ.M
Clearing under growth & shrubs - 0.03MH/SQ.M FORMWORKS & CARPENTRY WORKS
Disposal of soil - 1.69MH/CU.M
Hauling of soil - 1.00MH/CU.M FORM WORKS INSTALLATION
Gravel fill - 2.07MH/CU.M
Wall on ground - 2.00MH/SQ.M
EXCAVATION Wall above ground - 2.35MH/SQ.M
Beams - 3.08MH/SQ.M
Columns - 2.35MH/SQ.M WINDOWS

Suspended slab Glass - 3.23MH/SQ.M


Louver - 4.63MH/SQ.M
Suspended slab 0 – 18″ - 1.67MH/SQ.M Steel - 32.29MH/SQ.M
Suspended slab 10 – 36″ up - 3.33MH/SQ.M
PARTITIONS
Elevated & shored slab forming
single wall - 2.48MH/SQ.M
Forming only - 8.60MH/SQ.M Wooden wall - 3.44MH/SQ.M
Forming & Shoring - 11.00MH/SQ.M Wooden Louver - 3.44MH/SQ.M
Wood wall & Partition - 0.50MH/SQ.M cyclone Louver - 5.38MH/SQ.M

FORM WORKS FABRICATION PAINTING (3 coats)

Form works fabrication - 1.00MH/SQ.M Equipment - 0.24MH/SF


Pipes - 0.30MH/SF
STRIPPING OF FORMS Miscellaneous - 0.24MH/SF

Wall on ground - 0.25MH/SQ.M STRUCTURAL STEEL WORKS


Wall above 10″ - 1.29MH/SQ.M
Beams - 1.03MH/SQ.M STRUCTURAL STEEL
Columns - 0.85MH/SQ.M
Fabrication
Suspended slab Light - 110-130MH/MT
Heavy - 60-90MH/MT
Suspended slab 0 – 18″ - 0.83MH/SQ.M
Suspended slab 10 – 36″ up - 1.08MH/SQ.M Erecting
Light - 70-100MH/MT
Elevated & shored slab Heavy - 40-60MH/MT

forming – strip of forms - 3.50MH/SQ.M WELDING


Floor slab at grade – strip of forms - 2.80MH/SQ.M (One pass only )1- Welder and 1- Helper (16 total MH )40-
50LF/day
INSTALLATION OF CARPENTRY WORKS
STRUCTURAL STEEL
Plywood partition - 1.00MH/B.F.
Flooring and Siding - 0.14MH/B.F. Fabrication
Ceiling & framework - 0.36MH/B.F.
Siding framework - 0.27MH/B.F. Heavy weight - 50-90MH/MT
Flooring framing - 0.97MH/B.F. Light weight - 100-125MH/MT
Wooden post erecting - 0.43MH/B.F. Grating 1 1/4″ x 3/16″ - 3.0 – 3.5MH/SF
Truss Fabrication - 0.35MH/B.F. Star threat grating - 4.0 – 5.0MH/SF
Truss Installation - 0.80MH/B.F.
Girt Installation - 0.21MH/B.F. Erecting
Plates Installation - 0.13MH/B.F.
Purlins Installation - 0.27MH/B.F. Heavy Structural teel - 30 – 60MH/MT
Fascia board Installation - 0.46MH/B.F. Light Structural steel - 60- 90MH/MT
Stacks (Inc. full welding) - 250 – 300MH/MT
1/4″ or 3/4″ THK. Plywood Tanks (Inc. full welding) - 200 – 275MH/MT

Cutting by manual - 1.00MH/SQ.M FINISHING AND MASONRY WORKS


Assembly - 0.42MH/SQ.M
CONCRETE HOLLOW BLOCK / CONCRETE MASONRY UNIT
ARCHITECTURAL SPECIALTIES
4” CHB
DOORS
Laying - 8.0 – 10 SQ.M/day
Wooden - 2.37MH/SQ.M Tooling - 11 – 14 SQ.M/day
Steel - 7.64MH/SQ.M Plastering - 8.0 – 10 SQ.M/day
Aluminum - 8.07MH/SQ.M
Cyclone wire - 7.64MH/SQ.M 6” CHB
Laying - 7.0 – 9.0 SQ.M/day
Tooling - 11 – 14 SQ.M/day
Plastering - 8.0 – 10 SQ.M/day

8” CHB

Laying - 6.0 – 8.0 SQ.M/day


Tooling - 11 – 14 SQ.M/day
Plastering - 8.0 – 10 SQ.M/day

EQUIPMENT RENTAL RATES


(in Philippine Peso, PHP)

Dump truck (8-12CU.M) – 1650-2100/HR


Backhoe/Breaker (1.5CU.M) – 4110-5240/HR
Wheel loader (2-3CU.M) – 2810-4200/HR
Cargo truck (5-8MT) – 1230-1460/HR
Cargo truck (10-15MT) – 1550-1910/HR
Transit mixer truck (5-8CU.M) – 1830-2430/HR
Crawler Dozer (125kW) – 3220-4850/HR
Crawler Crane (21-25MT) – 2780-3560/HR
Vibratory drum Roller (10-14MT) – 2700-3150/HR
Boom truck (6-10MT) – 1450-1760/HR
Boom truck (12-15MT) – 1860-2450/HR
Bagger mixer (1-2bag) – 480-696/HR
Concrete vibrator – 402-471/HR
Air compressor (small) – 347-419/HR
Air compressor (big) – 677-818/HR
Bar cutter – 292-321/HR
Bar bender – 384-422/HR
Jack hammer – 309-340/HR
Tamping rammer – 297-331/HR
Welding machine, portable (300A) – 662-702/HR
Welding machine (600A) – 831-1038/HR
Generator set (15-25kVA) – 452-581/HR
Generator set (50kVA) – 809-977/HR
Sump pump (0.75-2HP) – 199-228/HR
Sump pump (5HP) – 397-456/HR
Road paint stripper – 181-192/HR
Road paint applicator – 470-603/HR

LEGEND:
MH – MANHOUR
SQ.M. – SQUARE METER (m2)
CU.M. – CUBIC METER (m3)
B.F. – BOARD FOOT (bdft)
LM – LINEAR METER (lm)
LF – LINEAR FOOT (lft)
SF – SQUARE FOOT (sqft)
KG – KILOGRAM (kg)
HR – HOUR (hr)