Method Statement For Dewatering
Method Statement For Dewatering
: 00
Doc. No.: STC CPBP-SITE-MS-0005 Date Issued: 16 JUNE, 2019
`
STC CAR PARK BUILDING PROJECT
Riyadh, K.S.A.
METHOD STATEMENT FOR
DEWATERING WORKS
0
16 JUNE, 2019
0
0
1
0 METHOD
2 STATEMENT FOR
0 DEWATERING
3 WORKS
04
PROJECT
MANAGER
RNZ
TAYYAB ABDUL SYED ATHER ULLAH
KHALID
00 16 JUNE, 2019 DEWATERING WORKS GHAFOOR HUSSAINI
MKHTALI
Table of Content
5. Work Procedure
o The Pump shall be connected to well points placed at 1.5-meter centers with
sufficient depth to ensure that lowering of the water table shall be carried out
from a level not less than 1 meter below the excavation bottom.
o Pre-digging will be carried out prior to installation of the well point, followed
by excavator, to remove the lose material from the bottom of the mini wells.
o Provide extra pump encase of breakdown may happen, it can be replaced
immediately and without interruption of dewatering.
Page | 3
Doc. Name: METHOD STATEMNT FOR DEWATERING WORKS Rev. No.: 00
Doc. No.: STC CPBP-SITE-MS-0005 Date Issued: 16 JUNE, 2019
o A filter media of 3/16 inches (3 – 5 mm) screened black sand shall be inserted
around the 3/4 depth of the wells to act as barrier against fines and prevent
choking of well points.
o Operate the dewatering system continuously 24 hours a day until drain and
structures have been constructed to fill material and until written by
authorization to cease dewatering.
o Pump will be connected to discharge pipe to running over land to the approved
area by authority’s jurisdiction.
o Dispose the water removed in a manner to avoid endangering public health,
environment, and neighboring property.
o For safety purpose, provide safety barrier along the perimeter of the excavated
area to prevent fall hazards.
Page | 4